CFOS for QuickBooks, coming January 2027Join the waitlist: 12 months with no subscription fee
WHY YOU'RE SHORT

EXCAVATION JOBS LOOK PROFITABLE. THE COST CODES SAY OTHERWISE.

QUICK ANSWER

Excavation subcontractors have no cash left for reasons specific to how the work is built and billed, on jobs that are making money. The three that cost the most in this trade are below, taken from excavation contractor research. Most are at 75 to 90 days from finishing work to holding the money, and 45 days is achievable.

Cash and profit are measured on different clocks. Your profit and loss records revenue when you invoice and costs when you incur them, while the bank account only knows what cleared. Labour goes out weekly and collects 45 to 90 days later, minus retention. That distance is what a growing, profitable excavation company funds out of pocket, and it widens as you grow. The specific things that widen it in this trade are what the rest of this page is about.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-11-14
WHERE THE CASH GOES IN EXCAVATION

WHERE IT LEAKS OUT.

01 · Iron economics

Same ownership math as civil: roughly $200 per day for a CAT 330 parked, $150 to $200 per hour loaded, industry idle rates near 30 percent. An operator's cubic yards per hour is the revenue engine, and unmeasured production turns good iron into expensive lawn art.

The system that controls this

02 · Weather and the seasonal wall

"Excavation is more weather-dependent than almost any other trade." A half inch of rain stops a spread; frozen ground rewrites production rates; fixed cost continues all winter.

THE THREE THAT DECIDE THE YEAR

WHAT MOVES MARGIN IN THIS TRADE.

LEAK 01

Production Blindness

Excavation sells cubic yards per hour. If you don't track production per operator, per machine and per soil class, the estimate and the field never match. A losing job looks like a winning one until the money is gone.

LEAK 02

The Ground Lies

The soil class changes, you find rock, groundwater rises and quantities move. You spend the cost before the change order is signed. A $630K excavation subcontract went all the way to the Fifth Circuit over this. Paperwork and unit prices decide whether you get paid for it or give it away.

LEAK 03

One Bucket, One Margin

One utility strike can wipe out a job's profit. You get repair bills, fines up to $10,000 for repeats, and GL sublimits that cap below the damage. The locate, the tolerance zone and the hand-dig are safety rules, and they are financial controls too.

THE NUMBER TO MANAGE

DAYS SALES OUTSTANDING.

Ninety days is weak, 45 is the target, 30 is strong. Nothing else moves cash faster.

PositionDaysWhat it means
Weak90 daysRoughly three months of work funded out of your own pocket.
Target45 daysYou can get here on the days you control. Bill on time, send complete paperwork, and follow up in week two.
Strong30 daysTakes work every month. It's the cheapest money you can get.

Moving from 90 days to 45 frees roughly annual revenue divided by 365, times 45 days. At $4M that's about $493,000. At $8M it's about $986,000. That money costs no interest and needs no bank. So we fix billing and collections before we talk about financing.

WHERE YOU SHOULD BE

EXCAVATION BENCHMARKS.

Excavation subcontractors at $1M to $5M net 7 percent, against the CFOS net profit target, set at your trade's net profit average at your revenue plus 3.5 points, never below 10 percent, before taxes. The working capital target is 13 percent of annual revenue, and the monthly close should finish by day 10 so the numbers can still change a decision.

Full excavation benchmarks
COMMON QUESTIONS

FREQUENTLY ASKED.

Because the jobs earn before the money comes in. Labour and material go out on a weekly cycle and collect 45 to 90 days later, with 5 to 10 percent held as retention behind that. In excavation specifically that distance is widened by iron economics and weather and the seasonal wall. None of that reads as a loss on any single job, which is why it goes unaddressed.

Because the trade pays you last and charges you first. Equipment payments and fuel are due daily. Trucking subs bill weekly. The receivable is paid 60 to 90 days later, minus retainage. Add one rock surprise or one failed compaction test and the quarter's cash is spoken for.

Three tiers, and which one you are in depends on how much of the work you want off your desk. On Core we build your plan every month and your team does the work: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. On Strategic we build the plan, track it and adjust it every month: our team does the bookkeeping and the bank reconciliations, and the job costing and WIP software is set up and managed for you, on your own online software or ours. On Platinum we manage the money side for you every week: our team handles your bills and receivables the way an in-house controller would, and you approve every payment. We don't do payroll.
$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time
WHAT THIS TIES INTO
Josh Luebker, SPM The Construction CFO
Josh Luebker
FRACTIONAL CFO · SPM THE CONSTRUCTION CFO

Josh Luebker is a master electrician turned construction CFO, president of SPM The Construction CFO and author of CONTROL: C.F.O.S. Construction Financial Operating System.

WHICH WEEK DO YOU COME UP SHORT?

Twenty minutes of questions about your open invoices, your payroll calendar, and how your general contractors really pay. Josh won't pitch you or send a proposal. If Josh can help, you'll set a longer second call.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute call

20 minutes. No pitch or proposal. Josh asks questions to find out if he can help.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.