CONSTRUCTION SCHEDULE OF VALUES — GUIDE AND TEMPLATE.
A schedule of values is not your estimate. It is the contractually agreed breakdown of your lump sum contract into line items — each with a weighting that controls how much you can bill at each stage. You bill percent complete by individual line item, not by overall project completion. Material lines are weighted at cost plus overhead plus profit plus 5%. General Conditions is a time-based monthly cost, weighted the same as material. Labor lines are weighted at exact cost and sequenced in build order. This structure is for private lump sum work only — it does not apply to public work or unit price contracts.
The SOV gets attached to your contract before signing with agreed-upon values filled in. Not blank — with numbers. The GC signs knowing exactly what mobilization costs, what each month of General Conditions costs, and what each material and labor phase is worth. That signed document is your billing authority for the life of the project — and your leverage on every change order that extends the schedule.
Attach to the contract before signing with dollar values agreed and filled in. Bill percent complete by individual line item — not overall project completion.
Color key: Orange = Mobilization · Blue = General Conditions and Permits (time and pass-through costs) · White = Material (cost + OH&P + 5%) · Grey = Labor (exact cost, build sequence order)
| ITEM | DESCRIPTION | SCHED VALUE | WEIGHT |
|---|---|---|---|
| 1.00 | Mobilization | $ — | 0.09000 |
| 2.00 | Permits and Inspections | $ — | 0.01489 |
| 3.00 | General Conditions — 6 Months (Equipment, PM & Superintendent) | $ — | 0.07500 |
| MATERIAL — COST + OH&P + 5% | |||
| 4.00 | Material — Switchgear and Main Distribution Gear | $ — | 0.11000 |
| 5.00 | Material — Underground PVC Conduit and Fittings | $ — | 0.04500 |
| 6.00 | Material — Rough-In Conduit, Wire, and Fittings | $ — | 0.07000 |
| 7.00 | Material — Devices, Panels, and Branch Circuit | $ — | 0.05000 |
| 8.00 | Material — Lighting Fixtures and Controls | $ — | 0.05500 |
| 9.00 | Material — Low Voltage and Specialty | $ — | 0.02000 |
| LABOR — EXACT COST · SEQUENCED BY BUILD ORDER | |||
| 10.00 | Labor — Underground Conduit and Rough-In | $ — | 0.10000 |
| 11.00 | Labor — Above-Slab Rough-In Floor 1 | $ — | 0.08000 |
| 12.00 | Labor — Above-Slab Rough-In Floor 2 | $ — | 0.07000 |
| 13.00 | Labor — Above-Slab Rough-In Floor 3 | $ — | 0.05000 |
| 14.00 | Labor — Panel Setting and Gear Installation | $ — | 0.06000 |
| 15.00 | Labor — Devices, Trim, and Fixtures | $ — | 0.05511 |
| 16.00 | Labor — Low Voltage and Fire Alarm | $ — | 0.03000 |
| 17.00 | Labor — Start-Up, Testing, and Punch | $ — | 0.02500 |
| TOTAL CONTRACT VALUE | $ — | 1.00000 | |
| ITEM | DESCRIPTION | SCHED VALUE | WEIGHT |
|---|---|---|---|
| 1.00 | Mobilization | $ — | 0.08000 |
| 2.00 | Permits and Inspections | $ — | 0.01489 |
| 3.00 | General Conditions — 5 Months (Equipment, PM & Superintendent) | $ — | 0.07000 |
| MATERIAL — COST + OH&P + 5% | |||
| 4.00 | Material — Storm Drainage Pipe and Structures | $ — | 0.07000 |
| 5.00 | Material — Sanitary Sewer Pipe and Manholes | $ — | 0.06000 |
| 6.00 | Material — Water Main Pipe and Appurtenances | $ — | 0.05500 |
| 7.00 | Material — Sub-Base and Base Aggregate | $ — | 0.07000 |
| 8.00 | Material — Asphalt — Base and Surface Course | $ — | 0.08000 |
| 9.00 | Material — Concrete — Curb, Gutter, and Flatwork | $ — | 0.04500 |
| 10.00 | Material — Erosion Control and SWPPP Supplies | $ — | 0.01500 |
| LABOR — EXACT COST · SEQUENCED BY BUILD ORDER | |||
| 11.00 | Labor — Site Clearing and Demolition | $ — | 0.03000 |
| 12.00 | Labor — Mass Grading — Cut and Fill | $ — | 0.10511 |
| 13.00 | Labor — Storm Drainage Installation | $ — | 0.07000 |
| 14.00 | Labor — Sanitary Sewer Installation | $ — | 0.06500 |
| 15.00 | Labor — Water Main Installation | $ — | 0.06000 |
| 16.00 | Labor — Sub-Base Placement and Compaction | $ — | 0.04000 |
| 17.00 | Labor — Asphalt Paving | $ — | 0.04000 |
| 18.00 | Labor — Concrete Curb, Gutter, and Flatwork | $ — | 0.03000 |
| TOTAL CONTRACT VALUE | $ — | 1.00000 | |
| ITEM | DESCRIPTION | SCHED VALUE | WEIGHT |
|---|---|---|---|
| 1.00 | Mobilization | $ — | 0.09000 |
| 2.00 | Permits and Layout Survey | $ — | 0.01489 |
| 3.00 | General Conditions — 4 Months (Equipment, PM & Superintendent) | $ — | 0.06500 |
| MATERIAL — COST + OH&P + 5% | |||
| 4.00 | Material — Rebar and Reinforcing Steel | $ — | 0.07000 |
| 5.00 | Material — Concrete — Footings and Walls | $ — | 0.06000 |
| 6.00 | Material — Concrete — Slabs and Elevated Decks | $ — | 0.05500 |
| 7.00 | Material — Forming Lumber and Hardware | $ — | 0.03500 |
| 8.00 | Material — Embed Plates, Anchors, and Sleeves | $ — | 0.02000 |
| 9.00 | Material — Vapor Barrier and Curing Supplies | $ — | 0.01000 |
| LABOR — EXACT COST · SEQUENCED BY BUILD ORDER | |||
| 10.00 | Labor — Excavation and Subgrade Preparation | $ — | 0.07000 |
| 11.00 | Labor — Footing — Form, Rebar, Pour, Strip | $ — | 0.13511 |
| 12.00 | Labor — Foundation Walls — Form, Pour, Strip | $ — | 0.14000 |
| 13.00 | Labor — Slab on Grade — Base, Vapor, Pour, Finish | $ — | 0.12000 |
| 14.00 | Labor — Elevated Slabs — Shore, Deck, Pour, Strip | $ — | 0.08000 |
| 15.00 | Labor — Patching, Grinding, and Punch | $ — | 0.03500 |
| TOTAL CONTRACT VALUE | $ — | 1.00000 | |
| ITEM | DESCRIPTION | SCHED VALUE | WEIGHT |
|---|---|---|---|
| 1.00 | Mobilization | $ — | 0.10000 |
| 2.00 | SWPPP Plan Preparation and Permits | $ — | 0.01489 |
| 3.00 | General Conditions — 6 Months (Equipment, PM & Superintendent) | $ — | 0.06500 |
| MATERIAL — COST + OH&P + 5% | |||
| 4.00 | Material — Silt Fence and Filter Fabric | $ — | 0.05500 |
| 5.00 | Material — Inlet Protection and Rock Bags | $ — | 0.04000 |
| 6.00 | Material — Erosion Control Blanket and Matting | $ — | 0.06000 |
| 7.00 | Material — Seed, Fertilizer, and Mulch | $ — | 0.06000 |
| 8.00 | Material — Sediment Basin Liner and Riser | $ — | 0.05000 |
| LABOR — EXACT COST · SEQUENCED BY BUILD ORDER | |||
| 9.00 | Labor — Perimeter Silt Fence Installation | $ — | 0.09511 |
| 10.00 | Labor — Inlet Protection Installation | $ — | 0.07000 |
| 11.00 | Labor — Sediment Basin or Trap Construction | $ — | 0.13000 |
| 12.00 | Labor — Slope Protection and Blanket Installation | $ — | 0.10000 |
| 13.00 | Labor — Seeding, Mulching, and Stabilization | $ — | 0.11000 |
| 14.00 | Labor — Monthly BMP Inspection and Maintenance | $ — | 0.05000 |
| TOTAL CONTRACT VALUE | $ — | 1.00000 | |
FOUR LINE TYPES. FOUR DIFFERENT WEIGHTING RULES.
Front-Loaded Cash Before Work Begins
Covers equipment mobilization, initial material procurement deposits, site setup, and the first period of superintendent time before production billing starts. Target 8–10% minimum. Negotiate hard — document the cost breakdown so the GC can approve it. Even 5% on a $600K contract is $30,000 in the bank at project start. Mobilization is the single highest-leverage line on the SOV.
Fixed Rate — Not Rounded
Permits and inspections is a pass-through cost with a specific, documented value. It is not 1.5% or 2% — it is the actual permit cost divided by the contract value, expressed to five decimal places. On a $480K electrical contract, if permits cost $7,147, the weight is 7,147 ÷ 480,000 = 0.01489. This line bills in full on permit issuance. Do not round it. The precision signals that you know exactly what permits cost and you are billing exactly that.
Time-Based Cost — Billed Monthly on Schedule
General Conditions covers every cost that runs on the clock regardless of production: equipment on site, superintendent salary, PM time, fuel, trailers, temporary facilities, phones, and site utilities. Calculate it like material — actual monthly cost times the number of contract months, plus overhead and profit, plus 5%. Divide by contract value to get the weight. Then bill 1/X of that weight every month on schedule. Rain month, slow month, disputed change order month — General Conditions bills in full. You did not choose the schedule or the season. Equipment sitting on a rained-out site costs the same as equipment working. Label the line as "General Conditions — X Months" so the GC understands it is schedule-driven from day one. When they extend the project a month, the change order is not a negotiation — it is the monthly rate already in the signed contract times one additional month. They knew the cost when they signed.
Separated by Type — Billed When On Site
Every material type gets its own line — switchgear is not conduit is not devices. Each line is weighted at its marked-up value: material cost plus overhead and profit plus an additional 5% for procurement, storage, and handling. This front-loads the billing — you recover material cost and markup before the labor phase that installs it even begins. Negotiate stored materials billing language into the contract so material can be billed on site before installation when lead times are long.
Weighted at Exact Cost — Ordered How You Build
Labor phase lines are weighted at their exact cost as a fraction of total contract value — no additional markup. The markup is captured in the material lines and in the overall contract price. Labor lines must be sequenced in build order — the order your crews actually execute the work. Underground before above-slab. Floor 1 before Floor 2 before Floor 3. Footings before walls before slabs. The sequence is not alphabetical, not by cost, not by spec section — it is the physical order of construction. Billing follows the build, and the build follows the sequence.
WHAT EVERY SOV MUST DO — AND MUST NEVER DO.
FREQUENTLY ASKED.
IS YOUR NEXT CONTRACT SOV ATTACHED AND SIGNED BEFORE MOBILIZATION?
If the SOV is blank at signing, you have no billing authority and no change order leverage. A 30-minute diagnostic will show you what your current billing structure is costing you.
BOOK A FREE 30-MIN DIAGNOSTIC →30 minutes. Free. No sales pressure.
OR SEE YOUR NUMBERS FIRST → FREE CEO REPORT TOOL