CFOS for QuickBooks, coming January 2027Join the waitlist: 12 months with no subscription fee
WHY YOU'RE SHORT

MARINE JOBS LOOK PROFITABLE. THE CASH IS STILL IN TRANSIT.

QUICK ANSWER

Marine subcontractors have no cash left for reasons specific to how the work is built and billed, on jobs that are making money. The three that cost the most in this trade are below, taken from marine contractor research. Most are at 75 to 90 days from finishing work to holding the money, and 45 days is achievable.

Cash and profit are measured on different clocks. Your profit and loss records revenue when you invoice and costs when you incur them, while the bank account only knows what cleared. Labour goes out weekly and collects 45 to 90 days later, minus retention. That distance is what a growing, profitable marine company funds out of pocket, and it widens as you grow. The specific things that widen it in this trade are what the rest of this page is about.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-11-02
WHERE THE CASH GOES IN MARINE

WHERE IT LEAKS OUT.

01 · The permit gauntlet (USACE and everyone else)

Most dredge and in-water work needs USACE Section 404 and state Section 401 permits, plus NOAA and habitat consultations. Environmental windows (fish spawning, bird nesting, turbidity limits) decide when the spread can work at all. Permit timing is schedule timing, and schedule timing is cash timing.

The system that controls this

02 · Sub-tier position on federal work (the query that found the site)

Marine subs on federal and port work are under primes on Corps contracts. They have Miller Act payment-bond rights in place of liens, flow-down clauses and certified payroll. That adds a payment step and paperwork most dirt contractors never see.

03 · Mobilization at marine scale

Getting a spread to the site (tug transit, permits for the tow, crane rigging, spud setup) costs six figures on real jobs, and demob is its own line. Marine needs separate SOV billing for mobilization more than any trade on the site.

The system that controls this

THE THREE THAT DECIDE THE YEAR

WHAT MOVES MARGIN IN THIS TRADE.

LEAK 01

The Spread That Never Sleeps

Barges, cranes and tugs bill by the day, good weather or bad. That's why marine overhead is 15 percent at the small end. Spread-day rates and weather-standby cost codes are your equipment utilization, at ten times the stakes.

LEAK 02

The Window

USACE permits, environmental windows and tide tables decide when the work happens. You decide only whether the cash plan matches. Competition in the peak window can move bids 10 to 25 percent.

LEAK 03

The Sub-Tier Maze

Under a prime on federal or port work, lien rights become Miller Act bond rights, the deadlines change and flow-downs govern. A $25M marine GC works on systems, because at marine scale the paperwork is the cash.

THE NUMBER TO MANAGE

DAYS SALES OUTSTANDING.

Ninety days is weak, 45 is the target, 30 is strong. Nothing else moves cash faster.

PositionDaysWhat it means
Weak90 daysRoughly three months of work funded out of your own pocket.
Target45 daysYou can get here on the days you control. Bill on time, send complete paperwork, and follow up in week two.
Strong30 daysTakes work every month. It's the cheapest money you can get.

Moving from 90 days to 45 frees roughly annual revenue divided by 365, times 45 days. At $4M that's about $493,000. At $8M it's about $986,000. That money costs no interest and needs no bank. So we fix billing and collections before we talk about financing.

WHERE YOU SHOULD BE

MARINE BENCHMARKS.

Marine subcontractors at $1M to $5M net 7 percent, against the CFOS net profit target, set at your trade's net profit average at your revenue plus 3.5 points, never below 10 percent, before taxes. The working capital target is 13 percent of annual revenue, and the monthly close should finish by day 10 so the numbers can still change a decision.

Full marine benchmarks
COMMON QUESTIONS

FREQUENTLY ASKED.

Because the jobs earn before the money comes in. Labour and material go out on a weekly cycle and collect 45 to 90 days later, with 5 to 10 percent held as retention behind that. In marine specifically that distance is widened by the permit gauntlet (usace and everyone else) and sub-tier position on federal work (the query that found the site). None of that reads as a loss on any single job, which is why it goes unaddressed.

They own the calendar. Environmental windows, tides and sea states decide when the spread works. Permits decide when the job can start. Peak-window competition can move bids 10 to 25 percent. Your cash plan has to pay for the spread through the standby days the window forces.

Three tiers, and which one you are in depends on how much of the work you want off your desk. On Core we build your plan every month and your team does the work: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. On Strategic we build the plan, track it and adjust it every month: our team does the bookkeeping and the bank reconciliations, and the job costing and WIP software is set up and managed for you, on your own online software or ours. On Platinum we manage the money side for you every week: our team handles your bills and receivables the way an in-house controller would, and you approve every payment. We don't do payroll.
$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time
WHAT THIS TIES INTO
Josh Luebker, SPM The Construction CFO
Josh Luebker
FRACTIONAL CFO · SPM THE CONSTRUCTION CFO

Josh Luebker is a master electrician turned construction CFO, president of SPM The Construction CFO and author of CONTROL: C.F.O.S. Construction Financial Operating System.

WHICH WEEK DO YOU COME UP SHORT?

Twenty minutes of questions about your open invoices, your payroll calendar, and how your general contractors really pay. Josh won't pitch you or send a proposal. If Josh can help, you'll set a longer second call.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute call

20 minutes. No pitch or proposal. Josh asks questions to find out if he can help.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.