ELECTRICAL CASH FLOW

GEAR BUYOUT HAPPENS BEFORE BILLING CAN CATCH UP.

QUICK ANSWER

Electrical contractors have to lock in switchgear and transformer pricing months before installation, but billing recovery doesn't open up until the equipment is set and inspected. The cash goes out in month two and the billing comes back in month seven or eight. Without proper LOC sizing and a stored materials line in the SOV from contract start, contractors fund a $200K to $800K material hole on major jobs out of operating cash.

Nothing here is a discipline problem or a bidding problem. The buyout decision is correct, the price protection is worth having, and the job is profitable at closeout. What's missing is a contract line that lets you bill for equipment you already paid for and a credit line sized to the months in between. Both of those get set at contract execution, which means the window to fix a job closes the day it's signed. After that you're managing a hole rather than preventing one, and every tool for managing it costs money.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-08-07
THE DEFINITION

WHAT IT MEANS.

Material buyout timing is the stretch between the day an electrical contractor pays for switchgear and conduit and the day the contract finally lets him bill for it.

Commercial electrical work is material heavy. Switchgear, transformers, and distribution equipment run 30% to 50% of total project cost, and all of it has to be ordered months before anybody sets it. Medium voltage switchgear runs 20 to 52 weeks from order to delivery and transformers run 16 to 40 weeks, so contractors order early, often before contract execution, to lock the price. That protects the bid and it creates cash outflow with no matching billing event for months.

This isn't a cash flow problem in the traditional sense. It's a timing problem with a structural fix. Nothing about the job is unprofitable and nothing about the buyout decision is wrong. The contract simply has no vehicle in it for billing money you've already spent.

3 REASONS YOUR CASH IS GONE

WHERE THE MONEY WENT.

01

Switchgear deposits come due long before installation billing

Manufacturers want a large deposit at order, and the order has to go in months before the gear reaches the site. Installation billing doesn't open up until the equipment is set, terminated, energized, and inspected. That puts your money out the door 4 to 6 months before the contract lets you ask for any of it back. On the bank statement it reads as a mysterious cash drain if it's not in the forecast and not sized into the LOC.

02

Price lock buyout creates inventory float with no billing vehicle

Conduit, wire, and raceway on large commercial jobs run $200,000 to $600,000. Buying early locks in the bid price and creates inventory with no billing event behind it until installation happens. The material sits in a warehouse or a laydown yard, already paid for, with nothing billed to the GC against it. Stored materials billing is the fix, and it's an SOV line structure that has to be negotiated before contract execution.

03

The LOC is sized to revenue instead of to material float

Most electrical contractors size the line of credit on a general sense of revenue and not on the peak cash deficit their buyout schedule creates. Those two figures aren't close to each other. Peak deficit happens when switchgear deposits, conduit buyout, and payroll all overlap before a major billing clears, and a revenue based rule of thumb never sees it coming.

THE ARITHMETIC

WHAT IT LOOKS LIKE IN DOLLARS.

The 2,000A switchboard

A 2,000A switchboard costs $180,000 to $400,000. Manufacturers require a 30% to 50% deposit at order, which is $54,000 to $200,000, with the balance due on delivery 20 to 52 weeks later. Installation billing doesn't happen until the gear is set, terminated, energized, and inspected, 4 to 6 months after that deposit went out. On a $3M electrical contract with $900K in switchgear, deposits of $270K to $450K can sit outstanding for months before any billing recovery.

Peak cash deficit on a $5M backlog

Peak cash deficit happens when switchgear deposits, conduit buyout, and payroll overlap before a major billing clears. On a $5M electrical backlog with 40% material content and early buyout, peak deficit can reach $600,000 to $900,000 at one point in the year. If the LOC is sized at $400,000 because that felt about right against revenue, the difference gets funded by paying suppliers late and giving up discounts.

What abandoning early buyout costs

When early buyout keeps creating cash problems, PMs stop doing it and buy closer to installation, which means absorbing escalation. A job bid at $12/LF for wire that now costs $14/LF is a 16% material cost increase on a line item that might be $300K of a $2M job. That's $48K gone on one material category alone, and it's permanent, unlike the interest on a properly sized LOC draw.

WHERE CONTRACTORS GET MISLED

WHAT TO FIX INSTEAD.

The structure is what fails, and cash flow is only where you notice

The observation is right and the diagnosis is wrong. The symptom comes from a buyout timing structure with no matching billing vehicle and no LOC capacity behind it. Fix the structure, meaning stored materials SOV lines, LOC sizing, and buyout timing carried in the forecast, and the symptom goes away without anybody changing how they buy.

The answer isn't to stop buying material early

Early buyout protects your bid price against real copper, steel conduit, and wire escalation. Giving it up trades a timing problem for a margin problem, and the margin problem is the permanent one. The fix is building a billing structure around early buyout rather than abandoning the practice that protects the job.

Most GCs will approve stored materials billing

Some won't, but most will if it's in the contract from the start. Requesting stored materials billing after the SOV is executed loses about 80% of those negotiations. Requesting it at contract execution with proper documentation gets approved far more often than most contractors assume, because at that point it's a line item instead of a favor.

WHAT YOU GET

THE OUTPUTS, NAMED.

A stored materials SOV line negotiated into every contract at execution, covering switchgear, transformers, and bulk conduit and wire buyout
The buyout schedule mapped into the 13 week cash flow forecast by job, with deposit dates, balance due dates, and installation billing events in one view
LOC sized against the real peak cash deficit, modeled from buyout timing and payroll overlap instead of a revenue rule of thumb
Job cost tracked at the material level, with switchgear and major equipment on their own cost codes so buyout spend doesn't blur into install labor variance
Vendor payment timing sequenced so supplier payments follow GC payments rather than precede them, wherever contract terms allow
A go/no-go buyout analysis at award covering material content percentage, lead times, stored materials approval odds, and LOC headroom before the first PO goes out
$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time
PRICING

FLAT MONTHLY FEE. NO SURPRISES.

Three tiers, priced by your trailing twelve month revenue. Which one you're in depends on how much of the work you want off your desk. No hourly billing, no payroll, and no add-ons.

Last 12 months revenueMonthly fee
Up to $1M$1,900 to $2,900
$1M to $3.5M$2,600 to $3,900
$3.5M to $6.5M$3,800 to $5,700
$6.5M to $9.5M$5,100 to $7,100
$9.5M to $12.5M$6,100 to $8,500
$12.5M to $15.5M$7,400 to $11,000
$15.5M to $18.5M$9,400 to $13,500
$18.5M+Quoted individually

Range reflects the three tiers below. Which one you're in depends on how much of the work you want off your desk. No payroll. No hidden line items.

Core

You stop guessing.

You get the CFO work. Job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a meeting every month that ends in decisions rather than a report.

Your bookkeeper keeps doing the books.

Executive

You stop touching the books.

Everything in Core, and we run the bookkeeping and the controllership as well. Nobody in your office is answering coding questions or chasing a reconciliation at month end.

We do the books. No payroll.

Strategic

Every job shows its margin while it's still running.

Everything in Executive, plus the job costing and WIP platform set up, loaded with your cost codes, and managed for you every month. You never have to learn it.

We do the job costing.

COMMON QUESTIONS

FREQUENTLY ASKED.

Three tiers, and which one you are in depends on how much of the work you want off your desk. Core is where you stop guessing: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. Executive is where you stop touching the books, because we run the bookkeeping and the controllership as well. Strategic is where every job shows its margin while it is still running, because the job costing and WIP platform is set up and managed for you. No payroll. No scope gaps.
Sixty days. We migrate your books back to the start of your last taxable year, set up ControlQore, and build your job costing structure from scratch. Fully operational in two months.
WHAT THIS TIES INTO
Josh Luebker, The Construction CFO
Josh Luebker
FRACTIONAL CFO · THE CONSTRUCTION CFO

Former commercial project manager and master electrician: 150+ projects worth $2.1B combined, from $50,000 to $300M. Now fractional CFO to commercial subcontractors.

BUYOUT TIMING IS A STRUCTURE PROBLEM. IT IS FIXABLE.

Stored materials billing, LOC sizing around your real material float, and buyout timing carried in the cash flow forecast. Built in 60 days. You buy the gear, and we make sure the billing structure is in place before it reaches the site.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute diagnostic

20 minutes. No sales pressure. We will tell you exactly what's broken before we talk about anything else.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.