TRADE SERVICE · CONCRETE & MASONRY CLUSTER

FRACTIONAL CFO FOR CONCRETE CONTRACTORS.

QUICK ANSWER

We manage the finance function for concrete subcontractors doing $1M to $12M: job costing aligned to the way you estimate, a 13 week cash flow forecast, monthly WIP, and a CFO in the room every month. Pricing starts at $1,900 per month.

Concrete spends on pour day and collects a season later, so the finance function is built around that clock. We price the pour as an event: truck standby, finishers on the ready, weekend delivery premiums of $50 to $300 per load, and short-load fees of $40 to $60 a yard that add $200 to $400 to every punch pour. We also treat procurement as math, because plant-to-plant spreads of $20 to $40 a yard in the same market are worth $60,000 to $120,000 on a 3,000 yard year. Then the 28-day strength clock goes on the billing calendar with a rework reserve behind it, so a failed cylinder is a protocol instead of a crisis.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-11-02
WHERE CONCRETE LOSES MONEY

THE THREE THINGS THAT DRAIN THE CASH.

LEAK 01

The Pour-Day Cascade

Trucks on the clock, finishers waiting, weekend premiums of $50 to $300 per load, and a cold-joint spec risk if sequencing falls behind. Pour day is where the estimate meets physics, and untracked standby and premium cost is margin poured into the slab.

LEAK 02

The 28-Day Gate

Strength comes on the concrete's schedule, not the billing schedule, and a failed break leads to coring, repour risk, and a delayed milestone. The test report is a payment gate; treat it like one with a reserve and a protocol.

LEAK 03

The Factoring Spiral

Aged AR sent through factoring or an MCA trades a timing problem for a permanent margin tax. A $4.9M concrete contractor netted $161K inside that cycle and $1.1M net outside it; the difference was the control system, in the same market as the year before.

THE MATH

FROM 7% TO 10.5% NET.

At $1M to $5M, the average concrete sub earns 21% gross margin and spends 14% of revenue on overhead, which leaves 7% net profit before taxes (Run On CFOS Trade Benchmark Reference). The CFOS target is 10.5% before taxes, the concrete average plus 3.5 points and never below 10%, where the book CONTROL's 12% is the rule of thumb across trades. It is not the industry average.

The target takes two moves. Overhead comes down 1 point to 13%, and gross margin comes up 2.5 points to 23.5%, so 23.5 minus 13 leaves 10.5. The gross margin points come from the three leaks above, priced and billed, not absorbed. On a $3M year, every point is $30,000.

HOW SPM FIXES IT

WHAT WE CHANGE.

These are the concrete problems we put a number on first. Each one gets its own cost code, its own line on the schedule of values or its own line in the 13 week cash forecast, so you can read it in the monthly meeting while the job is still open.

GAP CALCULATOR

THE CONCRETE GAP CALCULATOR. AVERAGE AGAINST TARGET, IN DOLLARS.

Put in your annual revenue. You get gross margin, overhead and net profit for concrete contractors your size: the industry average and the CFOS target, in dollars a year. Nothing you type leaves this page.

Another trade too? The gap calculator for every trade.

Your figures show here once you put in your revenue.

Book a 20 minute call

Why aim for the target. An average is the middle of the pack: about half of companies do worse. And about 6 in 10 construction businesses close within 10 years (U.S. Bureau of Labor Statistics: about 40 percent of construction businesses opened in 2013 were still open in 2023). So the business in the middle is one of the ones that close. On those numbers, average is a business that closes within 10 years. That is why the CFOS target is a requirement.

Want your own numbers against these? The Financial Health Snapshot builds a CEO Report from your last 12 months and sets every figure against your trade.

PRICING

FLAT MONTHLY FEE. NO SURPRISES.

Priced by trailing 12 month revenue. No hourly billing. No payroll. The one-time onboarding fee is right here in the table.

Type a number and your band and its prices show here. The full table is below.

Built for subs doing $1M to $12M. Above $12.5M we quote.

Last 12 months revenueCoreStrategicPlatinumOne-time onboarding
Under $1M$1,900$3,100$3,300$2,500
$1M to $3.5M$2,600$4,100$5,300$4,500
$3.5M to $6.5M$3,800$5,900$8,300$6,000
$6.5M to $9.5M$5,100$7,600$11,800$7,500
$9.5M to $12.5M$6,100$8,900$14,900$9,000
Above $12.5MQuotedQuotedQuotedQuoted

The onboarding fee covers migrating your books back to the start of your last taxable year and getting you fully operational in 60 days. It's billed once, with your first invoice. It's the same for all three tiers, and it moves with your revenue band. Your first month is prorated, and your monthly engagement starts on the first of the first full month.

Just want the setup? Onboarding only is the same onboarding work with no monthly service after it, one time, at the onboarding fee plus $2,000. Start a monthly engagement later and $2,000 counts toward it. It starts at $4,500, and the price for every band is on the pricing page.

The three tier columns are the whole price. Which one fits depends on how much of the work you want off your desk. No payroll. No hidden line items. The onboarding fee is right here in the table.

  • Online software only: QuickBooks, Sage, Viewpoint and similar. No VPN or hosted desktop.
  • Not in any tier: payroll, pay applications, collections on receivables.
  • Pricing valid through 2027.

What Core, Strategic and Platinum each include is on the pricing page.

Prevailing wage note: Concrete work often comes from public bids, which means certified payroll and wage classifications have to line up with the job cost record. ControlQore holds the classification against the cost code, so the certified report and the job cost report come from the same data, and your office stops keying the same numbers twice every week.

COMMON QUESTIONS

FREQUENTLY ASKED.

Concrete contractors at $1M to $5M net 7 percent on average, rising to 13 percent by $25M to $50M; the CFOS net profit target is 10.5 percent before taxes at $1M to $5M, the trade average plus 3.5 points. One verified $4.9M concrete contractor closed that exact gap, moving from $161K to $1.1M net, by fixing job costing and cash control rather than seeking more revenue. Every net profit figure here is gross margin minus overhead, stated before taxes, the same basis CFMA reports net income on.

See the full benchmarks for every revenue band on Run On CFOS.

Usually it needs the CFO work, not a full time CFO. At $5M to $10M, concrete subs average 9% net profit before taxes (Run On CFOS Trade Benchmark Reference), and the CFOS target is 12.5%. On $5M of revenue every point is $50,000, so that distance is worth $175,000 a year. A full time CFO costs $150,000 or more in salary alone. SPM's published price for $3.5M to $6.5M is $3,800 a month for Core to $8,300 for Platinum.

Because the trade spends on pour day and collects a season later. Ready-mix bills in 30 days, crews get paid Friday, the receivable lands at 60 to 90 days minus retainage, and the 28-day strength clock gates milestones. The profit is real; the cash is on other people's calendars.

Short-load fees are $40 to $60 per yard (adding $200 to $400 to a small pour), and Saturday or holiday deliveries add $50 to $300 per load. Punch pours and closeout dribs pay premium prices the bid never priced, so batch small pours and schedule weekday deliveries wherever the schedule allows.

Price both ways: plant-to-plant spreads are $20 to $40 per yard in the same market, but reliability on pour day has a price too. Quote at least two plants per market quarterly, and weigh the spread against standby risk; a cheap plant that delivers late costs more than the discount.

Investigation first (retests, cores), then worst case demolition and repour on your dime while the milestone is delayed. Fund a rework reserve, keep a written test-failure protocol, and document mix tickets and placement conditions on every structural pour; the paper decides who pays.

About 13 percent of revenue at that size, trending toward 11 percent as revenue grows. The outside benchmarks put construction as a whole at 8 to 15 percent of revenue in total indirect cost, per Jones Maresca and Company's 2025 Performance Benchmarks, with CFMA's 2024 Construction Financial Benchmarker reporting SG&A at 11.8 percent across all respondents. Concrete at your revenue is different, which /construction-overhead-rates-by-trade sets out band by band. Concrete overhead is held in forms, pump decisions, and the yard; the owned-versus-rented formwork and pump-truck ROI calls move the number more than office cuts do.

It converts a timing problem into a permanent margin tax, and it compounds. The verified alternative on this site: a $4.9M concrete contractor exited the factoring-and-debt spiral and moved from $161K to $1.1M net through AR discipline, billing velocity, and a 13-week cash forecast instead.

A bookkeeper records history. Pour-day cost codes, break-test protocols, crew-split tracking, supplier pricing discipline, and WIP for bonding are a control system, which is CFO work. SPM operates that financial control function for concrete contractors.

Three tiers, and which one you are in depends on how much of the work you want off your desk. Core is where you stop guessing: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. Strategic is where every job shows its margin while it is still open: a bookkeeper we choose does the books and the bank reconciliations, and the job costing and WIP software is set up and managed for you, on your own online software or ours. Platinum is where you approve and the money side gets handled: a controller we choose handles your bills and receivables the way an in-house controller would, and you approve every payment. No payroll. No scope gaps.

Sixty days. We migrate your books back to the start of your last taxable year and build your job costing structure from scratch, and on Strategic and Platinum we set up the job costing and WIP software too. Fully operational in two months. The onboarding fee is one time, the same for every tier, and set by your revenue band.

ControlQore is the job costing and WIP platform we use on the Strategic and Platinum tiers. Purpose-built for contractors, more affordable than legacy tools, and AI-infused. We set it up and manage it, so you do not have to learn it. Core is the CFO work only, so it does not include the software.

A bookkeeper records what happened. We tell you what it means and what to do about it. We align job costing to your estimates, track WIP monthly, and hold strategic accountability meetings so problems get fixed and not merely documented.
$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time

How concrete CFO firms compare: the concrete firm study, with every score and its source.

WHAT ELSE BREAKS IN CONCRETE

MORE PROBLEMS WE PUT A NUMBER ON.

Form and finishing crew economics

Labor cost per yard tracking · Finishing vs form crew cost codes

Form carpenters and finishers are different labor pools with different productivity math sold under one price, and formwork (owned vs rented) is its own capital decision. Blended tracking does not show which crew makes money, and pump-truck decisions ($ per pour vs owned ROI) depend on data most contractors never collect.

Pour day economics (all hands, one shot)

Ready mix supplier pricing strategy

A pour is a live event. Trucks are sequenced against a set clock, the whole crew plus finishers are ready, and any delay cascades: waiting trucks bill standby, cold joints threaten the spec, and weekend pours add $50 to $300 per load in delivery premiums. One badly sequenced pour day can erase the line item's margin.

Saturday and holiday deliveries add $50 to $300 per load; ready-mix costs roughly $125 to $195 per cubic yard delivered; plant-to-plant pricing spreads $20 to $40 per yard within the same market. (2026 ready-mix cost guides, logged below)

MORE ON CONCRETE

CONCRETE PROBLEMS, ONE PAGE EACH.

OTHER CONCRETE AND STRUCTURE TRADES

Concrete is one of 8 trades in the concrete and structure family on our CFO for subcontractors page. Nearby trades with their own page:

WHAT THIS TIES INTO
Josh Luebker, SPM The Construction CFO
Josh Luebker
FRACTIONAL CFO · SPM THE CONSTRUCTION CFO

Josh Luebker is a master electrician turned construction CFO, president of SPM The Construction CFO and author of CONTROL: C.F.O.S. Construction Financial Operating System.

THE CHEAPER OPTION WORKS. IT TAKES LONGER.

If price comes first, plenty of CFOs and bookkeepers can get your construction company results. It often takes the better part of a year.

If you're a trade contractor, a sub or a GC who wins work, keeps the crews busy and still can't figure out where the money goes, we get in the weeds with you. We change the processes that cost you money on every job, build the ones you're missing and give you the formula, so you see results in 60 to 90 days.

Our guarantee holds when you come to every meeting, do the process and keep a strong pipeline of work. We can fix how your work pays. We can't fix having no work.

DO YOU KNOW YOUR TRUE MARGIN ON CONCRETE WORK?

Twenty minutes of questions about how you price concrete work, what your jobs come in at once they close, and what keeps landing back on your desk. Nothing gets sold on that call and nothing gets proposed. If Josh can help, you'll set a longer second call.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute call

20 minutes. Nothing gets sold on this call and nothing gets proposed. Josh asks questions to work out whether he can help at all.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.