TWO UNITS BILL $8,400 EACH. ONE COSTS 12 TIMES THE OTHER.
A full maintenance contract is priced like an insurance policy. You set the rate and you take on the risk. If every unit in the book has the same rate, the young equipment pays for the old, and nobody can see which is which.
A 90 unit elevator maintenance book at $700 per unit per month is $756,000 a year and holds about $204,000 of gross profit at the trade's 27 percent. Callback frequency varies by a factor of ten across unit ages, so at a $340 burdened cost per visit one unit consumes $136 a year and another $1,700, both billed $8,400. Twelve high callback units consume $20,400 against $100,800 of revenue. Elevator subs at $1M to $5M average 27 percent gross and 9 percent net before taxes, among the best floors in the 48 trade dataset.
Your mechanics are doing the work, and nothing here is a service delivery problem. The contract charges one price for units whose callbacks differ by a factor of ten.
This post covers one costing question inside the maintenance book. That page covers how the trade operates and where elevator margin comes from across install, modernization and service. Read CFO for Elevator Contractors for the complete treatment, worked figures included.
WHY IS THE ELEVATOR BOOK THE BEST MARGIN IN CONSTRUCTION?
Because it recurs. Full maintenance contracts bill $500 to $1,200 per traction unit per month at published market rates, and $400 to $900 for hydraulic. A three elevator building budgets $15,000 to $40,000 a year and renews it without a bid.
Elevator has a 9 percent net profit floor before taxes at $1M to $5M, which is among the strongest of the 48 trades SPM tracks. That figure is the annuity at work inside the average. No project trade earns a dollar in January for work it will perform in December.
So the maintenance book is the asset. And the asset is priced with one number, which makes what follows the most expensive blind spot in the trade.
WHAT A FULL MAINTENANCE CONTRACT REALLY IS.
It is an insurance policy you underwrote. You set the monthly rate, you set your own visit cadence, and you assume responsibility for whatever the unit does between visits. If it behaves, the contract is very profitable. If it does not, you pay for parts and a mechanic at whatever hour the call comes in.
That bet works when the rate is priced above the unit's callback frequency. Most books use one rate band across units built thirty years apart. The buildings have completely different traffic, and the door operators are in completely different condition.
A 2019 traction unit in an office tower with a working door protection system might produce 0.4 callbacks a year. A 1996 hydraulic in a residential building where the doors get held with a foot every morning produces five. Both are on the schedule at $700 a month.
WHAT THAT COSTS ON A 90 UNIT BOOK.
Ninety units at $700 a month is $756,000 a year of recurring revenue, holding about $204,000 of gross profit at elevator's 27 percent.
Price a callback properly and it is a mechanic, a truck, drive time, and frequently a part, so call it $340 fully burdened per visit. The 0.4 callback unit costs $136 a year against $8,400 of revenue. The five callback unit costs $1,700 against the same $8,400.
Now say twelve of the ninety are at the high end. Those twelve consume $20,400 of callback cost against $100,800 of revenue, a 20 percent cost line on contracts priced as though callbacks were a 4 percent line. The other seventy eight units are paying for them, and the book's blended 27 percent gross margin reports the whole thing as healthy.
MOST SUBS MISS THIS: YOU CANNOT REPRICE WHAT YOU DO NOT COUNT.
Here is the part to screenshot. Almost every elevator service book tracks callbacks as a dispatch record. Nobody tracks them as a cost per unit. The call comes in, somebody goes, the work gets done, and the hours go to a service labor code. That code adds up the whole portfolio.
So at renewal time you have a monthly rate, a customer relationship and a gut feeling. What you do not have is the one figure that would justify a 40 percent increase on a specific building, which is that this unit cost you $1,700 to maintain last year against $8,400 of revenue while the building next door cost $136.
A customer will argue with a rate increase. Twelve dated service tickets on their own equipment are much harder to argue with. The tracking gives you your negotiating position, and it takes one field on a work order.
THE FOUR FIELDS THAT BUILD THE PICTURE.
You don't need a new dispatch system. You need four fields on the work order and one report a quarter.
1. A unit identifier on every callback. A building identifier is too coarse, because a building with four cars has four different risk profiles and merging them conceals all of it.
2. Cause code on every callback: door system, controller, hydraulic, entrapment, vandalism and misuse. Cause is what tells you whether a repair or a rate increase is the answer.
3. Hours and parts booked against that unit, so the cost is the unit's own cost. A standard visit charge won't tell you.
4. Unit age and last modernization date, entered once. This is the number that predicts everything else. Nobody records it, because it is printed on a nameplate in the machine room.
One report a quarter: revenue, callback count and callback cost per unit, sorted by margin. The bottom ten lines are your renewal conversation list.
WHAT IT IS WORTH ON A $2.8M SHOP.
Elevator at $1M to $5M averages 9 percent net profit before taxes against a 12.5 percent target. On $2.8M that distance is about $98,000 a year.
Per unit costing does not close all of it, and the repricing takes a renewal cycle to work through. It tells you right away which contracts to walk away from. Most service contractors have never had the data to make that decision.
There is also a growth argument. A contractor who knows his callback cost by unit age can price an acquisition of somebody else's book properly, and books get bought and sold in this trade constantly. Buying ninety units at a flat multiple when a third of them are 1990s hydraulics is how a good year becomes a bad one.