YOU STARTED FIVE WEEKS LATE. YOU FINISH ON THE ORIGINAL DAY.
Drywall comes after MEP rough-in and before finishes. Every upstream trade that takes longer than planned pushes your start. Nobody moves your completion. So a nine week window becomes six, and you buy back the missing three weeks with premium labor.
On a $240,000 hang and finish package, a five week mobilization slip against a fixed completion date compresses a nine week window to six. Buying back three weeks of production costs about $10,980 in premium hours and second crew learning curve. Drywall subs at $1M to $5M average 19 percent gross. So that job held $45,600 of gross profit, and the compression took 24 percent of it. The job closed at 14.4 percent. The delay was upstream and the cost was yours.
Your crews did not slow down, and nothing here is a production failure. The calendar moved on one end only, and the trade in the middle paid for it.
This post covers one schedule mechanic and what it costs. That page covers the three places drywall margin goes and how the trade is managed month to month. Read CFO for Drywall Contractors for the complete treatment, worked figures included.
WHY DOES DRYWALL ALWAYS START LATE?
Because you cannot hang board over rough-in that has not passed inspection. Framing has to be complete, mechanical, electrical and plumbing all have to be roughed and signed off, and insulation has to be in. That is four trades and at least two inspections in front of you, and every one of them owns part of your start date.
None of them owns your finish date. Finishes do. Paint, flooring, casework and ceilings are all waiting on your board, and the certificate of occupancy is waiting on them. So the back end of the schedule is defended by everybody and the front end is defended by nobody.
So a drywall subcontractor has the most trades ahead of it and the least float behind it. That comes from where drywall falls in the schedule, and a better crew won't change it.
WHAT A FIVE WEEK SLIP DOES TO NINE WEEKS.
Take a $240,000 hang and finish package bid at nine weeks. Labor is about 55 percent of that contract, or $132,000. The production plan assumes one crew working straight time.
MEP rough-in takes three weeks longer than planned and the inspector needs another two for a re-inspection. You mobilize five weeks late. The finish trades are already sequenced and the owner has a lease commitment, so completion does not move. Nine weeks of work now has six weeks of calendar.
There are only two ways to buy back three weeks. Work longer days, or add people. Both cost more per unit of production than the bid assumed, and neither is a change order unless somebody wrote one.
WHERE THE $10,980 ENDS UP.
Saturdays and ten hour days first. Say 320 premium hours across the crew at a $19 per hour differential once burden is on it. That is $6,080, and it is the visible half.
The second half is harder to see. Adding a crew to a job already in motion means two weeks of somebody learning a board layout, a stocking route and a GC's punch standard that the first crew already knows. Call it $4,900 of production that got paid for and did not get installed.
Together that is $10,980. The job held $45,600 of gross profit at drywall's 19 percent, so the compression took 24 percent of the job's profit and closed it at 14.4 percent gross. Your bid was fine. Your calendar was not.
MOST SUBS MISS THIS: THE CLOCK STARTED WITHOUT YOU.
Here is the part that costs money on the next twelve jobs. The overtime is booked to your labor cost code, so the job cost report says drywall labor is over budget. It doesn't say why. The window was cut by a third, and the report reads cost codes. A cost code has no calendar in it.
So the review meeting goes looking for a production problem. Are the crews too slow. Should we be piece rating the hang. Is the foreman managing the stock properly. Every one of those questions is fair and every one of them is aimed at the wrong number.
The number that moved was days available, and nobody tracked it. If you take one thing from this post, put two dates in your job setup: contracted mobilization date and actual mobilization date. The difference in days is the best predictor of whether that job will overrun labor. You have it before you hang a sheet.
THE FOUR LINES THAT MAKE IT BILLABLE.
You don't have to renegotiate a contract. You need four things in writing up front, and one email on the day the slip happens.
1. A contracted mobilization date in the subcontract, next to the completion date. A completion date with no start date is a duration you never agreed to.
2. A clause saying that if mobilization is delayed and completion is unchanged, the compressed duration is a change in the work and premium time is compensable.
3. A notice email on the day you learn the start moved. It states the new available duration and the premium cost of holding the original completion. Send it before the overtime starts.
4. A separate cost code for schedule acceleration. The premium hours go there, apart from base labor, and the review meeting can see them.
WHAT THIS IS WORTH ACROSS A YEAR.
One job at $10,980 is a bad month. Repetition is the problem. A drywall sub with $2.5M spread across eight to twelve packages a year, with half of them compressed to some degree, has $40,000 to $60,000 of unbilled acceleration.
Drywall at $1M to $5M averages 6 percent net before taxes against a 10 percent target, four points below where it should be. On $2.5M that distance is $100,000, and unbilled acceleration is a large piece of it.
The fix is a start date in the contract and an email on the day it moves. A bigger crew or a harder foreman leaves the problem where it is.