$24,000 IN NET PROFIT. THEN $1.1 MILLION.
An erosion control and SWPPP contractor was doing $5.2M and netting $24,000 before taxes. Nobody tracked sites one by one, so nobody knew which ones made money and which ones used up what the others made. We built job costing for each site, fixed the overhead rate, and added WIP reporting. Net profit reached $1.1M before taxes the following year.
A SWPPP and erosion control business has dozens of sites at once. Each has its own inspection schedule, material use and crew travel. Each one is too small to seem worth its own report. That's why this trade is so exposed. Averaged together, the sites looked like a company near break even. The average covered up a wide spread, where a handful of sites paid for the rest. Giving every site its own number was the whole fix. It worked because the profitable work was already there.
- Revenue
- $5.2M
- Before
- $5.2M of revenue and $24,000 of net profit before taxes, with sites not tracked individually.
- After
- Per site reporting in place every month. Net profit of $1,105,000 before taxes in 2025, a 30 percent net margin before taxes, on $1.6M less revenue than the peak year.
- Time
- About 10 weeks to per site reporting. The full profit result showed in the following complete year.
- Result
- Net profit from $24,000 to $1.1M before taxes.
A $5.2M SWPPP SUB. FIFTY SITES, ONE NUMBER.
An erosion control and SWPPP contractor doing $5.2M a year. It handles inspection, installation and maintenance across a large number of active sites for civil general contractors and developers. The crews were experienced and the customer base was strong, so work was never the problem. The company netted $24,000 before taxes on $5.2M, which is close to nothing for a business that size.
NO IDEA WHICH SITES PAID.
Every site was billed and costed into one pool. The company knew what it made in total and nothing about where. A site with long crew travel and heavy maintenance looked the same in the books as a site 10 minutes away that needed almost nothing.
Pricing was the same for all of them. So the sites that cost a lot to service were priced like cheap ones. Nobody turned down or repriced anything, because nothing told them to.
Overhead was posted at a rate nobody had recalculated for the current volume. So the one pooled number they had was wrong twice.
POOLED COSTING CONCEALING THE SPREAD.
Job costs were pooled for the whole company. So pricing couldn't reflect what it cost to serve each site. Profitable sites paid for unprofitable ones. Net margin was near zero at a revenue level that should have made real money.
The Job Profitability System wasn't in place, and this is the clearest way it fails. You can't manage service work spread over many sites on an average. The average is the one number sure to describe none of the sites.
WHAT CHANGED, WEEK BY WEEK.
THE NUMBERS, NOT THE FEELING.
In 2025 the company netted $1,105,000 before taxes, a 30 percent net margin, on $1.6M less revenue than its peak year. The revenue it gave up had been using up the profit from everything else.
Total time from first call to per site reporting in place every month: about 10 weeks. The full profit result showed in the following complete year.
SIXTEEN MONTHS LATER. EQUITY UP $1.17M.
The profit from 2025 stayed in the business. From April 2025 to August 2026, equity went from $475K to $1.65M, working capital from negative $90K to $1.07M, debt to equity from 3.32 to 0.92, and the current ratio from 0.92 to 2.12.
2026 has been a lighter year for new work so far. Revenue through August was $1.32M, against $2.23M for the same eight months of 2025, and the year to date is a loss of $48K before taxes. For most stormwater contractors, a slow year turns into a cash problem.
Here it did not. In every month of 2026, working capital stayed above $510K and the current ratio stayed at 1.49 or better. Per site job costing shows which sites still earn at the lower volume, and the balance sheet built in 2025 pays for the slow months while new work comes in.
DOES THIS SOUND FAMILIAR?
This applies to any contractor with many small jobs or sites at once. Here's what to look for. Costs are pooled because no single site seems big enough to track. Pricing is about the same across very different sites. Revenue is fine and net profit isn't. And nobody can point to your worst site.
If you can't point to your worst three sites without looking, your average is covering up the same spread it covered up here.
See how CFOS applies to SWPPP subcontractors specifically on theCFO for SWPPP Contractors page, or book a 20 minute call. Josh won't pitch you or send a proposal.
