SITEWORK JOBS LOOK PROFITABLE. THE CASH IS STILL IN TRANSIT.
Sitework subcontractors have no cash left for reasons specific to how the work is built and billed, on jobs that are making money. The three that cost the most in this trade are below, taken from sitework contractor research. Most are at 75 to 90 days from finishing work to holding the money, and 45 days is achievable.
Cash and profit are measured on different clocks. Your profit and loss records revenue when you invoice and costs when you incur them, while the bank account only knows what cleared. Labour goes out weekly and collects 45 to 90 days later, minus retention. That distance is what a growing, profitable sitework company funds out of pocket, and it widens as you grow. The specific things that widen it in this trade are what the rest of this page is about.
WHERE IT LEAKS OUT.
Sitework often contracts straight with developers, and developer draws follow construction-loan disbursement schedules. When the lender's draw is late, your receivable is late with it, at whatever stage the dirt is in.
Clearing, mass grading, utilities and paving prep each have their own cost curve inside one contract. A flat monthly percent-complete bill underbills the early phases, when most of the iron and trucking cost comes in.
WHAT MOVES MARGIN IN THIS TRADE.
The Lender's Leash
Developer-direct contracts pay on construction-loan draw schedules. When the draw is late, your receivable is late too, and you pay for the gap with your iron on site. Check the developer's credit and draw schedule before you bid.
The Package Blur
Multi-scope contracts don't show quantity variance, and the scope boundary moves. Every undocumented "while you're out there" is production without paper. A directive log and phase-weighted billing keep the package a contract, and keep it from turning into favors.
The Sequence Tax
Every utility crew and inspector who comes through the site can idle your spread. Standby you don't code and document is margin you give away for someone else's delay.
DAYS SALES OUTSTANDING.
Ninety days is weak, 45 is the target, 30 is strong. Nothing else moves cash faster.
| Position | Days | What it means |
|---|---|---|
| Weak | 90 days | Roughly three months of work funded out of your own pocket. |
| Target | 45 days | You can get here on the days you control. Bill on time, send complete paperwork, and follow up in week two. |
| Strong | 30 days | Takes work every month. It's the cheapest money you can get. |
Moving from 90 days to 45 frees roughly annual revenue divided by 365, times 45 days. At $4M that's about $493,000. At $8M it's about $986,000. That money costs no interest and needs no bank. So we fix billing and collections before we talk about financing.
SITEWORK BENCHMARKS.
Sitework subcontractors at $1M to $5M net 3 percent, against the CFOS net profit target, set at your trade's net profit average at your revenue plus 3.5 points, never below 10 percent, before taxes. The working capital target is 13 percent of annual revenue, and the monthly close should finish by day 10 so the numbers can still change a decision.
