WHY YOU'RE SHORT

MARINE JOBS LOOK PROFITABLE. THE CASH IS STILL IN TRANSIT.

QUICK ANSWER

Marine subcontractors run out of cash for reasons specific to how the work is built and billed, on jobs that are making money. The three that cost the most in this trade are below, taken from marine contractor research. Most sit at 75 to 90 days from finishing work to holding the money, and 45 days is achievable.

Cash and profit are measured on different clocks. Your profit and loss records revenue when you invoice and costs when you incur them, while the bank account only knows what cleared. Labour goes out weekly and collects 45 to 90 days later, minus retention. That distance is what a growing, profitable marine company funds out of pocket, and it widens as you grow. The specific things that widen it in this trade are what the rest of this page is about.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-08-06
WHERE THE CASH GOES IN MARINE

WHERE IT LEAKS OUT.

01 · The permit gauntlet (USACE and everyone else)

Most dredge and in-water work needs USACE Section 404 and state Section 401 permits, plus NOAA and habitat consultations, with environmental windows (fish spawning, bird nesting, turbidity limits) that dictate when the spread can even work. Permit timing is schedule timing, and schedule timing is cash timing.

The module that controls this

02 · Sub-tier position on federal work (the query that found the site)

The trade's top GSC query is "marine construction sub-tier contractor" (18 impressions). Marine subs on federal and port work sit under primes on Corps contracts, with Miller Act payment-bond rights instead of liens, flow-down clauses, and certified payroll. The sub-tier position adds a payment layer and a paperwork regime most dirt contractors never see.

03 · Mobilization at marine scale

Getting a spread to the site (tug transit, permits for the tow, crane rigging, spud setup) is a six-figure event on real jobs, and demob is its own line. Marine mobilization deserves separate SOV billing more than any trade on the site.

The module that controls this

THE THREE THAT DECIDE THE YEAR

WHAT MOVES MARGIN IN THIS TRADE.

LEAK 01

The Spread That Never Sleeps

Barges, cranes, and tugs bill by the day whether the weather cooperates or not, which is why marine overhead runs 16 percent at the small end. Spread-day rates and weather-standby cost codes are the trade's version of equipment utilization, at ten times the stakes.

LEAK 02

The Window

USACE permits, environmental windows, and tide tables decide when the work happens; the contractor decides only whether the cash plan matches. Peak-window competition alone can shift bids 10 to 25 percent.

LEAK 03

The Sub-Tier Maze

Under a prime on federal or port work, lien rights become Miller Act bond rights, deadlines change, and flow-downs govern. A $25M marine GC runs on systems because at marine scale, paperwork discipline is cash discipline. (cfos-cash-control-system) ---

THE NUMBER TO MANAGE

DAYS SALES OUTSTANDING.

Ninety days is weak, 45 is the target, 30 is strong. Nothing else moves cash faster.

PositionDaysWhat it means
Weak90 daysRoughly three months of work funded out of your own pocket.
Target45 daysAchievable on the days you control: submission timing, complete documentation, follow up in week two.
Strong30 daysRequires discipline every month, and it's the cheapest capital available to you.

Moving from 90 days to 45 frees roughly annual revenue divided by 365, times 45 days. At $4M that's about $493,000. At $8M it's about $986,000. That money doesn't come from a bank and it costs no interest, which is why we work the cycle before discussing financing anything.

WHERE YOU SHOULD BE

MARINE BENCHMARKS.

Marine subcontractors at $1M to $5M net 7 percent, against a CFOS target of 10 percent, set at 10 percent before taxes or 3.5 points better than your trade's average at your revenue, whichever is higher. Working capital should sit at 13 percent of annual revenue, and the monthly close should finish by day 10 so the numbers can still change a decision.

Full marine benchmarks
COMMON QUESTIONS

FREQUENTLY ASKED.

Because the jobs earn before the money comes in. Labour and material go out on a weekly cycle and collect 45 to 90 days later, with 5 to 10 percent held as retention behind that. In marine specifically that distance is widened by the permit gauntlet (usace and everyone else) and sub-tier position on federal work (the query that found the site). None of that reads as a loss on any single job, which is why it goes unaddressed.
They own the calendar. Environmental windows, tides, and sea states decide when the spread works, permits decide when the job can start, and peak-window competition can move bids 10 to 25 percent. The cash plan has to carry the spread through the standby days the window forces.
Three tiers, and which one you are in depends on how much of the work you want off your desk. Core is where you stop guessing: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. Executive is where you stop touching the books, because we run the bookkeeping and the controllership as well. Strategic is where every job shows its margin while it is still running, because the job costing and WIP platform is set up and managed for you. No payroll. No scope gaps.
$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time
WHAT THIS TIES INTO
Josh Luebker, The Construction CFO
Josh Luebker
FRACTIONAL CFO · THE CONSTRUCTION CFO

Former commercial construction project manager and master electrician. Managed 150+ projects worth more than $2.1B combined, with individual jobs from $50,000 to $300M, including data centers, military bases, hospitals, and high-rises. Now fractional CFO for commercial subcontractors doing $1M to $12M through Sulphur Prairie Management.About Josh  | LinkedIn

WHICH WEEK DO YOU RUN SHORT?

Bring your open invoices and your payroll calendar. We will build enough of a forecast on the call to tell you which week is tight and why.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute diagnostic

20 minutes. No sales pressure. We will tell you exactly what's broken before we talk about anything else.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.