WHY YOU'RE SHORT

TILE & STONE JOBS LOOK PROFITABLE. THE BALANCE SHEET IS STILL THIN.

QUICK ANSWER

Tile & Stone subcontractors run out of cash for reasons specific to how the work is built and billed, on jobs that are making money. The three that cost the most in this trade are below, taken from tile & stone contractor research. Most sit at 75 to 90 days from finishing work to holding the money, and 45 days is achievable.

Cash and profit are measured on different clocks. Your profit and loss records revenue when you invoice and costs when you incur them, while the bank account only knows what cleared. Labour goes out weekly and collects 45 to 90 days later, minus retention. That distance is what a growing, profitable tile & stone company funds out of pocket, and it widens as you grow. The specific things that widen it in this trade are what the rest of this page is about.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-08-06
WHERE THE CASH GOES IN TILE & STONE

WHERE IT LEAKS OUT.

01 · The material deposit float (slabs on a boat)

Stone and specialty tile are deposit-heavy, long-lead, and often imported: fabricated countertop slabs, book-matched stone, and special-order tile tie up five figures between deposit and install, with breakage and dye-lot risk riding along. The flooring cluster's material-float story applies with harder edges: a cracked slab or a short dye lot isn't restocked from a warehouse.

The module that controls this

02 · Last-trade retainage, hard-finish edition

Tile finishes late, and the painting file's math transfers: a 5-to-10 percent hold against a 5.5 percent net floor means the retainage exceeds the profit. Punch scrutiny on visible finish work (grout shade, lippage claims under raking light) gives closeout pressure extra teeth; the drywall cluster's lighting-standard discipline is the cousin argument.

The module that controls this

THE THREE THAT DECIDE THE YEAR

WHAT MOVES MARGIN IN THIS TRADE.

LEAK 01

The Inherited Slab

Tile is rigid; the substrate's sins (out-of-flat, wet, cracked) become the tile contractor's callbacks unless substrate acceptance, prep pricing, and test records are on paper before setting. Request the FF/FL report and the moisture readings at handoff; they exist for exactly this.

LEAK 02

The Slab on the Boat

Deposits out months early, breakage and dye-lot risk in transit, no warehouse restock behind a cracked book-match: the material float is the trade's silent bank loan, and stored-materials terms plus priced attrition allowances are the repayment plan.

LEAK 03

The Flood Test Nobody Billed

Wet areas fail at the membrane, and the bill lands on whoever lacks the test record. A witnessed, photographed, billed flood test before setting is cheap insurance against the most expensive tear-out in the interiors family. (cfos-job-profitability-system) ---

THE NUMBER TO MANAGE

DAYS SALES OUTSTANDING.

Ninety days is weak, 45 is the target, 30 is strong. Nothing else moves cash faster.

PositionDaysWhat it means
Weak90 daysRoughly three months of work funded out of your own pocket.
Target45 daysAchievable on the days you control: submission timing, complete documentation, follow up in week two.
Strong30 daysRequires discipline every month, and it's the cheapest capital available to you.

Moving from 90 days to 45 frees roughly annual revenue divided by 365, times 45 days. At $4M that's about $493,000. At $8M it's about $986,000. That money doesn't come from a bank and it costs no interest, which is why we work the cycle before discussing financing anything.

WHERE YOU SHOULD BE

TILE & STONE BENCHMARKS.

Tile & Stone subcontractors at $1M to $5M net 8 percent, against a CFOS target of 10 percent, set at 10 percent before taxes or 3.5 points better than your trade's average at your revenue, whichever is higher. Working capital should sit at 13 percent of annual revenue, and the monthly close should finish by day 10 so the numbers can still change a decision.

Full tile & stone benchmarks
COMMON QUESTIONS

FREQUENTLY ASKED.

Because the jobs earn before the money comes in. Labour and material go out on a weekly cycle and collect 45 to 90 days later, with 5 to 10 percent held as retention behind that. In tile & stone specifically that distance is widened by the material deposit float (slabs on a boat) and last-trade retainage, hard-finish edition. None of that reads as a loss on any single job, which is why it goes unaddressed.
Three tiers, and which one you are in depends on how much of the work you want off your desk. Core is where you stop guessing: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. Executive is where you stop touching the books, because we run the bookkeeping and the controllership as well. Strategic is where every job shows its margin while it is still running, because the job costing and WIP platform is set up and managed for you. No payroll. No scope gaps.
$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time
WHAT THIS TIES INTO
Josh Luebker, The Construction CFO
Josh Luebker
FRACTIONAL CFO · THE CONSTRUCTION CFO

Former commercial construction project manager and master electrician. Managed 150+ projects worth more than $2.1B combined, with individual jobs from $50,000 to $300M, including data centers, military bases, hospitals, and high-rises. Now fractional CFO for commercial subcontractors doing $1M to $12M through Sulphur Prairie Management.About Josh  | LinkedIn

WHICH WEEK DO YOU RUN SHORT?

Bring your open invoices and your payroll calendar. We will build enough of a forecast on the call to tell you which week is tight and why.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute diagnostic

20 minutes. No sales pressure. We will tell you exactly what's broken before we talk about anything else.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.