THE NUMBERS, NOT THE FEELING.
9 anonymized client engagements across 7 trades, from $2.3M to $25M in revenue. Every figure comes from the client's own books rather than from a survey or an estimate. Between them: four merchant cash advances cleared to zero, overdue receivables collected in four separate engagements with $365,000 the largest of them and one of the others collecting $203,000 inside a single week, two overhead rates corrected by double digits, profit sharing and bonuses paid in four companies, one business whose valuation moved from $2.3M to $5.5M in nine months without adding revenue, and one study whose outcome is visibility rather than a dollar figure, which that page states in those words. No company is identified, because a contractor's financial position is his business and not our marketing.
Read these looking for your own situation and not for the biggest number. The useful part is almost never the outcome, it's the diagnosis: what was really wrong, how long it had been wrong, and what the owner had been told was wrong instead.
SMALLEST BUSINESS TO LARGEST.
Ordered by revenue so you can go straight to the one closest to your size. The problems don't change much with scale, but the amount of money each one costs does.
VISIBILITY INTO A BUSINESS THAT FELT RANDOM.
A $2.3M fiber splicing subcontractor had skilled crews, major telecom carrier clients, and a bank account nobody could explain. Some months looked strong, some looked like a disaster, and none of it was predictable. Project costs were posting to the wrong places, so the real picture was invisible. January 2026 ran $141,000 of project cost against $144,000 of revenue, which leaves almost nothing before overhead. The owner now reads his own numbers every month and knows what his T&M rate has to be.
Total time from first call to a monthly close the owner reads himself: the standard 60 day onboarding. There's no debt payoff date to report on this engagement, because the outcome here is visibility and a corrected pricing basis rather than a recovery.
$365,000 RECOVERED AND ALL DEBT CLEARED IN 120 DAYS.
A $3.2M commercial electrical subcontractor had a collections problem that had turned into a debt problem, borrowing to cover work that had been performed and never collected. We built job costing from scratch and put a systematic collections process in place. $365,000 of overdue receivables came in, all debt was cleared within 120 days, and the owner paid $23,000 in bonuses.
Total time from first call to all debt cleared: 120 days. The collections routine and the billing calendar are still running, which is why the debt hasn't returned.
FROM FOUR MERCHANT CASH ADVANCES TO DEBT FREE.
A $3.4M civil subcontractor had grown fast and financed the growth with four stacked merchant cash advances, overhead at 32 percent, and gross profit at 5 percent. We rebuilt job costing, restructured overhead, and pursued $245,000 of uncollected receivables. The advances were eliminated, overhead dropped to 15 percent, and gross profit reached 33 percent.
Total time from first call to the last merchant cash advance being cleared: about 12 weeks. The overhead reduction and the gross profit correction held through the following year.
$1.3M LESS REVENUE AND MORE PROFIT.
A $4.9M concrete subcontractor felt that something was wrong, because revenue kept rising and cash never reflected it. Overhead was carried on the books at 5 percent when the real number was closer to 12, so every job had been priced against a cost structure that was wrong. We collected $203,000 in the first week, corrected the rate, and rebuilt job costing.
Total time from first call to a corrected overhead rate running inside live bids: about 10 weeks. The revenue reduction and the profit increase both showed in the following full year.
$24,000 TO $1.1M IN NET PROFIT.
An erosion control and SWPPP contractor was doing $5.2M and netting $24,000. Sites weren't tracked individually, so nobody knew which ones earned and which ones consumed the earnings of the others. We built per site job costing, corrected the overhead rate, and added WIP reporting. Net profit reached $1.1M the following year.
Total time from first call to per site reporting running every month: about 10 weeks. The full profit result showed in the following complete year.
OVERHEAD 30 PERCENT TO 17, $309K IN THE BANK.
A $6.7M contractor had a $348,000 line of credit maxed out and overhead running at 30 percent of revenue. He knew something was off and couldn't see where the money was going. We cut overhead from 30 percent to 17 percent and put a collections process in place. $309,000 was in the bank within 30 days, the $348,000 line of credit was fully paid off within 60, and the owner paid out $65,000 in bonuses.
Total time from first call to the $348,000 line of credit reading zero: 60 days. The first $309,000 was in the bank inside the first 30, because collecting money already owed doesn't wait for a system to be finished.
$310K COLLECTED IN 30 DAYS AND THE HOUSE KEPT.
A $7.1M turnkey civil contractor had grown from $500,000 in his first year to $5M in his second, and every month the business committed money to new work faster than it collected on finished work. Two lines of credit, an SBA loan, and a personal line secured against his house were all maxed out. We built a cash flow forecast, slowed the pace of new work for two months so receivables could catch up, and overhauled billing and collections. $310,000 came in during the first 30 days, and both lines of credit and the SBA loan were paid off within 90.
Total time from first call to both lines of credit and the SBA loan reading zero: about 90 days. The first $310,000 was collected inside the first 30, because collecting money already owed doesn't wait for a system to be finished.
A $2.3M BUSINESS BECAME A $5.5M BUSINESS IN 9 MONTHS.
A $13.1M marine general contractor wanted to sell, and the number wasn't there. Four accounting staff, no job costing, no per project reporting. We built the cost structure, tightened spending nobody had examined, and put twice monthly reporting on every job. Net profit went from 7 to 14 percent on the same revenue, and the valuation went from $2.3M to $5.5M.
Total time from first call to the revalued business: nine months. The margin recovery itself was largely complete inside the first 90 days, and the remaining six months were spent building the documented record a buyer would rely on.
FINANCIAL INFRASTRUCTURE BUILT FROM ZERO, $2.6M IN PROFIT SHARING.
A $25M marine general contractor came to us with no job costing, no WIP reporting, and no visibility at the project level. We built the entire finance function from scratch. The bank balance hasn't dropped below $1.2M since the engagement started, the business generated over $1M in net profit, and it paid out $2.6M in profit sharing.
Total time from first call to the full finance function running, meaning job costing, WIP, cost to complete, and the monthly cadence: about 90 days. The bank floor and the profit sharing followed in the first full year.
WHAT WE WILL NOT CLAIM.
NONE OF THEM HAD A REVENUE PROBLEM.
Every business on this page was busy. Full schedules, capable crews, and general contractors who wanted to keep using them. In several of them the P&L looked acceptable right up until the bank balance didn't. That's the thing worth taking away: by the time a contractor calls a CFO, the problem has usually been misdiagnosed as a sales problem or a bookkeeping problem for two or three years.
The other thing they share is a timeline. Onboarding runs 60 days to fully operational, and in most of these engagements the first recovered money came in before that was finished, because collections on work already performed doesn't wait for a system to be complete.
