CFOS, coming January 2027Join testing: 90 days free
BLOG · CASH FLOW

YOU FUND THREE THINGS. BILLING COMES FOURTH.

Most cash flow advice for subcontractors starts at the invoice. In fiber the money has already left three times by then. One of those prices tripled in five years, and nobody renegotiated the terms around it.

BY JOSH LUEBKERPublished August 25, 2026Updated November 14, 20265 min read
QUICK ANSWER

A fiber subcontractor funds three separate things before an invoice exists. Make-ready gets paid up front at a price the pole owner sets. Compliance on publicly funded work (the certificates, the certified payroll and the mapping deliverables) gets paid for months ahead of the revenue it belongs to. Then the closeout audit holds the last payment until the as-builts clear. Fiber subs at $1M to $5M have 22 percent gross and 7 percent net before taxes. That thin number feels worse than it reads because all three outflows are paid before a single dollar comes back.

This is how carrier and publicly funded fiber work is bought. It's why a fiber sub with a full schedule ends up borrowing money that costs 30 percent a year. The fix is knowing which week each outflow comes due, and that's a forecasting job.

THE FULL BREAKDOWN

This post covers the money that leaves before you bill. That page covers the 75 to 90 days after you do. Read Fiber Subcontractor Cash Flow for the complete treatment, worked figures included.

WHAT IS MAKE-READY, AND WHY DOES IT COST YOU FIRST?

You sign a carrier master service agreement to place 40,000 feet of aerial fiber. Good unit pricing, a route you've built before, crews you trust. Then the pole owner sends the make-ready estimate, which is the work the utility has to do to its own poles before your strand can attach. Transferring somebody else's cable down a foot. Replacing a pole that can't support another attachment. You don't do that work, you don't price that work, and you pay for it up front.

That's the first outflow, and it's the one that moved. Make-ready has risen roughly 300 percent over five years on outside-plant work. The unit prices in your MSA did not move 300 percent. So a route that penciled at a reasonable margin three years ago now comes with a large up-front payment to a third party who has no reason to hurry, on a schedule you don't control.

Both of those are cash problems. You've spent real money before a crew is on site, so there's nothing to bill against it yet. And the pole owner's calendar sets when your crews can start. The money can stay out for weeks while your splicers are on payroll waiting for a route to open.

THE SECOND OUTFLOW IS PAPERWORK ON PUBLICLY FUNDED WORK.

The $42.45 billion BEAD program reached its deployment stride in 2026, and for a lot of fiber subs that's the best backlog they've ever seen. It also adds a compliance load you fund before the revenue clears.

Certificates of insurance at limits above your normal book. Certified payroll every week, so somebody in the office is producing reports while receivables wait. Mapping and GIS deliverables built as the work goes in. You pay for each of those in the month it happens. The revenue clears an approval cycle later.

Estimating misses this outflow because it doesn't look like construction cost. It looks like overhead. So it goes into an overhead rate that was set before the funded work existed, and the bid recovers a fraction of what the compliance really costs.

THE THIRD OUTFLOW IS THE ONE THAT HOLDS YOUR LAST PAYMENT.

In fiber, the paperwork is the last mile of the job. Carrier and publicly funded contracts both hold payment until the as-built documentation and closeout pass audit. That means what got placed, where it got placed, what it's spliced to, and mapping to a standard somebody else wrote.

The physical work is finished. The crews are on the next route. The final payment, often the piece that holds the job's whole profit, waits on a document package. Nobody is assigned to finish it, because everybody who could is producing revenue somewhere else.

So the third outflow is the cost of holding a completed job. You've paid for everything. The customer has what they bought. And the money is waiting on a deliverable that costs a fraction of the payment it's holding.

MOST SUBS MISS THIS: FACTORING IS A SYMPTOM.

One of the search terms fiber contractors bring to this site is fiber contractor factoring. Somebody typed that. It's a business with a full schedule going to look for money that costs 20 to 30 percent a year.

Factoring isn't stupid. Sometimes it's the only thing available on a Tuesday when payroll is Friday. But it's expensive money bought to solve a timing problem the contract created. Three outflows come before billing. The closeout holds the last payment. And the business fills the hole with the most costly money it can find.

Here's what to do. Before you price factoring, price the three outflows. Total the make-ready you've paid on jobs that haven't billed yet. Total the compliance labor you've paid for on funded work. Total the value of completed jobs held behind an as-built package. That number is what you're financing. In most fiber shops it's larger than the shortfall that sent you looking for a factor.

WHAT THE NUMBERS SAY ABOUT THE ROOM YOU HAVE.

Fiber subcontractors between $1M and $5M have about 22 percent gross margin and 7 percent net before taxes. The CFOS target at that revenue is 24.5 percent gross and 10.5 percent net before taxes. Getting there starts with the three outflows above. It also takes collections: most fiber subs collect in 75 to 90 days, and 45 is achievable.

Two and a half points of gross margin on a $3M fiber sub is $75,000 a year. You won't get it by bidding higher on a carrier MSA where the unit prices are set. You get it three ways. Bill make-ready through as the pass-through it is. Put the compliance cost into the overhead rate. And assign the as-built package to somebody before the crew leaves the route.

THE ONE THING TO DO THIS WEEK.

Make a list of every job where you've spent money and can't bill for it yet. Put a date beside each one for when it becomes billable. Make-ready paid, crews idle waiting on a pole owner, compliance produced, as-builts outstanding. One page, a column of dollars and a column of dates.

That page is a thirteen week cash forecast in its simplest form. For a fiber sub it usually explains the whole problem in about twenty minutes. You'll see which week comes up short before it gets there. Then you can plan a draw ahead of time and skip taking whatever money answers the phone.

WHAT TO DO WITH THIS

THE SHORT LIST.

Total the make-ready you've paid on routes that haven't billed. That figure is working capital you're financing for a third party on their schedule.
Put the funded-work compliance cost (the certificates, the certified payroll and the mapping) into your overhead rate. If you set that rate before you took BEAD work, it recovers a fraction of what compliance costs.
Assign the as-built package to a person with a date before the crew leaves the route, because the last payment is usually the job's profit.
Price the three outflows before you price a factor. The total you're holding is normally bigger than the shortfall that sent you looking.
COMMON QUESTIONS

FREQUENTLY ASKED.

It's the pole owner's work on the pole owner's asset, and utilities collect for it up front. You're paying a third party to make room for your strand, at a price they set, on a calendar they control. It has risen roughly 300 percent over five years on outside-plant work. Carrier unit pricing hasn't moved anywhere near that. So a route that priced well three years ago can send a large payment out the door before a crew sets foot on site. Bill it as a pass-through, show the cash timing, and forecast the week it leaves.

The as-built and closeout package. Carrier and publicly funded contracts both hold payment for documentation: what was placed, where, what it's spliced to, and mapping to the standard in the contract. The work can be finished and accepted in the field while the last payment waits on the paperwork. It's the cheapest thing on the job to produce, and it holds the biggest piece of the money. Give it an owner and a date. Otherwise it goes to whoever has a slow week.

It's a real tool, and sometimes it's the only one available before payroll. It costs something like 20 to 30 percent a year. That's expensive for a timing problem the contract created. Before you price a factor, total the make-ready paid on unbilled routes, the compliance labor on funded work, and the completed jobs held behind as-builts. In most fiber shops that total is larger than the shortfall, and you can collect it without borrowing.
WHAT THIS TIES INTO
Josh Luebker, SPM The Construction CFO
Josh Luebker
FRACTIONAL CFO · SPM THE CONSTRUCTION CFO

Josh Luebker is a master electrician turned construction CFO, president of SPM The Construction CFO and author of CONTROL: C.F.O.S. Construction Financial Operating System.

Josh Luebker is the author of CONTROL. Within 48 hours of its October 1, 2026 release the book ranked on Amazon: #1 in Construction Industry, #1 in Home Improvement Estimating, #9 in Financial Accounting. Captured October 2, 2026 at 8:03 PM Central.

WHICH WEEK ARE YOU SHORT?

Josh Luebker is a fractional CFO for commercial subcontractors at constructioncfo.net. The call is twenty minutes of questions about your unbilled routes, your aging and which week tends to come up short. Josh won't sell you anything and he won't propose anything.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute call

20 minutes. No pitch or proposal. Josh asks questions to find out if he can help.

OR GET THE SOV AND PAY APPLICATION TEMPLATE. NO CALL NEEDED.