JOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOSUBCONTRACTOR FINANCEOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQOREJOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOSUBCONTRACTOR FINANCEOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQOREJOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOSUBCONTRACTOR FINANCEOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQOREJOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOSUBCONTRACTOR FINANCEOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQORE
The Construction CFOSchedule a Free Call

TL;DR: ControlQore for concrete contractors uses cost codes by pour phase — formwork, rebar, pump, placement by pour, finishing — to track labor cost per yard, material cost against budget, and equipment cost by job. GC relationship profitability is visible by grouping job results. WIP schedule produced monthly from cost-to-cost percentage complete. SOV structure reviewed and recommended before each new contract is signed. SPM migrates concrete clients from QuickBooks to ControlQore in 60 days.

Software — Concrete Contractors

ControlQore for
Concrete Contractors.

Generic accounting software cannot track labor cost per yard by pour, show which GC relationship is profitable, or flag when a job is trending toward a loss in week three. ControlQore can.

Published: May 2026Updated: May 2026
By Pour
Cost Code Structure for Concrete Work
Weekly
Labor Cost Per Yard vs. Estimate
GC Level
Profitability Grouped by Relationship
Monthly
WIP Schedule From Actual Data
The Problem

What You Are Dealing With

01

No Labor Cost Per Yard Visibility

QuickBooks job tracking shows total labor cost by job. ControlQore shows labor cost per cubic yard by pour phase — weekly, compared to the estimated rate from the bid. When a pour is running at $52/yard against an estimate of $38/yard in week two, there is still time to adjust crew size, change methods, or initiate a change order conversation. At closeout, there is not.

02

GC Relationships Blended Into One P&L

A concrete contractor working with four GCs at 28%, 22%, 18%, and 9% gross margin respectively sees a blended P&L of approximately 20%. The 9% GC is consuming crew capacity that the 28% GC could use. Without job costing grouped by GC, the decision of where to direct capacity is made on relationship history and gut feel rather than data.

03

SOV Accepted Without Review

Concrete subcontractors accepting GC-drafted schedules of values without review are accepting SOV structures that underbill formwork, rebar, and mobilization — the most cash-intensive early phases — and back-load value to later milestones. On a $600,000 concrete contract, a poorly structured SOV can create a $60,000–$120,000 cash hole in the first 60 days.

The Fix

How to Fix It

Cost Codes by Pour Phase in ControlQore

SPM builds ControlQore cost codes for concrete clients by pour phase: mobilization, formwork and shoring, rebar and reinforcing, concrete pump, concrete placement (by pour), finishing, and cleanup. Labor, material, and equipment post to the correct phase. Weekly actual labor cost per yard is calculated from phase cost codes and compared to the estimated rate. Variance over 10% triggers a review.

GC Relationship Profitability Report Monthly

ControlQore job attributes include GC name. Monthly reporting groups job results by GC — gross margin by relationship, average days to payment, open change orders. After six months, the pattern is clear. Concrete contractors who go through this analysis redirect 20–30% of capacity from low-margin GC relationships to high-margin ones — same revenue, meaningfully better margin.

SOV Review Before Every New Contract

SPM reviews every new concrete subcontract SOV before signing and recommends front-loading adjustments — mobilization line item at 5–8% of contract value, formwork and rebar billable at installation, pump mobilization as a separate line. The review takes one meeting. The cash flow benefit applies for the full duration of the project.

Monthly WIP From Pour-Level Job Costing

The WIP schedule for concrete clients is produced monthly from cost-to-cost percentage complete by job. Underbilled positions — work performed but not billed — show immediately and trigger a corrected pay app. Overbilled positions — billed more than work performed — flag jobs where billing has outrun actual progress. Both are visible before they become problems.

Client Outcome

Real Numbers — Real Results

Concrete Contractor · $4.9M Revenue

This contractor had no job costing system — P&L only, no per-job visibility, no labor cost per yard tracking. Overhead rate was 5% (actual was 12%). GC relationships were indistinguishable in the blended P&L.

$203,000

Collected in AR in the first 7 days of engagement.

Overhead: 5% → 12%

Corrected immediately. $130,000 in profit sharing paid within 12 months.

FAQ

Frequently Asked Questions

How does ControlQore track labor cost per yard for concrete contractors?
SPM builds pour-phase cost codes in ControlQore. Foremen log hours by pour at end of each day. ControlQore calculates burdened labor cost for those hours and divides by cubic yards placed in that period. The result — actual labor cost per yard — is compared weekly to the estimated rate from the bid. Variance is visible in week two, not at closeout.
Can ControlQore show which GC relationships are most profitable for concrete contractors?
Yes. SPM configures GC name as a job attribute in ControlQore. Monthly reporting groups all closed and in-progress jobs by GC, showing gross margin, average days to payment, and open change orders by relationship. After six months of data, the profitability ranking of each GC relationship is clear and data-driven.
How does ControlQore handle the SOV structure for concrete billing?
ControlQore is configured with the same SOV line items as the subcontract — mobilization, formwork, rebar, placement by pour, finishing. Pay app billings post against these line items. When a line item is billed at a percentage that exceeds the actual cost incurred as a percentage of total estimated cost for that phase, the WIP flags it as overbilled.
How long does ControlQore setup take for a concrete contractor?
60 days from engagement start to live job costing with WIP reporting. The concrete-specific setup includes pour-phase cost code build, GC attribute configuration, SOV structure alignment, and historical data migration from QuickBooks. Most concrete clients are fully operational in ControlQore within 60 days.
Josh Luebker
Josh Luebker
Fractional CFO · The Construction CFO

Former commercial construction PM and master electrician. Managed 150+ projects totaling $300M+. Now fractional CFO for subcontractors doing $1M–$12M through Sulphur Prairie Management. About Josh →  |  LinkedIn →

Ready to Fix the Cash Problem?

A free call with Josh takes 30 minutes. Bring your last P&L and current bank balance.

Schedule a Free Call →
Related Resources
CFO Services
Best CFO for Concrete Contractors
Concrete-specific financial systems including ControlQore
Software
ControlQore Job Costing Setup Guide
The full 60-day setup sequence
Software
ControlQore vs QuickBooks
Why ControlQore instead of QuickBooks for concrete work
Pain Point
Concrete Labor Cost Per Yard
What pour-level job costing enables
Pain Point
Which GC Relationships Profitable
GC profitability analysis from ControlQore data
CFO Services
CFO for Concrete Contractors
Full service overview for concrete subcontractors
The Construction CFO
ControlQore for ConcreteControlQore Setup GuideBest CFO ConcreteSchedule a CallJosh@ConstructionCFO.net
© 2026 SULPHUR PRAIRIE MANAGEMENT · SULPHUR ROCK, AR
0