ELECTRICAL CASH FLOW

GEAR BUYOUT HAPPENS BEFORE BILLING CAN CATCH UP.

QUICK ANSWER

Electrical contractors have to lock in switchgear and transformer pricing months before installation, but billing recovery doesn't open up until the equipment is set and inspected. The cash goes out in month two and the billing comes back in month seven or eight. Without proper LOC sizing and a stored materials line in the SOV from contract start, contractors fund a $200K to $800K material hole on major jobs out of operating cash.

Nothing here is a discipline problem or a bidding problem. The buyout decision is correct, the price protection is worth having, and the job is profitable at closeout. What's missing is a contract line that lets you bill for equipment you already paid for and a credit line sized to the months in between. Both of those get set at contract execution, which means the window to fix a job closes the day it's signed. After that you're managing a hole rather than preventing one, and every tool for managing it costs money.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-10-19
THE DEFINITION

WHAT IT MEANS.

Material buyout timing is the stretch between the day an electrical contractor pays for switchgear and conduit and the day the contract finally lets him bill for it.

Commercial electrical work is material heavy. Switchgear, transformers, and distribution equipment are 30% to 50% of total project cost, and all of it has to be ordered months before anybody sets it. Medium voltage switchgear takes 20 to 52 weeks from order to delivery and transformers take 16 to 40 weeks, so contractors order early, often before contract execution, to fix the price. That protects the bid and it creates cash outflow with no matching billing event for months.

This isn't a cash flow problem in the traditional sense. It's a timing problem with a structural fix. Nothing about the job is unprofitable and nothing about the buyout decision is wrong. The contract simply has no vehicle in it for billing money you've already spent.

3 REASONS YOUR CASH IS GONE

WHERE THE MONEY WENT.

01

Switchgear deposits come due long before installation billing

Manufacturers want a large deposit at order, and the order has to go in months before the gear reaches the site. Installation billing doesn't open up until the equipment is set, terminated, energized, and inspected. That puts your money out the door 4 to 6 months before the contract lets you ask for any of it back. On the bank statement it reads as a mysterious cash drain if it's not in the forecast and not sized into the LOC.

02

Price lock buyout creates inventory float with no billing vehicle

Conduit, wire, and raceway on large commercial jobs cost $200,000 to $600,000. Buying early fixes the bid price and creates inventory with no billing event behind it until installation happens. The material is stored in a warehouse or a laydown yard, already paid for, with nothing billed to the GC against it. Stored materials billing is the fix, and it's an SOV line structure that has to be negotiated before contract execution.

03

The LOC is sized to revenue instead of to material float

Most electrical contractors size the line of credit on a general sense of revenue and not on the peak cash deficit their buyout schedule creates. Those two figures aren't close to each other. Peak deficit happens when switchgear deposits, conduit buyout, and payroll all overlap before a major billing clears, and a revenue based rule of thumb never sees it coming.

THE MATH

WHAT IT LOOKS LIKE IN DOLLARS.

The 2,000A switchboard

A 2,000A switchboard costs $180,000 to $400,000. Manufacturers require a 30% to 50% deposit at order, which is $54,000 to $200,000, with the balance due on delivery 20 to 52 weeks later. Installation billing doesn't happen until the gear is set, terminated, energized, and inspected, 4 to 6 months after that deposit went out. On a $3M electrical contract with $900K in switchgear, deposits of $270K to $450K can stay outstanding for months before any billing recovery.

Peak cash deficit on a $5M backlog

Peak cash deficit happens when switchgear deposits, conduit buyout, and payroll overlap before a major billing clears. On a $5M electrical backlog with 40% material content and early buyout, peak deficit can reach $600,000 to $900,000 at one point in the year. If the LOC is sized at $400,000 because that felt about right against revenue, the difference gets funded by paying suppliers late and giving up discounts.

What abandoning early buyout costs

When early buyout keeps creating cash problems, PMs stop doing it and buy closer to installation, which means absorbing escalation. A job bid at $12/LF for wire that now costs $14/LF is a 16% material cost increase on a line item that might be $300K of a $2M job. That's $48K gone on one material category alone, and it's permanent, unlike the interest on a properly sized LOC draw.

WHERE CONTRACTORS GET MISLED

WHAT TO FIX INSTEAD.

The structure is what fails, and cash flow is only where you notice

The observation is right and the diagnosis is wrong. The symptom comes from a buyout timing structure with no matching billing vehicle and no LOC capacity behind it. Fix the structure, meaning stored materials SOV lines, LOC sizing, and buyout timing reflected in the forecast, and the symptom goes away without anybody changing how they buy.

The answer isn't to stop buying material early

Early buyout protects your bid price against real copper, steel conduit, and wire escalation. Giving it up trades a timing problem for a margin problem, and the margin problem is the permanent one. The fix is building a billing structure around early buyout rather than abandoning the practice that protects the job.

Most GCs will approve stored materials billing

Some won't, but most will if it's in the contract from the start. Requesting stored materials billing after the SOV is executed loses about 80% of those negotiations. Requesting it at contract execution with proper documentation gets approved far more often than most contractors assume, because at that point it's a line item instead of a favor.

WHAT YOU GET

THE OUTPUTS, NAMED.

A stored materials SOV line negotiated into every contract at execution, covering switchgear, transformers, and bulk conduit and wire buyout
The buyout schedule mapped into the 13 week cash flow forecast by job, with deposit dates, balance due dates, and installation billing events in one view
LOC sized against the real peak cash deficit, modeled from buyout timing and payroll overlap instead of a revenue rule of thumb
Job cost tracked at the material level, with switchgear and major equipment on their own cost codes so buyout spend doesn't blur into install labor variance
Vendor payment timing sequenced so supplier payments follow GC payments rather than precede them, wherever contract terms allow
A go/no-go buyout analysis at award covering material content percentage, lead times, stored materials approval odds, and LOC headroom before the first PO goes out
$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time
PRICING

FLAT MONTHLY FEE. NO SURPRISES.

Three tiers, priced by your trailing twelve month revenue. Which one you're in depends on how much of the work you want off your desk. No hourly billing. No payroll. The one-time onboarding fee is right here in the table.

Last 12 months revenueMonthly feeOne-time onboarding
Under $1M$1,900 to $3,300$1,000
$1M to $3.5M$2,600 to $5,300$1,500
$3.5M to $6.5M$3,800 to $8,300$3,000
$6.5M to $9.5M$5,100 to $11,800$4,500
$9.5M to $12.5M$6,100 to $14,900$6,000
$12.5M to $15.5M$7,400 to $17,650$7,500
$15.5M to $18.5M$9,400 to $22,400$9,000
$18.5M+Quoted individuallyQuoted individually

The onboarding fee covers migrating your books back to the start of your last taxable year and getting you fully operational in 60 days. It's billed once, with your first invoice. It's the same for all three tiers. Your first month is prorated, and your monthly engagement starts on the first of the first full month.

Range reflects the three tiers below. Which one you're in depends on how much of the work you want off your desk. No payroll. No hidden line items. The onboarding fee is right here in the table.

Core

You stop guessing.

You get the CFO work. Job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a meeting every month that ends in decisions and never in a report.

Your bookkeeper still does the books.

Strategic

Every job shows its margin while it is still open.

Everything in Core, plus the bookkeeping and bank reconciliations done for you, and the job costing and WIP software set up, loaded with your cost codes, and managed every month. Use your own online software, or move to ours and we cover it.

A bookkeeper we choose does the books and reconciliations. No payroll.

Platinum

You approve, and the money side gets handled.

Everything in Strategic, plus a controller we choose who handles your bills and receivables for you the way an in-house controller would. They call vendors, pay the bills and keep the accounting current. We plan the cash flow first, and you approve every payment because it is your money.

A controller we choose does the payables and receivables. No payroll, no pay applications, no collections.

COMMON QUESTIONS

FREQUENTLY ASKED.

Three tiers, and which one you are in depends on how much of the work you want off your desk. Core is where you stop guessing: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. Strategic is where every job shows its margin while it is still open: a bookkeeper we choose does the books and the bank reconciliations, and the job costing and WIP software is set up and managed for you, on your own online software or ours. Platinum is where you approve and the money side gets handled: a controller we choose handles your bills and receivables the way an in-house controller would, and you approve every payment. No payroll. No scope gaps.

Sixty days. We migrate your books back to the start of your last taxable year, set up ControlQore, and build your job costing structure from scratch. Fully operational in two months.
WHAT THIS TIES INTO
Josh Luebker, SPM The Construction CFO
Josh Luebker
FRACTIONAL CFO · SPM THE CONSTRUCTION CFO

Josh Luebker is a master electrician turned construction CFO, president of SPM The Construction CFO and author of CONTROL: C.F.O.S. Construction Financial Operating System.

BUYOUT TIMING IS A STRUCTURE PROBLEM. IT'S FIXABLE.

Twenty minutes of questions about when you buy material, how stored materials get billed, and what your line of credit looks like during the float. No sale and no proposal. If Josh can help, you'll set a longer second call.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute call

20 minutes. Nothing gets sold on this call and nothing gets proposed. Josh asks questions to work out whether he can help at all.

OR GET THE SOV AND PAY APPLICATION TEMPLATE. NO CALL NEEDED.