Skip to main content
JOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOSUBCONTRACTOR FINANCEOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQORERETENTION RECOVERYEQUIPMENT COST BASIS13-WEEK FORECAST JOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOSUBCONTRACTOR FINANCEOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQORERETENTION RECOVERYEQUIPMENT COST BASIS13-WEEK FORECAST
The Construction CFO SCHEDULE A FREE CALL
CIVIL CLUSTER · TRADE OPERATING SYSTEM

WHY SITEWORK CONTRACTORS RUN OUT OF CASH.

QUICK ANSWER

Sitework contractors run out of cash because one contract hides several trades inside it. Clearing, grading, utilities, and paving each have their own cost structure, but tracked as one blended number a winning phase masks a losing one. Add remobilization between scopes and six-figure retention on long jobs, and the bank account empties while the job still shows a profit.

A sitework contract bundles clearing, mass and fine grading, underground utilities, and sometimes paving into one job, which means several cost structures and several production rates living under a single number. Track the whole site as one bucket and a grading phase earning 25 percent will quietly cover a utility phase losing 20 percent. You never reprice the utility work because you never see it lose. Add the remobilization between scopes and retention of 5 to 10 percent on a $2M site, $100K to $200K held for months, and the cash squeeze is built in. CFOS costs each phase on its own so the loser cannot hide.

BY JOSH LUEBKER Published: February 2026 Updated: June 2026
THE FAILURE MODE

WHY SITEWORK EATS CASH.

Sitework is really several trades sold as one. A single contract can carry clearing, mass and fine grading, underground utilities, and sometimes paving. Each of those has a different cost structure, a different production rate, and a different way of failing, and all of it hides inside one blended job number.

When the whole site is tracked as a single bucket, the math averages out. A strong grading phase masks a bleeding utility phase. The job posts a modest profit, the utility pricing never gets fixed, and the same loss repeats on the next site. Meanwhile each scope tends to remobilize equipment and crews, and those moves cost thousands that rarely get billed as discrete events.

Sitework jobs are also large and long, which means retention is large and long. Five to ten percent on a $2M site is $100K to $200K held for months past substantial completion, while punch list and closeout drag the final billing and overhead keeps running. The income statement shows a profitable job. The bank account tells a different story.

Gross Margin Target
18-24%
Healthy range at $1M to $12M
Overhead Rate
12-15%
Of revenue, recovered in bids
Net Margin Target
7%+
After real overhead is loaded
3 REASONS YOUR CASH IS GONE

THE MECHANISMS NO ONE PRICES IN.

PHASE BLENDING HIDES LOSERS

One number averages a winner with a loser.

A sitework job tracked as a single number averages a strong phase against a weak one. Utilities can lose 20 percent while grading makes 25 percent, and the blended job still shows a modest profit. You never fix the utility pricing because the loss is never visible, and the same mistake rides along on the next site.

MOBILIZATION ACROSS PHASES

Every scope move is a cost you give away.

Each scope on a site job often remobilizes equipment and crews. Those moves run thousands of dollars and are rarely billed as discrete events, so they erode margin quietly across a long-duration job. Five phases can mean five mobilizations the bid treated as one.

RETENTION AND CLOSEOUT DRAG

Big long jobs mean big long holds.

Sitework jobs are large and long, so retention is large and long. Five to ten percent on a $2M site is $100K to $200K held for months past substantial completion. Punch list and closeout drag the final billing while overhead keeps running, and the last 10 percent of the cash is the hardest to collect.

WHERE CONTRACTORS GET MISLED

THE WRONG DIAGNOSIS COSTS YOU YEARS.

Wrong answer 1: sitework is just complicated. It is, which is the argument for phase-level costing, not an excuse for blended numbers that hide the loss.

Wrong answer 2: the GC schedule killed us. Schedule slippage hurts, but without phase costing you cannot show which scope the slippage actually cost you, or bill for it.

Wrong answer 3: one bad phase was a fluke. If you cannot see phase margins, you cannot know it was a fluke. Most of the time it is a pricing pattern that repeats.

The real answer: there is no phase-level job costing and no schedule of values built to the real scopes. The whole site is one bucket, so the losers stay hidden. CFOS splits the bucket.

HOW CFOS FIXES IT

SAME BUSINESS. BETTER SYSTEM.

CFOS is the Construction Financial Operating System. For sitework contractors it installs as a set of specific deliverables, not advice:

Job costing broken out by phase so clearing, grading, utilities, and paving each show their own margin
Schedule of values structured to bill each phase as it completes, not back-loaded to the end
Mobilization billed as discrete line items for each remobilization
Retention tracked per job with a closeout collection routine
Real overhead rate loaded into every bid
13-week cash forecast around long-duration billing and retention release
PRICING

FLAT MONTHLY FEE. NO SURPRISES.

Two tiers based on trailing 12-month revenue. No hourly billing. No payroll. No add-ons. Everything included in the flat monthly fee.

RevenueCore FinancialExecutive Financial
Under $1M$1,900/mo$2,900/mo
$1M–$3M$2,600/mo$3,600/mo
$4M–$6M$3,800/mo$5,500/mo
$7M–$9M$5,100/mo$6,900/mo
$10M–$12M$6,100/mo$8,500/mo
$13M+QuotedQuoted
What's Included →
COMMON QUESTIONS

FREQUENTLY ASKED.

Sitework bundles clearing, grading, utilities, and sometimes paving into one contract, so multiple cost structures hide inside one blended job number. Tracked as a single bucket, a grading phase making 25 percent can mask a utility phase losing 20 percent, and you find out at closeout. Each scope remobilizes equipment and crews at a cost rarely billed as its own line. Retention of 5 to 10 percent on a $2M site is $100K to $200K held for months while closeout drags the final billing and overhead keeps running. The income statement shows profit because the phase-level losses and mobilization never surface.
CFOS breaks job costing out by phase so clearing, grading, utilities, and paving each show their own margin, structures your schedule of values to bill each phase as it completes instead of back-loading, bills every remobilization as a discrete line, tracks retention per job with a closeout collection routine, loads your real overhead rate into every bid, and runs a 13-week forecast around long-duration billing and retention release.
CFOS serves commercial sitework subcontractors doing $1M–$12M. Core Financial starts at $1,900/month. Executive Financial starts at $2,900/month. Onboarding takes 60 days.
Core Financial includes ControlQore setup, job costing aligned to your estimates, full-service bookkeeping, and bank reconciliations. Executive Financial adds monthly CFO advisory meetings, controllership, and strategic accountability. No payroll. No scope gaps.
60 days. We migrate your books to the start of your last taxable year, set up ControlQore, and build your job costing structure from scratch. Fully operational in two months.
Josh Luebker, The Construction CFO
Josh Luebker
Fractional CFO · The Construction CFO

Former commercial construction project manager and master electrician. Managed 150+ projects totaling $300M+ including data centers, military bases, hospitals, and high-rises. Now fractional CFO for commercial subcontractors doing $1M–$12M through Sulphur Prairie Management. About Josh →  |  LinkedIn →

$2.1M+
Client AR Recovered Since 2023
24
Active Trade Specializations
60 DAYS
Average Onboarding Time
RELATED RESOURCES
CFOS System
Run on CFOS
The Construction Financial Operating System. What it is and how it runs.
CFOS Module
Cash Control System
Payroll, AR, LOC, and cash timing. How CFOS controls the crisis layer.
CFOS Module
Job Profitability System
Why jobs look profitable but lose money. How CFOS shows you the truth.
SYSTEM CONNECTIONS
CFOS SPINE + MODULES
Run on CFOS — Full System Index Job Profitability System Cash Control System Cash Flow Cycle System
RELATED TRADE OS
Civil OSGrading OSUnderground Utility OS
SERVICE LAYER
Fractional CFO for Construction Construction Bookkeeping Construction Controllership

DO YOU KNOW WHICH PHASE IS LOSING MONEY?

We will show you exactly where the cash is leaking on your sitework jobs before we talk about anything else.

BOOK A FREE 30-MIN DIAGNOSTIC →

30 minutes. Free. No sales pressure. We tell you what is broken first.

OR SEE YOUR NUMBERS FIRST → FREE CEO REPORT TOOL
THE CONSTRUCTION CFO
Run on CFOS Cash Control System Sitework Overhead Rate Schedule a Call Josh@ConstructionCFO.net CONTROL Book →
© 2026 SULPHUR PRAIRIE MANAGEMENT · SULPHUR ROCK, AR
0
Josh Luebker, The Construction CFO
JOSH LUEBKER
FOUNDER & CFO

Master electrician and former project manager, 150+ projects and $2.1B+ in commercial work. Now runs the numbers for subcontractors instead of standing on the job site.

LinkedIn About
Stewart Bohrer, The Construction CFO
STEWART BOHRER
VP OF OPERATIONS

Keeps the system running day to day: job costing, WIP, monthly financial reviews, and the follow-through between calls. Josh handles onboarding.

LinkedIn About
LinkedIn YouTube About Run on CFOS