CFOS, coming January 2027Join testing: 90 days free
LABOR COST CONTROL

WHY CONSTRUCTION LABOR COSTS GET OUT OF CONTROL FIVE OPERATIONAL CAUSES.

QUICK ANSWER

Construction labor costs get out of control for five reasons. Nobody tracks labor by phase, so an overrun goes unseen the week it starts. The crew on site differs from the crew in the estimate. Nonproductive time was never in the estimate. Added scope gets done with no change order. And overtime gets worked with no record and no recovery. You can measure each one, and each one gets fixed in your job cost setup. Talking to the foreman won't fix it.

Your field crew didn't cause these five. Four of them are estimate and coding problems set before the crew mobilized. The fifth is missing paperwork that costs you a change order you were owed. That's why yelling at the foreman doesn't move the number. Labor comes back under control when you track hours by phase every week, write down the crew mix and nonproductive time the estimate assumed, and give directed work its own cost code from day one.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-11-25
THE DEFINITION

WHAT IT MEANS.

A labor overrun is the difference between the labor hours and dollars an estimate assumed and what the timecards report once the phase is complete.

FIVE OPERATIONAL CAUSES

WHERE THE HOURS GO.

01

Phase level tracking doesn't exist

One labor line for the whole project keeps phase overruns out of sight until closeout. A phase can be 40 percent over and nobody sees it until several other phases finish and the total finally moves. Track labor by phase, actual against estimated, from weekly timecards. Then you catch the overrun at week two of that phase.

02

Crew composition differs from the estimate assumption

Estimates assume a crew mix at set rates, something like two journeymen, one apprentice and one laborer. When the field sends more journeymen, older workers at higher rates or a different workers comp class, your fully burdened labor rate is over the estimate from day one. The crew can be working fine. So the fix is tracking the crew you sent against the crew you estimated, by phase.

03

Nonproductive time was never in the estimate

Production estimates count install time, the hours the crew spends installing the work. Travel, toolbox talks, setup and breakdown, waiting on material and rain delays all cost money, and production rates leave them out. A project with 15 percent nonproductive time against a 5 percent estimate gets 89 percent of estimated production. That's a 12 percent labor overrun, and the crew wasn't slow.

04

Scope additions get absorbed into base scope labor

The GC tells your crew to do extra work, and they do it. With no separate change order cost code, the labor gets coded to base scope. Base scope then looks over budget, and the added scope has no record. The fix is a change order cost code you open on day one and review every week, signed change order or not.

05

Overtime is required in the field but wasn't in the estimate

Tight schedules, milestone deadlines and late starts mean overtime at 1.5x or 2.0x the rate, and most estimates don't include any. When other trades or owner changes cause the schedule pressure, write the overtime down and submit it as a labor premium change order. Most contractors pay for it themselves and then wonder why labor closed over.

THE MATH

WHAT IT LOOKS LIKE IN DOLLARS.

Nonproductive time, worked out

If the estimate assumes 5 percent nonproductive time and the actual is 15 percent, every labor line in that estimate is understated by roughly 12 percent. Effective production comes in at 89 percent of estimated. Typical nonproductive time for commercial field trades is 10 to 18 percent, so a 5 percent assumption is optimistic on most work.

What a single labor line keeps unseen

A phase can be 40 percent over and nobody sees it inside one project labor line until several phases finish. By then the money is spent and the cost to complete has already been reported wrong. Tracking each phase weekly means you find it at week two of the phase.

HOW TO CONTROL LABOR COSTS

WHAT CHANGES THE NUMBER.

A phase level labor budget with weekly variance

Budget labor hours by phase from the estimate and compare them to timecards every week. A variance you find at week eight from month end data is already two to three weeks old. Weekly entry is what makes the number worth acting on.

A foreman production count, daily

The foreman counts units installed every day. So the crew sees units per hour that day, and accounting doesn't work it out weeks later. The field gets the same measure the estimate was built on. Nobody needs an accounting background to read it.

A change order cost code for every directed item of work

As soon as someone directs work outside base scope, it gets its own cost code, signed change order or not. Base scope stays clean and the added scope keeps its own labor history. That history is the paperwork that gets the change order paid.

Overtime documented the week it happens

When schedule pressure causes overtime, write it down the day it happens, with the cause and who caused it. That's how overtime you'd pay for yourself becomes a labor premium change order. Paperwork put together after the fact almost never gets paid.

The cost to complete rolls the labor variance forward

Phase variances get flagged in the cost to complete at month two, while you can still adjust. The projected final cost updates before the next billing cycle. The monthly report then shows where the job is today.

WHAT YOU GET

THE OUTPUTS, NAMED.

Phase level labor budget with weekly variance
Daily foreman production count in units per hour
A change order cost code for all directed work
Overtime documentation captured the week it occurs
Cost to complete updated from the phase variance
$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time
PRICING

FLAT MONTHLY FEE. NO SURPRISES.

Three tiers, priced by your trailing twelve month revenue. Which one you're in depends on how much of the work you want off your desk. We don't bill by the hour, and we don't do payroll. The one-time onboarding fee is in the table.

Built for subs doing $1M to $12M. Above $12.5M we quote.

Last 12 months revenueCoreStrategicPlatinumOne-time onboarding
Under $1M$1,900$3,100$3,300$2,500
$1M to $3.5M$2,600$4,100$5,300$4,500
$3.5M to $6.5M$3,800$5,900$8,300$6,000
$6.5M to $9.5M$5,100$7,600$11,800$7,500
$9.5M to $12.5M$6,100$8,900$14,900$9,000
Above $12.5MQuotedQuotedQuotedQuoted

The onboarding fee covers migrating your books back to the start of your last taxable year and getting you fully operational in 60 days. It's billed once, with your first invoice. It's the same for all three tiers, and it moves with your revenue band. Your first month is prorated, and your monthly engagement starts on the first of the first full month.

Just want the setup? Onboarding only is the same onboarding work with no monthly service after it, one time, at the onboarding fee plus $2,000. Start a monthly engagement later and $2,000 counts toward it. It starts at $4,500, and the price for every band is on the pricing page.

The three tier columns are the whole price. Which one fits depends on how much of the work you want off your desk. No payroll. No hidden line items. The onboarding fee is right here in the table.

  • Online software only: QuickBooks, Sage, Viewpoint and similar. No VPN or hosted desktop.
  • Not in any tier: payroll, pay applications, collections on receivables.
  • Pricing valid through 2027.
Core

CFO work. Your own bookkeeper keeps doing the books.

We build your plan every month. Your team does the work.

You get the CFO work: job costing built to match the way you estimate, a 13 week cash forecast, WIP every month, and a monthly meeting that ends with decisions.

Your bookkeeper still does the books.

Strategic

Core, plus bookkeeping and bank reconciliations, plus job costing and WIP software set up and managed for you. Use your own online accounting software or we supply it, one price.

We build the plan, track it and adjust it every month.

We only work with trade subcontractors. We know what to look for, and we fix problems while they're still small. Everything in Core, plus the bookkeeping and bank reconciliations done for you, and the job costing and WIP software set up, loaded with your cost codes, and managed every month. Use your own online software, or move to ours and we pay for it.

Our team does the bookkeeping and the reconciliations. We don't do payroll.

Platinum

Strategic, plus a controller who handles payables and receivables the way an in-house controller would. You approve every payment.

We manage the money side for you, every week.

Everything in Strategic, plus our team does the controller work. We handle your bills and receivables the way an in-house controller would: we call vendors, pay the bills and keep the accounting current. We plan the cash flow first, and you approve every payment because it is your money.

Our team does the payables and receivables. We don't do payroll, pay applications or collections.

COMMON QUESTIONS

FREQUENTLY ASKED.

Compare estimated to actual labor hours on your last five finished projects, by phase. If the same phase types come in 10 to 20 percent over estimate every time, you have a production rate problem or a nonproductive time problem. That's more than a few bad jobs. Pull one estimate and compare the production rate it assumed to what the timecards say the crew did.

It varies by trade and project type, and typical commercial field trades are 10 to 18 percent. It goes higher on projects with significant travel between work areas, on equipment intensive trades, and where inspection holds are frequent. If your estimate assumes 5 percent and the actual is 15 percent, every labor line is understated by roughly 12 percent.

Yes. Phase level labor tracking is the foundation of the CFOS job profitability system. Actual labor cost by phase is compared to estimated monthly from closed books, and phase variances are flagged in the cost to complete at month two while adjustments are still possible.

Three tiers, and which one you are in depends on how much of the work you want off your desk. On Core we build your plan every month and your team does the work: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. On Strategic we build the plan, track it and adjust it every month: our team does the bookkeeping and the bank reconciliations, and the job costing and WIP software is set up and managed for you, on your own online software or ours. On Platinum we manage the money side for you every week: our team handles your bills and receivables the way an in-house controller would, and you approve every payment. We don't do payroll.

Sixty days. We migrate your books back to the start of your last taxable year and build your job costing structure from scratch, and on Strategic and Platinum we set up the job costing and WIP software too. You're fully up and working in two months. The onboarding fee is one time, the same for every tier, and set by your revenue band.
WHAT THIS TIES INTO
Josh Luebker, SPM The Construction CFO
Josh Luebker
FRACTIONAL CFO · SPM THE CONSTRUCTION CFO

Josh Luebker is a master electrician turned construction CFO, president of SPM The Construction CFO and author of CONTROL: C.F.O.S. Construction Financial Operating System.

WHICH OF THE FIVE IS COSTING YOU THE MOST?

Twenty minutes of questions about how you estimate labor, how time gets coded, and who watches the variance while the job's still in progress. No sale and no proposal. If Josh can help, you'll set a longer call.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute call

20 minutes. No pitch or proposal. Josh asks questions to find out if he can help.

OR GET THE WIP SCHEDULE TEMPLATE. NO CALL NEEDED.