CLIENT RESULTS · 14 STUDIES

THE NUMBERS, NOT THE FEELING.

QUICK ANSWER

14 anonymized client engagements across 11 trades, from $2.3M to $700K in revenue. Every figure comes from the client's own books rather than from a survey or an estimate. Between them: four merchant cash advances cleared to zero, overdue receivables collected in four separate engagements with $365,000 the largest of them and one of the others collecting $203,000 inside a single week, two overhead rates corrected by double digits, profit sharing and bonuses paid in four companies, one business whose valuation moved from $2.3M to $5.5M in nine months without adding revenue, and one study whose outcome is visibility rather than a dollar figure, which that page states in those words. No company is identified, because a contractor's financial position is his business and not our marketing.

Read these looking for your own situation and not for the biggest number. The useful part is almost never the outcome, it's the diagnosis: what was really wrong, how long it had been wrong, and what the owner had been told was wrong instead.

EVERY STUDY

SMALLEST BUSINESS TO LARGEST.

Ordered by revenue so you can go straight to the one closest to your size. The problems don't change much with scale, but the amount of money each one costs does.

Filter by problem
Filter by size

$2.3M Fiber: Visibility Into a Business That Felt Random
A $2.3M fiber splicing subcontractor couldn't predict a month. January 2026 ran $141,000 of project cost against $144,000 of revenue. Here is what was wrong.
$2.8M Masonry: 80% Spent at 60% Complete, Job After Job
A $2.8M masonry sub priced brick at a production-wall rate. CMU made money, brick gave it back, and one blended cost code hid both.
$3.1M Electrical: 39% Gross, 6% Net, and 33 Points In Between
A $3.1M electrical service contractor was not losing money on jobs. She was losing it on structure, and 33 points of overhead is what that looks like.
$3.2M Electrical: $365,000 Recovered and All Debt Cleared in 120 Days
A $3.2M commercial electrical subcontractor was borrowing to cover work it had performed and never collected. No lenders left, and bonuses paid.
$3.4M Civil: From Four Merchant Cash Advances to Debt Free
A $3.4M civil subcontractor pursued $245,000 of uncollected receivables, restructured overhead, and moved gross profit from 5 percent to 33 percent.
$4.9M Concrete: $1.3M Less Revenue and More Profit
A $4.9M concrete subcontractor had priced every job against a 5 percent overhead rate that was really 12, collected $203,000 in week one, and repriced.
$5M Interior: 6.7% to 11.2% Net in 120 Days
A $5M tenant improvement GC priced every job at a 10 percent overhead rate while running 16.4. Correcting it moved net from 6.7 to 11.2 in 120 days.
$5.2M SWPPP: $24,000 to $1.1M in Net Profit
A $5.2M erosion control contractor couldn't tell which sites earned. Per site job costing and a corrected overhead rate produced a 30 percent net margin.
$6.7M Grading: Overhead 30 Percent to 17, $309K in the Bank
A $6.7M grading contractor cut overhead from 30 percent to 17 percent, collected $309,000 in 30 days, and cleared a maxed $348,000 line of credit in 60.
$7.1M Civil: $310K Collected in 30 Days and the House Kept
A $7.1M turnkey civil contractor collected $310,000 of overdue receivables in 30 days, paid off two lines of credit and an SBA loan, then borrowed $750,000.
$13.1M Marine: A $2.3M Business Became a $5.5M Business in 9 Months
A $13.1M marine general contractor recovered $917,000 of annual margin on the same revenue and same crews, then revalued at a 3 times multiple in 9 months.
$25M Marine: Financial Infrastructure Built From Zero, $2.6M in Profit Sharing
A marine general contractor built job costing, WIP and cost to complete from nothing in about 90 days, and the bank balance hasn't gone under $1.2M since.
$550K Sitework: One Customer to Eight, and a 15% Price Rise Nobody Fought
A sitework contractor billed machine, operator and fuel as one number. Itemizing it raised prices 15 percent and the customer preferred it.
$700K Landscaping: Breakeven to $12K a Month in 75 Days
Nothing was badly broken, which is why nobody chased it. A $700K turf contractor went from breakeven to $12,000 a month cash positive in 75 days.
FIBER, $2.3M

VISIBILITY INTO A BUSINESS THAT FELT RANDOM.

A $2.3M fiber splicing subcontractor had skilled crews, major telecom carrier clients, and a bank account nobody could explain. Some months looked strong, some looked like a disaster, and none of it was predictable. Project costs were posting to the wrong places, so the real picture was invisible. January 2026 ran $141,000 of project cost against $144,000 of revenue, which leaves almost nothing before overhead. The owner now reads his own numbers every month and knows what his T&M rate has to be.

$141K vs $144K
January 2026 Project Cost Against Revenue
12 MONTHS
Utilization Basis for the Corrected T&M Rate
MONTHLY
Financials the Owner Now Reads Himself
2 REVENUE LINES
T&M Plus Contracted Structured Cabling

Total time from first call to a monthly close the owner reads himself: the standard 60 day onboarding. There's no debt payoff date to report on this engagement, because the outcome here is visibility and a corrected pricing basis rather than a recovery.

Read the fiber study

MASONRY, $2.8M

80% SPENT AT 60% COMPLETE, JOB AFTER JOB.

A $2.8M CMU and brick subcontractor kept finishing jobs at 80 percent of budget spent against 60 percent of the work complete. He assumed the trouble was retainage, money already earned and sitting where he couldn't reach it. The job cost report said something else in its first cycle: CMU was profitable and brick was handing the profit back. He priced brick per unit at a rate built for production wall, and soldier courses and the directional cuts around windows and doors consume labor at a different rate entirely. About 20 percent light, on every brick job, for roughly eighteen months.

20%
Light on Brick Labor, Rebuilt by Type
80 TO 60
Spent Against Complete, Corrected
90 TO 30 DAYS
Receivables Pulled In
10% NET
What He Bids At Now

The diagnosis took one job cost cycle, because separating the two scopes was enough to show it. Rebuilding the brick rates by type and correcting the billing took about six weeks. The merchant cash advances were caught at roughly six months into their term, which is why they were payable at all: a year in, the compounding makes them very hard to clear.

Read the masonry study

ELECTRICAL, $3.1M

39% GROSS, 6% NET, AND 33 POINTS IN BETWEEN.

A $3.1M electrical service contractor came to us running the business from fear. A partner separation had pulled six figures out of the company, and everything after that was scrambling. The numbers said the work was fine: gross profit at 39.17 percent, net at 6.07. That leaves 33 points of overhead in between, about $1.03M a year on $3.1M of revenue. She wasn't losing money on jobs at all. She was losing it on structure, and no amount of selling harder closes a hole that size.

60+ TO 30 DAYS
Receivables, Done
CURRENT
Accounts Payable, Done
4 POINTS
Overhead Identified, About $124K a Year
6.07 TO 10.1%
Net Profit, Targeted

Thirty days. The receivables move, the payables position and the payoff order are done and hold today. The 4 points of overhead are identified and not yet removed, so the 10.1 percent net is a target and not a result. That is the honest state of this engagement and it will be updated when the reduction is complete.

Read the electrical study

ELECTRICAL, $3.2M

$365,000 RECOVERED AND ALL DEBT CLEARED IN 120 DAYS.

A $3.2M commercial electrical subcontractor had a collections problem that had turned into a debt problem, borrowing to cover work that had been performed and never collected. We built job costing from scratch and put a systematic collections process in place. $365,000 of overdue receivables came in, all debt was cleared within 120 days, and the owner paid $23,000 in bonuses.

$365K
Overdue Receivables Recovered
120 DAYS
To Clear All Debt
$23K
Bonuses Paid, First in 11 Years
0
Lenders Remaining

Total time from first call to all debt cleared: 120 days. The collections routine and the billing calendar are still running, which is why the debt hasn't returned.

Read the electrical study

CIVIL, $3.4M

FROM FOUR MERCHANT CASH ADVANCES TO DEBT FREE.

A $3.4M civil subcontractor had grown fast and financed the growth with four stacked merchant cash advances, overhead at 32 percent, and gross profit at 5 percent. We rebuilt job costing, restructured overhead, and pursued $245,000 of uncollected receivables. The advances were eliminated, overhead dropped to 15 percent, and gross profit reached 33 percent.

$245K
Overdue Receivables Pursued
4 to 0
Merchant Cash Advances
32 to 15%
Overhead Rate
5 to 33%
Gross Profit

Total time from first call to the last merchant cash advance being cleared: about 12 weeks. The overhead reduction and the gross profit correction held through the following year.

Read the civil study

CONCRETE, $4.9M

$1.3M LESS REVENUE AND MORE PROFIT.

A $4.9M concrete subcontractor felt that something was wrong, because revenue kept rising and cash never reflected it. Overhead was carried on the books at 5 percent when the real number was closer to 12, so every job had been priced against a cost structure that was wrong. We collected $203,000 in the first week, corrected the rate, and rebuilt job costing.

$203K
Collected in Week One
5 to 12%
Overhead Rate Corrected
$130K
Profit Sharing Paid, First Time
$1.3M
Less Revenue, More Profit

Total time from first call to a corrected overhead rate running inside live bids: about 10 weeks. The revenue reduction and the profit increase both showed in the following full year.

Read the concrete study

INTERIOR, $5M

6.7% TO 11.2% NET IN 120 DAYS.

A commercial general contractor doing $5M in tenant improvement buildouts was pricing every job with a 10 percent overhead rate in it. The trailing quarter said 16.4. Tenant improvement work is feast and famine, so the assumption had been set once and never flexed with the volume it was supposed to track. Every bid left the office 6 points light before a crew mobilised, and the shortfall got funded by whatever job started next. Net profit moved from 6.7 percent to 11.2 percent in 120 days, and most of that came from taking 4 points out of overhead, not from winning better work.

6.7 to 11.2%
Net Profit in 120 Days
$389K
A Year of MCA Payments Stopped
4 POINTS
Out of Overhead, About $200K a Year
10 to 16.4%
Overhead Rate Bids Now Carry

120 days from first call to a net margin of 11.2 percent, a swing of 4.5 points worth roughly $225,000 a year at this volume. Most of it is the overhead cut, because that hits the month you make it. The rebuilt estimating template had not fully shown up at the 120 day mark, since jobs bid under the old pricing were still working through the backlog. That gain is still coming.

Read the interior study

SWPPP, $5.2M

$24,000 TO $1.1M IN NET PROFIT.

An erosion control and SWPPP contractor was doing $5.2M and netting $24,000. Sites weren't tracked individually, so nobody knew which ones earned and which ones consumed the earnings of the others. We built per site job costing, corrected the overhead rate, and added WIP reporting. Net profit reached $1.1M the following year.

$24K to $1.1M
Net Profit
$1,105,000
Net Profit, 2025
30%
Net Margin
$1.6M
Less Revenue Than Peak Year

Total time from first call to per site reporting running every month: about 10 weeks. The full profit result showed in the following complete year.

Read the swppp study

GRADING, $6.7M

OVERHEAD 30 PERCENT TO 17, $309K IN THE BANK.

A $6.7M contractor had a $348,000 line of credit maxed out and overhead running at 30 percent of revenue. He knew something was off and couldn't see where the money was going. We cut overhead from 30 percent to 17 percent and put a collections process in place. $309,000 was in the bank within 30 days, the $348,000 line of credit was fully paid off within 60, and the owner paid out $65,000 in bonuses.

$309K
In the Bank Within 30 Days
$348K
Line of Credit Paid Off in 60 Days
30 to 17%
Overhead Rate
$65K
Paid Out in Bonuses

Total time from first call to the $348,000 line of credit reading zero: 60 days. The first $309,000 was in the bank inside the first 30, because collecting money already owed doesn't wait for a system to be finished.

Read the grading study

CIVIL, $7.1M

$310K COLLECTED IN 30 DAYS AND THE HOUSE KEPT.

A $7.1M turnkey civil contractor had grown from $500,000 in his first year to $5M in his second, and every month the business committed money to new work faster than it collected on finished work. Two lines of credit, an SBA loan, and a personal line secured against his house were all maxed out. We built a cash flow forecast, slowed the pace of new work for two months so receivables could catch up, and overhauled billing and collections. $310,000 came in during the first 30 days, and both lines of credit and the SBA loan were paid off within 90.

$310K
Collected in the First 30 Days
90 DAYS
To Pay Off Both LOCs and the SBA Loan
$750K
Loan Approved, Unavailable Before
$300K
Cash Floor Held in the Bank

Total time from first call to both lines of credit and the SBA loan reading zero: about 90 days. The first $310,000 was collected inside the first 30, because collecting money already owed doesn't wait for a system to be finished.

Read the civil study

MARINE, $13.1M

A $2.3M BUSINESS BECAME A $5.5M BUSINESS IN 9 MONTHS.

A $13.1M marine general contractor wanted to sell, and the number wasn't there. Four accounting staff, no job costing, no per project reporting. We built the cost structure, tightened spending nobody had examined, and put twice monthly reporting on every job. Net profit went from 7 to 14 percent on the same revenue, and the valuation went from $2.3M to $5.5M.

7 to 14%
Net Profit, Same Revenue
$917K
Annual Margin Recovered
$2.3M to $5.5M
Business Valuation
9 MONTHS
Time to the New Number

Total time from first call to the revalued business: nine months. The margin recovery itself was largely complete inside the first 90 days, and the remaining six months were spent building the documented record a buyer would rely on.

Read the marine study

MARINE, $25M

FINANCIAL INFRASTRUCTURE BUILT FROM ZERO, $2.6M IN PROFIT SHARING.

A $25M marine general contractor came to us without job costing or WIP reporting, so nobody could tell which projects were making money. We built the entire finance function from scratch. The bank balance hasn't dropped below $1.2M since the engagement started, the business generated over $1M in net profit, and it paid out $2.6M in profit sharing.

$1.2M
Bank Floor Held Since Engagement
$2.6M
Profit Sharing Paid
$1M+
Net Profit Generated
ZERO TO FULL
Job Cost and WIP Coverage

Total time from first call to the full finance function running, meaning job costing, WIP, cost to complete, and the monthly cadence: about 90 days. The bank floor and the profit sharing followed in the first full year.

Read the marine study

SITEWORK, $550K

ONE CUSTOMER TO EIGHT, AND A 15% PRICE RISE NOBODY FOUGHT.

A site work and civil contractor came to us at $550,000 annualized in a partial first year. He wasn't in trouble. After thirty years of starting and owning businesses he knew his own habit: run flat out to survive, put off cash flow and systems until it's too late. This time he wanted the system built first. His time and material rate turned out to be the fault, and it was invisible because the work was profitable enough to cover it. He billed operator, machine and fuel as one combined number, so anything past a six hour day lost money and nothing reported it.

1 TO 8
Customers, in 55 Days
+15%
Pricing, With No Customer Lost
6 HOURS
The Day Length That Used to Cost Him
5 LINES
Machine, Fuel, Labor, Insurance, Maintenance

Fifty five days from first call to eight contractors in the fold at the new pricing. The rate rebuild took about four weeks, and the diversification ran alongside it, never after, which is what made the next part survivable.

Read the sitework study

LANDSCAPING, $700K

BREAKEVEN TO $12K A MONTH IN 75 DAYS.

A father and son team doing about $700,000 came to us on a referral. They spray lawns, run maintenance and laser grade baseball fields alongside commercial work. Their books had been with the same local firm for years, and the work had moved to an overseas team without much being said about it. The local office stopped answering the phone. Nothing in the business was badly broken, which is why none of it got chased: a few dollars adrift on equipment and fuel, labor priced slightly light, overhead two points above what they believed, ACH fees, loan interest. Eleven small things nobody would bother with, and together they took the entire margin.

$12K A MONTH
Cash Positive, From Breakeven
75 DAYS
Time to Get There
$1,000/MO
ACH Fees Removed
$35 TO $45
Minimum Charge, Quotes +15%

Seventy five days from breakeven to $12,000 a month cash positive. The accounting move took two weeks, the pricing corrections came over the following six, and the forecasting cycle is what made the debt paydown deliberate, and no longer whatever was left at month end.

Read the landscaping study

HOW TO READ A CASE STUDY LIKE THIS

WHAT WE WILL NOT CLAIM.

No figure on any of these pages is a projection, a model, or an average. Each one came off a client's own financial statements, and where a number couldn't be verified it's left out rather than estimated.
None of these outcomes came from new revenue. Several came alongside revenue going down on purpose, because work priced below break even isn't revenue worth defending.
No client is identified, and no client will be. That doesn't stop at the company: the general contractors, the markets, and the projects stay out too, since any two of those identify a company in a regional trade.
Nobody is promised these results. What's repeatable is the diagnosis: job costing built against the estimate, an overhead rate that includes what the job really costs, and a forecast dated on when money really moves. What each business does with that's its own.
WHAT THEY HAVE IN COMMON

NONE OF THEM HAD A REVENUE PROBLEM.

Every business on this page was busy. Full schedules, capable crews, and general contractors who wanted to keep using them. In several of them the P&L looked acceptable right up until the bank balance didn't. That's the thing worth taking away: by the time a contractor calls a CFO, the problem has usually been misdiagnosed as a sales problem or a bookkeeping problem for two or three years.

The other thing they share is a timeline. Onboarding runs 60 days to fully operational, and in most of these engagements the first recovered money came in before that was finished, because collections on work already performed doesn't wait for a system to be complete.

WHERE TO GO NEXT
Josh Luebker, The Construction CFO
Josh Luebker
FRACTIONAL CFO · THE CONSTRUCTION CFO

Former commercial project manager and master electrician: 150+ projects worth $2.1B combined, from $50,000 to $300M. Now fractional CFO to commercial subcontractors.

YOUR NUMBERS, NOT SOMEBODY ELSE'S.

Every study here started with one call and a set of books nobody was happy with. Bring your last WIP schedule, or your last three bank statements if there's no WIP schedule.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute diagnostic

20 minutes. No sales pressure. We will tell you exactly what's broken before we talk about anything else.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.