ALLOWANCE SAID $18,000. FIXTURES CAME TO $27,400.
A fixture allowance is a revenue number you don't control against a cost number the owner controls. Written as one lump sum it becomes unenforceable, and the overrun surfaces at trim-out as a material variance with your buying department written across it.
On a $310,000 plumbing rough and trim, a $18,000 lump fixture allowance against $27,400 of owner-selected fixtures is a $9,400 overrun. Plumbing subs at $1M to $5M average 25 percent gross, so that job had $77,500 of gross profit. The overrun took 12 percent of it and dropped the job to 22 percent. You can't recover it, because a lump allowance gives you nothing to compare one selection against. Itemize the same $18,000 by fixture, and the freestanding tub at $4,200 against its $1,400 line is a $2,800 change order signed the day it's chosen.
Your buyer and your supply house did nothing wrong. The contract gave away the only document that could have priced a substitution.
This post covers one contract line and what it does to a job cost report. That page covers the three things plumbing margin is lost to and how the trade operates. Read CFO for Plumbing Contractors for the complete treatment, worked figures included.
WHY DOES A FIXTURE ALLOWANCE EXIST AT ALL?
On a custom residence or a high-end tenant fit-out, nobody has picked the fixtures when the plumbing goes out to bid. Rough-in is fully designed and the fixture schedule says by owner. The plumber still has to put a number in the bid for tubs, toilets, lavatories, shower systems, basins and trim.
So an allowance goes in. The owner gets a budget to shop against and the plumber gets a line to buy against. Both sign it knowing somebody who wasn't in the meeting will pick the fixtures later.
That part is fine. The trouble is how the allowance gets written. There are two ways to write it, and eight months later they work out very differently.
THE LUMP SUM, AND WHAT IT COSTS.
One line: fixture allowance, $18,000. Clean, fast, everyone signs. Now trim-out comes around on a $310,000 job and here's what the owner picked. A freestanding tub at $4,200, where the plumber's internal line was $1,400. A thermostatic shower system with three outlets at $2,800, where the line was $900. Two vanity sets and a pot filler over their lines by $1,900 between them.
Fixtures deliver at $27,400 against an $18,000 allowance. That's $9,400 over. Plumbing subs at $1M to $5M average 25 percent gross, so a $310,000 job holds $77,500 of gross profit, and the overrun took 12 percent of it. The job closes at 22 percent gross.
Now try to bill it. You have one allowance number and one delivered number, and the difference is $9,400. The GC asks which selection caused it. The honest answer is all of them, some a little. You can't prove any one of them, so the credit request dies in a meeting.
WHAT YOUR JOB COST REPORT SAYS ABOUT IT.
This part costs you money on the next job. The job cost report shows plumbing materials over budget by $9,400. It doesn't say fixture selections over allowance by $9,400. The report reads the cost code, and most plumbing subs book fixtures inside materials with copper, PVC, carriers and trim.
So the review meeting looks for a buying problem. Are we getting the best price on copper. Should we buy direct. Is the supply house holding us to list. Every question is fair, and every one is about the wrong number.
Then the same thing happens on the next custom job, because the contract and the cost code are the same. Two or three jobs in, a plumbing sub starts to believe his buying is uncompetitive. What he really has is a contract that turns somebody else's taste into his variance.
MOST SUBS MISS THIS: AN ALLOWANCE IS A DOCUMENT BEFORE IT IS A BUDGET.
You itemize an allowance so you can prove a substitution. Your fixture guesses will be wrong either way, and that's fine. An allowance was never a prediction. It's the baseline you price a change from.
Itemized, the same $18,000 reads: tub $1,400, toilets $1,100, lavatories $1,600, shower system $900, and so on down the schedule. The owner picks a $4,200 tub. That's a $2,800 change order, priced from a line both parties signed. You submit it the day the selection is made, and it's approved before anybody orders anything.
Screenshot this for whoever writes your contracts. If you can't compare a single selection against the allowance, the allowance caps your revenue and puts no limit on your cost.
THE THREE THINGS TO PUT IN THE CONTRACT.
First, itemize the allowance by fixture type with a quantity and a unit price, and attach it as an exhibit. It takes an estimator twenty minutes, because he already built it that way to get to the $18,000. The breakdown just moves from his file into the contract.
Second, a selection deadline tied to the schedule, with a stated consequence. Selections are due four weeks before trim-out. After that the plumber's specified fixture gets ordered, and a change order covers any switch. Without a deadline, the owner's indecision becomes your schedule problem and your storage problem.
Third, a substitution clause that prices the difference both ways. If the owner picks below the line, credit it. Plumbers push back on that because it feels like giving money back. It's the clause that makes the other two enforceable. A GC will strike a one-way allowance as a markup grab.
THE ONE THING TO DO THIS WEEK.
Split fixtures out of your materials cost code. Use one code for pipe, fittings and carriers and one for fixtures and trim. The fixture allowance is the budget on the fixture code. Then the next overrun shows on the report the month it happens.
Then pull the last two custom jobs you closed and total the fixture invoices against the allowance in the contract. If the difference is more than a point of gross margin, fix the contract template. Buying harder won't change it.
