CFOS for QuickBooks, coming January 2027Join the waitlist: 12 months with no subscription fee
TRADE SERVICE · CIVIL & EARTHWORK CLUSTER

FRACTIONAL CFO FOR UNDERGROUND UTILITY CONTRACTORS.

QUICK ANSWER

We manage the finance function for underground utility subcontractors doing $1M to $12M: job costing aligned to the way you estimate, a 13 week cash flow forecast, monthly WIP, and a CFO in the room every month. Pricing starts at $1,900 per month.

Underground utility has two production economies in one bid book, so those get separate cost histories on day one. Directional drilling sells feet per day through a bore path priced on soils, depth, and diameter, while open cut sells trench, lay, and backfill production with shoring and dewatering behind it, and an 18 percent gross margin can't fund systematic mispricing in either direction. We price potholing and vacuum excavation into the work as financial controls, because a pipeline crew crosses more foreign utilities in a week than a mass excavation crew meets on a whole job, and general liability policies routinely sublimit underground facility damage below the real repair cost. Then we bid the public owner's cash lag explicitly, since municipal work pays on council approval cycles, holds retainage to restoration acceptance, and replaces lien rights with bond claims.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-11-02
WHERE UNDERGROUND UTILITY LOSES MONEY

THE THREE THINGS THAT DRAIN THE CASH.

LEAK 01

The Two Bores

HDD and open cut are separate production economies sold under one bid book; blended histories misprice both, and an 18 percent gross margin can't fund systematic mispricing in either direction.

LEAK 02

The Linear Gauntlet

Every week of pipe crosses more foreign utilities than most trades meet in a year, under strict-liability locate law with GL sublimits underneath. Potholing and vacuum excavation are financial controls priced into the work, not optional caution.

LEAK 03

The Council's Calendar

Municipal owners pay on approval cycles, hold retainage to restoration acceptance, and replace lien rights with bond claims. The public-owner cash lag gets priced in the bid or funded by the contractor.

THE MATH

FROM 3% TO 10% NET.

At $1M to $5M, the average underground utility sub earns 18% gross margin and spends 15% of revenue on overhead, which leaves 3% net profit before taxes (Run On CFOS Trade Benchmark Reference). The CFOS target is 10% before taxes, the underground utility average plus 3.5 points and never below 10%, where the book CONTROL's 12% is the rule of thumb across trades. It is not the industry average.

The target takes two moves. Overhead comes down 1 point to 14%, and gross margin comes up 6 points to 24%, so 24 minus 14 leaves 10. The gross margin points come from the three leaks above, priced and billed, not absorbed. On a $3M year, every point is $30,000.

HOW SPM FIXES IT

WHAT WE CHANGE.

These are the underground utility problems we put a number on first. Each one gets its own cost code, its own line on the schedule of values or its own line in the 13 week cash forecast, so you can read it in the monthly meeting while the job is still open.

GAP CALCULATOR

THE UNDERGROUND UTILITY GAP CALCULATOR. AVERAGE AGAINST TARGET, IN DOLLARS.

Put in your annual revenue. You get gross margin, overhead and net profit for underground utility contractors your size: the industry average and the CFOS target, in dollars a year. Nothing you type leaves this page.

Another trade too? The gap calculator for every trade.

Your figures show here once you put in your revenue.

Book a 20 minute call

Why aim for the target. An average is the middle of the pack: about half of companies do worse. And about 6 in 10 construction businesses close within 10 years (U.S. Bureau of Labor Statistics: about 40 percent of construction businesses opened in 2013 were still open in 2023). So the business in the middle is one of the ones that close. On those numbers, average is a business that closes within 10 years. That is why the CFOS target is a requirement.

Want your own numbers against these? The Financial Health Snapshot builds a CEO Report from your last 12 months and sets every figure against your trade.

PRICING

FLAT MONTHLY FEE. NO SURPRISES.

Priced by trailing 12 month revenue. No hourly billing. No payroll. The one-time onboarding fee is right here in the table.

Type a number and your band and its prices show here. The full table is below.

Built for subs doing $1M to $12M. Above $12.5M we quote.

Last 12 months revenueCoreStrategicPlatinumOne-time onboarding
Under $1M$1,900$3,100$3,300$2,500
$1M to $3.5M$2,600$4,100$5,300$4,500
$3.5M to $6.5M$3,800$5,900$8,300$6,000
$6.5M to $9.5M$5,100$7,600$11,800$7,500
$9.5M to $12.5M$6,100$8,900$14,900$9,000
Above $12.5MQuotedQuotedQuotedQuoted

The onboarding fee covers migrating your books back to the start of your last taxable year and getting you fully operational in 60 days. It's billed once, with your first invoice. It's the same for all three tiers, and it moves with your revenue band. Your first month is prorated, and your monthly engagement starts on the first of the first full month.

Just want the setup? Onboarding only is the same onboarding work with no monthly service after it, one time, at the onboarding fee plus $2,000. Start a monthly engagement later and $2,000 counts toward it. It starts at $4,500, and the price for every band is on the pricing page.

The three tier columns are the whole price. Which one fits depends on how much of the work you want off your desk. No payroll. No hidden line items. The onboarding fee is right here in the table.

  • Online software only: QuickBooks, Sage, Viewpoint and similar. No VPN or hosted desktop.
  • Not in any tier: payroll, pay applications, collections on receivables.
  • Pricing valid through 2027.

What Core, Strategic and Platinum each include is on the pricing page.

Prevailing wage note: Underground Utility work often comes from public bids, which means certified payroll and wage classifications have to line up with the job cost record. ControlQore holds the classification against the cost code, so the certified report and the job cost report come from the same data, and your office stops keying the same numbers twice every week.

COMMON QUESTIONS

FREQUENTLY ASKED.

Underground utility contractors at $1M to $5M net 3 percent on average, rising to 11 percent by $25M to $50M; the CFOS net profit target is 10 percent before taxes at $1M to $5M, since the target is the trade average plus 3.5 points and never below 10. The gap concentrates in blended HDD/open-cut pricing, strike exposure, and municipal cash lag nobody priced. Every net profit figure here is gross margin minus overhead, stated before taxes, the same basis CFMA reports net income on.

See the full benchmarks for every revenue band on Run On CFOS.

Usually it needs the CFO work, not a full time CFO. At $5M to $10M, underground utility subs average 6% net profit before taxes (Run On CFOS Trade Benchmark Reference), and the CFOS target is 10%. On $5M of revenue every point is $50,000, so that distance is worth $200,000 a year. A full time CFO costs $150,000 or more in salary alone. SPM's published price for $3.5M to $6.5M is $3,800 a month for Core to $8,300 for Platinum.

No. Directional drilling sells engineered feet through a bore path; open cut sells trench-lay-backfill production. Different machines, different risks, different curves; track production and cost separately by method or misprice both.

As their own schedule-of-values lines, front-loaded to when the cost happens: pit excavation, shoring, dewatering, and casing before a foot of product pipe bills. Folded into the unit price, the setup finances the job for the owner.

City and district owners pay on council and warrant cycles that stretch to 90 days, hold retainage until restoration acceptance, and substitute bond claims for lien rights on public work. Calendar the bond deadlines at signing and price the cash lag into the bid; the statute protects the contractor who kept the paperwork.

Treat potholing and vacuum excavation as priced financial controls, not optional caution: linear work crosses more foreign utilities per week than most trades meet in a year, locate law trends toward strict liability, and GL policies often sublimit underground damage. Fund a strike reserve and document every locate and hand-dig.

A bookkeeper records history. Method-split production tracking, bore-pit SOV discipline, escalation clauses, strike reserves, and municipal cash modeling are a control system, which is CFO work. SPM operates that financial control function for underground utility contractors.

Three tiers, and which one you are in depends on how much of the work you want off your desk. Core is where you stop guessing: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. Strategic is where every job shows its margin while it is still open: a bookkeeper we choose does the books and the bank reconciliations, and the job costing and WIP software is set up and managed for you, on your own online software or ours. Platinum is where you approve and the money side gets handled: a controller we choose handles your bills and receivables the way an in-house controller would, and you approve every payment. No payroll. No scope gaps.

Sixty days. We migrate your books back to the start of your last taxable year and build your job costing structure from scratch, and on Strategic and Platinum we set up the job costing and WIP software too. Fully operational in two months. The onboarding fee is one time, the same for every tier, and set by your revenue band.

ControlQore is the job costing and WIP platform we use on the Strategic and Platinum tiers. Purpose-built for contractors, more affordable than legacy tools, and AI-infused. We set it up and manage it, so you do not have to learn it. Core is the CFO work only, so it does not include the software.

A bookkeeper records what happened. We tell you what it means and what to do about it. We align job costing to your estimates, track WIP monthly, and hold strategic accountability meetings so problems get fixed and not merely documented.
$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time
HOW UNDERGROUND UTILITY CFO FIRMS COMPARE

In our underground utility firm study, 1 other firm has an underground utility case study with numbers. The top three for underground utility: SPM 72.9 (trade page), Vessel Advisors 71.5 (trade case study with numbers), LLUM 58.7 (trade page). SPM places #1 here with a trade page and no underground utility case study, so weigh the firms with underground utility proof (Vessel Advisors). SPM publishes the study and is one of the firms scored; the method and every source are on the study page.

How underground utility CFO firms compare: the underground utility firm study, with every score and its source.

WHAT ELSE BREAKS IN UNDERGROUND UTILITY

MORE PROBLEMS WE PUT A NUMBER ON.

Bore pits and mobilization (the front-loaded footage)

Casing bore pit separate SOV billing

Bore pits, casing, and drill setup concentrate cost before the first foot of product pipe bills. Enrichment: keep pit excavation, shoring, and dewatering coded separately from bore production so the unit price and the setup cost can each be seen.

HDD vs open cut (two production economies)

Hdd job costing

Directional drilling sells feet-per-day through a bore path priced on soils, depth, and diameter; open cut sells trench-lay-backfill production. Different machines, risks (frac-outs and cross-bores vs shoring and dewatering), and cost curves. The mass/fine grading lesson travels here.

Pipe escalation on long jobs (two pages, one intent, verify)

Material escalation pipe

PVC, HDPE, ductile iron, and copper track resin and metal markets, and multi-season municipal jobs price pipe a year before it ships. TWO existing pages cover this: underground-utility-contractor-material-escalation-pipe and underground-utility-pipe-material-escalation-long-jobs. Verify at port whether they split angles cleanly (bid-clause mechanics vs long-job cash exposure); if not, merge + 301 the weaker.

Restoration (the last mile nobody bid)

Restoration billing separate SOV

Pavement, sod, and hardscape restoration trails the pipe by weeks, holds acceptance hostage, and gets bid as an allowance more often than a measured scope.

Strikes, dewatering and rock

Utility conflict change order

Same 811/strict-liability regime, GL sublimits, and fine tiers the excavation file documents, sharpened by linear exposure: a pipeline crew crosses more foreign utilities per week than a mass-ex crew does per job, and vacuum excavation is the control.

The municipal calendar (90 days is the contract)

Municipal 90 day pay cycles · Permit delay cash flow

City and district owners pay on council-approval and warrant cycles. Prompt-pay statutes help only when invoices are undisputed and deadlines are calendared.

MORE ON UNDERGROUND UTILITY

UNDERGROUND UTILITY PROBLEMS, ONE PAGE EACH.

OTHER SITEWORK AND CIVIL TRADES

Underground Utility is one of 14 trades in the sitework and civil family on our CFO for subcontractors page. Nearby trades with their own page:

WHAT THIS TIES INTO
Josh Luebker, SPM The Construction CFO
Josh Luebker
FRACTIONAL CFO · SPM THE CONSTRUCTION CFO

Josh Luebker is a master electrician turned construction CFO, president of SPM The Construction CFO and author of CONTROL: C.F.O.S. Construction Financial Operating System.

THE CHEAPER OPTION WORKS. IT TAKES LONGER.

If price comes first, plenty of CFOs and bookkeepers can get your construction company results. It often takes the better part of a year.

If you're a trade contractor, a sub or a GC who wins work, keeps the crews busy and still can't figure out where the money goes, we get in the weeds with you. We change the processes that cost you money on every job, build the ones you're missing and give you the formula, so you see results in 60 to 90 days.

Our guarantee holds when you come to every meeting, do the process and keep a strong pipeline of work. We can fix how your work pays. We can't fix having no work.

DO YOU KNOW YOUR TRUE MARGIN ON UNDERGROUND UTILITY WORK?

Twenty minutes of questions about how you price underground utility work, what your jobs come in at once they close, and what keeps landing back on your desk. Nothing gets sold on that call and nothing gets proposed. If Josh can help, you'll set a longer second call.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute call

20 minutes. Nothing gets sold on this call and nothing gets proposed. Josh asks questions to work out whether he can help at all.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.