CFOS for QuickBooks, coming January 2027Join the waitlist: 12 months with no subscription fee
CLIENT RESULTS · 15 STUDIES

THE NUMBERS, NOT THE FEELING.

QUICK ANSWER

15 anonymized client engagements across 11 trades, from $2.3M to $700K in revenue. Every figure comes from the client's own books. Four merchant cash advances were cleared to zero. Overdue receivables were collected in four separate engagements. The largest collected $365,000, and one of the others collected $203,000 inside a single week. Two overhead rates were corrected by double digits. Four companies paid profit sharing and bonuses. One business's valuation went from $2.3M to $5.5M in nine months without adding revenue. One study has no dollar outcome. The owner can now see his numbers, and that page says so. No company is identified, because a contractor's financial position is his own business.

Read these looking for your own situation. The most useful part of each one is the diagnosis: what was really wrong, how long it had been wrong, and what the owner had been told was wrong.

EVERY STUDY

SMALLEST BUSINESS TO LARGEST.

Ordered by revenue so you can go straight to the one closest to your size. The problems don't change much with scale, but the amount of money each one costs does.

Filter by problem
Filter by size

$2.3M Fiber: Visibility Into a Business That Felt Random
A $2.3M fiber splicing subcontractor couldn't predict a month. January 2026 had $141,000 of project cost against $144,000 of revenue. Here is what was wrong.
$4.1M to $2.8M Concrete: Gross Margin Doubled in One Year
A concrete subcontractor took gross margin from 10.8 to 22.3 percent and net profit before taxes from $156K to $178K, on $1.3M less revenue.
$2.8M Masonry: 80% Spent at 60% Complete, Job After Job
A $2.8M masonry sub priced brick at a production-wall rate. CMU made money, brick gave it back, and one blended cost code kept both out of view.
$3.1M Electrical: 39% Gross, 6% Net, and 33 Points In Between
A $3.1M electrical service contractor was not losing money on jobs. She was losing it on structure, and 33 points of overhead is what that looks like.
$3.2M Electrical: $365,000 Recovered and All Debt Cleared in 120 Days
A $3.2M commercial electrical subcontractor was borrowing to cover work it had performed and never collected. No lenders left, and bonuses paid.
$3.4M Civil and Excavating: From Four Merchant Cash Advances (MCAs) to Debt Free
A $3.4M civil subcontractor pursued $245,000 of uncollected receivables, restructured overhead, and moved gross profit from 5 percent to 33 percent.
$4.9M Concrete: $1.3M Less Revenue and More Profit
A $4.9M concrete subcontractor had priced every job against a 5 percent overhead rate that was really 12, collected $203,000 in week one, and repriced.
$5M Interior: 6.7% to 11.2% Net in 120 Days
A $5M tenant improvement GC priced every job at a 10 percent overhead rate while operating at 16.4. Correcting it moved net from 6.7 to 11.2 in 120 days.
$5.2M SWPPP: $24,000 to $1.1M in Net Profit
A $5.2M erosion control contractor couldn't tell which sites earned. Per site job costing and a corrected overhead rate produced a 30 percent net margin.
$6.7M Grading: Overhead 30 Percent to 17, $309K in the Bank
A $6.7M grading contractor cut overhead from 30 percent to 17 percent, collected $309,000 in 30 days, and cleared a maxed $348,000 line of credit in 60.
$7.1M Civil and Excavating: $310K Collected in 30 Days and Their House Was Removed from Collateral
A $7.1M turnkey civil contractor collected $310,000 of overdue receivables in 30 days, cleared two lines of credit and an SBA loan, then borrowed $750,000.
$13.1M Marine: A $2.3M Business Became a $5.5M Business in 9 MonthsOutside our core $1M to $12M range
A $13.1M marine general contractor recovered $917,000 of annual margin on the same revenue and same crews, then revalued at a 3 times multiple in 9 months.
$25M Marine: Financial Infrastructure Built From Zero, $2.6M in Profit SharingOutside our core $1M to $12M range
A marine general contractor built job costing, WIP and cost to complete from nothing in about 90 days, and the bank balance hasn't gone under $1.2M since.
$550K Sitework: One Customer to Eight, and a 15% Price Rise Nobody Pushed Back OnOutside our core $1M to $12M range
A sitework contractor billed machine, operator and fuel as one number. Itemizing it raised prices 15 percent and the customer preferred it.
$700K Landscaping: Breakeven to $12K a Month in 75 DaysOutside our core $1M to $12M range
Nothing was badly broken, which is why nobody went after it. A $700K turf contractor went from breakeven to $12,000 a month cash positive in 75 days.
FIBER, $2.3M

VISIBILITY INTO A BUSINESS THAT FELT RANDOM.

A $2.3M fiber splicing subcontractor had skilled crews, major telecom carrier clients, and a bank account nobody could explain. Some months looked strong and some looked like a disaster, and nobody could predict which. Project costs were posting to the wrong places, so nobody could see the real numbers. One winter month had $141,000 of project cost against $144,000 of revenue. That leaves almost nothing before overhead. The owner now reads his own numbers every month and knows what his T&M rate has to be.

$141K vs $144K
One Winter Month, Project Cost Against Revenue
12 MONTHS
Utilization Basis for the Corrected T&M Rate
MONTHLY
Financials the Owner Now Reads Himself
2 REVENUE LINES
T&M Plus Contracted Structured Cabling

Total time from first call to a monthly close the owner reads himself: the standard 60 day onboarding. There's no debt payoff date to report here. The outcome is that the owner can see the business, and his pricing basis is corrected.

Read the fiber study

CONCRETE, $4.1M to $2.8M

GROSS MARGIN DOUBLED IN ONE YEAR.

A concrete subcontractor doing $4.1M a year kept 10.8 percent of revenue after project costs. Twelve months later, on $2.8M of revenue, it kept 22.3 percent, and net profit before taxes went from $156K to $178K. The work was job costing by cost code, a template for every new project, a monthly CEO Report and pricing built from what each job really cost.

10.8% to 22.3%
Gross Margin, Twelve Months
$156K to $178K
Net Profit Before Taxes
3.8% to 6.3%
Net Margin Before Taxes
$1.3M
Less Revenue

The first CEO Report and cash flow forecast were in use about three months after the work started in April 2025. The margin change shows in the twelve months through August 2026.

Read the concrete study

MASONRY, $2.8M

80% SPENT AT 60% COMPLETE, JOB AFTER JOB.

A $2.8M CMU and brick subcontractor kept finishing jobs with 80 percent of the budget spent and 60 percent of the work complete. He thought retainage was the trouble, money already earned and held where he couldn't reach it. The job cost report said something else in its first cycle. CMU made money and brick gave it back. He priced brick per unit at a rate built for production wall. Soldier courses and the directional cuts around windows and doors take labor at a different rate. He was about 20 percent light on every brick job, for roughly eighteen months.

20%
Light on Brick Labor, Rebuilt by Type
80 TO 60
Spent Against Complete, Corrected
90 TO 30 DAYS
Receivables Pulled In
10% NET
What He Bids At Now, Before Taxes

The diagnosis took one job cost cycle, because splitting the two scopes was enough to show it. Rebuilding the brick rates by type and fixing the billing took about six weeks. The merchant cash advances were caught roughly six months into their term, which is why they could be paid off. A year in, the compounding makes them very hard to clear.

Read the masonry study

ELECTRICAL, $3.1M

39% GROSS, 6% NET, AND 33 POINTS IN BETWEEN.

A $3.1M electrical service contractor came to us managing the business from fear. A partner separation had taken six figures out of the company, and everything since was scrambling. The work was fine: gross profit was 39.17 percent and net was 6.07 before taxes. That leaves 33 points of overhead in between, about $1.03M a year on $3.1M of revenue. She wasn't losing money on jobs. She was losing it in overhead, and selling more won't fix a cost that size.

60+ TO 30 DAYS
Receivables, Done
CURRENT
Accounts Payable, Done
4 POINTS
Overhead Identified, About $124K a Year
SET
Debt Payoff Order, Done

Thirty days. The receivables, the payables and the payoff order are done and still in place today. The 4 points of overhead are identified and not yet removed. We'll update this page when the reduction is done.

Read the electrical study

ELECTRICAL, $3.2M

$365,000 RECOVERED AND ALL DEBT CLEARED IN 120 DAYS.

A $3.2M commercial electrical subcontractor had a collections problem that turned into a debt problem. It was borrowing to cover work it had done and never collected on. We built job costing from scratch and set up a collections process. $365,000 of overdue receivables came in, all debt was cleared within 120 days, and the owner paid $23,000 in bonuses.

$365K
Overdue Receivables Recovered
120 DAYS
To Clear All Debt
$23K
Bonuses Paid, First in 11 Years
0
Lenders Remaining

Total time from first call to all debt cleared: 120 days. The collections routine and the billing calendar are still in use, which is why the debt hasn't returned.

Read the electrical study

CIVIL AND EXCAVATING, $3.4M

FROM FOUR MERCHANT CASH ADVANCES (MCAS) TO DEBT FREE.

A $3.4M civil infrastructure and sitework subcontractor that self performs excavation and underground utility work grew fast and paid for the growth with four stacked merchant cash advances. Overhead was 32 percent and gross profit was 5 percent. We rebuilt job costing, cut overhead, and went after $245,000 of uncollected receivables. The advances were paid off, overhead dropped to 15 percent, and gross profit reached 33 percent.

$245K
Overdue Receivables Collected
4 to 0
Merchant Cash Advances (MCAs)
32 to 15%
Overhead Rate
5 to 33%
Gross Profit

Total time from first call to the last merchant cash advance being cleared: about 12 weeks. The overhead reduction and the gross profit correction held through the following year.

Read the civil and excavating study

CONCRETE, $4.9M

$1.3M LESS REVENUE AND MORE PROFIT.

A $4.9M concrete subcontractor felt that something was wrong. Revenue kept rising and the cash never followed. The books showed overhead at 5 percent when the real number was closer to 12, so every job had been priced against the wrong costs. We collected $203,000 in the first week, corrected the rate, and rebuilt job costing.

$203K
Collected in Week One
5 to 12%
Overhead Rate Corrected
$130K
Profit Sharing Paid, First Time
$1.3M
Less Revenue, More Profit

Total time from first call to a corrected overhead rate in use in live bids: about 10 weeks. The revenue reduction and the profit increase both showed in the following full year.

Read the concrete study

INTERIOR, $5M

6.7% TO 11.2% NET IN 120 DAYS.

A commercial general contractor doing $5M in tenant improvement buildouts priced every job with a 10 percent overhead rate. The trailing quarter said 16.4. Tenant improvement work is feast and famine, and the rate was set once and never adjusted with volume. Every bid left the office 6 points light before a crew mobilized. Whatever job started next paid for the shortfall. Net profit moved from 6.7 percent to 11.2 percent before taxes in 120 days. Most of that came from taking 4 points out of overhead.

6.7 to 11.2%
Net Profit in 120 Days
$389K
A Year of MCA Payments Stopped
4 POINTS
Out of Overhead, About $200K a Year
10 to 16.4%
Overhead Rate Bids Now Include

120 days from first call to a net margin of 11.2 percent before taxes, a change of 4.5 points worth roughly $225,000 a year at this volume. Most of it is the overhead cut, because that takes effect the month you make it. The rebuilt estimating template was not fully visible at the 120 day mark, since jobs bid under the old pricing were still working through the backlog. That gain is still coming.

Read the interior study

SWPPP, $5.2M

$24,000 TO $1.1M IN NET PROFIT.

An erosion control and SWPPP contractor was doing $5.2M and netting $24,000 before taxes. Nobody tracked sites one by one, so nobody knew which ones made money and which ones used up what the others made. We built job costing for each site, fixed the overhead rate, and added WIP reporting. Net profit reached $1.1M before taxes the following year.

$24K to $1.1M
Net Profit, $1.1M After Taxes
$1,105,000
Net Profit After Taxes, 2025
30%
Net Margin Before Taxes
$1.6M
Less Revenue Than Peak Year

Total time from first call to per site reporting in place every month: about 10 weeks. The full profit result showed in the following complete year.

Read the swppp study

GRADING, $6.7M

OVERHEAD 30 PERCENT TO 17, $309K IN THE BANK.

A $6.7M contractor had a $348,000 line of credit maxed out and overhead at 30 percent of revenue. He knew something was off and couldn't see where the money was going. We cut overhead from 30 percent to 17 percent and put a collections process in place. $309,000 was in the bank within 30 days, the $348,000 line of credit was fully paid off within 60, and the owner paid out $65,000 in bonuses.

$309K
In the Bank Within 30 Days
$348K
Line of Credit Paid Off in 60 Days
30 to 17%
Overhead Rate
$65K
Paid Out in Bonuses

Total time from first call to the $348,000 line of credit reading zero: 60 days. The first $309,000 was in the bank inside the first 30, because collecting money already owed doesn't wait for a system to be finished.

Read the grading study

CIVIL AND EXCAVATING, $7.1M

$310K COLLECTED IN 30 DAYS AND THEIR HOUSE WAS REMOVED FROM COLLATERAL.

A $7.1M turnkey civil and excavating contractor grew from $500,000 in his first year to $5M in his second. Every month the business spent money on new work faster than it collected on finished work. Two lines of credit and an SBA loan were all maxed out, with a personal guarantee against his house. We built a cash flow forecast, slowed new work for two months so receivables could catch up, and overhauled billing and collections. $310,000 came in during the first 30 days. Within 90, both lines of credit were paid off out of collections and the SBA loan was refinanced into one bank line.

$310K
Collected in the First 30 Days
90 DAYS
To Clear Both LOCs and the SBA Loan
$750K
Loan Approved, Previously Unavailable
$300K
Cash Floor Held in the Bank

Total time from first call to both lines of credit and the SBA loan reading zero: about 90 days. The first $310,000 was collected inside the first 30, because collecting money already owed doesn't wait for a system to be finished.

Read the civil and excavating study

MARINE, $13.1M
Outside our core $1M to $12M range

A $2.3M BUSINESS BECAME A $5.5M BUSINESS IN 9 MONTHS.

A $13.1M marine general contractor wanted to sell, and the number wasn't there. It had four accounting staff and no job costing or reports by project. We built the job cost setup, cut spending nobody had looked at, and set up reporting on every job twice a month. Net profit went from 7 to 14 percent before taxes on the same revenue. The valuation went from $2.3M to $5.5M.

7 to 14%
Net Profit, Same Revenue
$917K
Annual Margin Recovered
$2.3M to $5.5M
Business Valuation
9 MONTHS
Time to the New Number

Total time from first call to the new valuation: nine months. Most of the margin recovery was done in the first 90 days. The other six months built the documented record a buyer would rely on.

Read the marine study

MARINE, $25M
Outside our core $1M to $12M range

FINANCIAL INFRASTRUCTURE BUILT FROM ZERO, $2.6M IN PROFIT SHARING.

A $25M marine general contractor came to us without job costing or WIP reporting, so nobody could tell which projects were making money. We built the entire finance function from scratch. The bank balance hasn't dropped below $1.2M since the engagement started, the business paid out $2.6M in profit sharing, and after that it still had over $1M in net profit before taxes.

$1.2M
Bank Floor Held Since Engagement
$2.6M
Profit Sharing Paid
$1M+
Net Profit Generated
ZERO TO FULL
Job Cost and WIP Coverage

Total time from first call to the full finance function in place, meaning job costing, WIP, cost to complete, and the monthly cadence: about 90 days. The bank floor and the profit sharing followed in the first full year.

Read the marine study

SITEWORK, $550K
Outside our core $1M to $12M range

ONE CUSTOMER TO EIGHT, AND A 15% PRICE RISE NOBODY PUSHED BACK ON.

A site work and civil contractor came to us at $550,000 annualized in a partial first year. He wasn't in trouble. After thirty years of starting and owning businesses, he knew his habit. He worked flat out to survive and put off cash flow and systems until it was too late. This time he wanted the system built first. His time and material rate was the fault. The work was profitable enough to cover it, so nobody saw it. He billed operator, machine and fuel as one number. Anything past a six hour day lost money, and nothing reported it.

1 TO 8
Customers, in 55 Days
+15%
Pricing, With No Customer Lost
6 HOURS
The Day Length That Used to Cost Him
5 LINES
Machine, Fuel, Labor, Insurance, Maintenance

Fifty five days from first call to eight contractors in the fold at the new pricing. The rate rebuild took about four weeks, and the diversification happened alongside it, never after, which is what made the next part survivable.

Read the sitework study

LANDSCAPING, $700K
Outside our core $1M to $12M range

BREAKEVEN TO $12K A MONTH IN 75 DAYS.

A father and son team doing about $700,000 came to us on a referral. They spray lawns, do maintenance and laser grade baseball fields, along with commercial work. Their books had been with the same local firm for years. The work moved to an overseas team without much said about it, and the local office stopped answering the phone. Nothing in the business was badly broken, so nobody went after any of it. Equipment and fuel were a few dollars off. Labor was priced slightly light. Overhead was two points above what they believed. Then card and ACH fees and loan interest. Eleven small things nobody would bother with, and together they took the entire margin.

$12K A MONTH
Cash Positive, From Breakeven
75 DAYS
Time to Get There
$1,000/MO
Card and ACH Fees Removed
$35 TO $45
Minimum Charge, Quotes +15%

Seventy five days from breakeven to $12,000 a month cash positive. The accounting move took two weeks, the pricing corrections came over the following six, and the forecasting cycle is what made the debt paydown deliberate, and no longer whatever was left at month end.

Read the landscaping study

HOW TO READ A CASE STUDY LIKE THIS

WHAT WE WILL NOT CLAIM.

No figure on any of these pages is a projection, a model, or an average. Each one came off a client's own financial statements. Where a number couldn't be verified, it's left out.
None of these outcomes came from new revenue. In several, revenue went down on purpose, because work priced below break even isn't worth keeping.
No client is identified, and no client will be. The general contractors, the markets and the projects stay out too, because any two of those identify a company in a regional trade.
Nobody is promised these results. What repeats is the diagnosis: job costing built against the estimate, an overhead rate that includes what the job really costs, and a forecast dated on when money really moves. What each business does with that is its own decision.
WHAT THEY HAVE IN COMMON

NONE OF THEM HAD A REVENUE PROBLEM.

Every business on this page was busy. They had full schedules, capable crews and general contractors who wanted to keep using them. In several of them the P&L looked acceptable until the bank balance was short. By the time a contractor calls a CFO, the problem has usually been misdiagnosed as a sales problem or a bookkeeping problem for two or three years.

They also share a timeline. Onboarding takes 60 days to be fully operational. In most of these engagements the first recovered money came in before onboarding was finished, because you can collect on work already performed before the system is complete.

WHERE TO GO NEXT
Josh Luebker, SPM The Construction CFO
Josh Luebker
FRACTIONAL CFO · SPM THE CONSTRUCTION CFO

Josh Luebker is a master electrician turned construction CFO, president of SPM The Construction CFO and author of CONTROL: C.F.O.S. Construction Financial Operating System.

NOW LOOK AT YOUR OWN NUMBERS.

Every study here started with one call and a set of books nobody was happy with. Twenty minutes of questions, nothing sold and nothing proposed. If Josh can help, you'll set a longer second call.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute call

20 minutes. No pitch or proposal. Josh asks questions to find out if he can help.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.