WHY YOU'RE SHORT

PLUMBING JOBS LOOK PROFITABLE. THE CASH IS STILL IN TRANSIT.

QUICK ANSWER

Plumbing subcontractors run out of cash for reasons specific to how the work is built and billed, on jobs that are making money. The three that cost the most in this trade are below, taken from plumbing contractor research. Most sit at 75 to 90 days from finishing work to holding the money, and 45 days is achievable.

Cash and profit are measured on different clocks. Your profit and loss records revenue when you invoice and costs when you incur them, while the bank account only knows what cleared. Labour goes out weekly and collects 45 to 90 days later, minus retention. That distance is what a growing, profitable plumbing company funds out of pocket, and it widens as you grow. The specific things that widen it in this trade are what the rest of this page is about.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-08-06
WHERE THE CASH GOES IN PLUMBING

WHERE IT LEAKS OUT.

01 · The rough-in cash hole (the trade's shape, named on the site already)

Plumbing spends in two humps with a canyon between: underground and rough-in load the labor and pipe early, then the trade demobilizes while walls close and finishes run, then trim-out returns months later for fixtures and final. The. Together they're the trade's cash story, told in two pages that should cross-link as one arc.

The module that controls this

THE THREE THAT DECIDE THE YEAR

WHAT MOVES MARGIN IN THIS TRADE.

LEAK 01

The Two-Hump Canyon

Underground and rough-in spend the money; trim-out collects it, months later, behind punch and retainage. A flat percent-complete SOV starves the front and strands the back; phase-weighted billing is the trade's oxygen.

LEAK 02

The Allowance Ambush

Fixture allowances reconcile at the end unless the contractor reconciles them in writing as selections land. Late selections, silent substitutions, and unpriced deltas are the finish line's favorite back-charges.

LEAK 03

The Buried Evidence

Under-slab surprises get documented before backfill or they never happened. The photograph taken before the concrete truck arrives is worth more than the claim filed after it leaves. (cfos-job-profitability-system) ---

THE NUMBER TO MANAGE

DAYS SALES OUTSTANDING.

Ninety days is weak, 45 is the target, 30 is strong. Nothing else moves cash faster.

PositionDaysWhat it means
Weak90 daysRoughly three months of work funded out of your own pocket.
Target45 daysAchievable on the days you control: submission timing, complete documentation, follow up in week two.
Strong30 daysRequires discipline every month, and it's the cheapest capital available to you.

Moving from 90 days to 45 frees roughly annual revenue divided by 365, times 45 days. At $4M that's about $493,000. At $8M it's about $986,000. That money doesn't come from a bank and it costs no interest, which is why we work the cycle before discussing financing anything.

WHERE YOU SHOULD BE

PLUMBING BENCHMARKS.

Plumbing subcontractors at $1M to $5M net 9 percent, against a CFOS target of 11 percent, set at 10 percent before taxes or 3.5 points better than your trade's average at your revenue, whichever is higher. Working capital should sit at 13 percent of annual revenue, and the monthly close should finish by day 10 so the numbers can still change a decision.

Full plumbing benchmarks
COMMON QUESTIONS

FREQUENTLY ASKED.

Because the jobs earn before the money comes in. Labour and material go out on a weekly cycle and collect 45 to 90 days later, with 5 to 10 percent held as retention behind that. In plumbing specifically that distance is widened by the rough-in cash hole (the trade's shape, named on the site already). None of that reads as a loss on any single job, which is why it goes unaddressed.
The canyon between plumbing's two spending humps: underground and rough-in consume labor and pipe early, the trade demobilizes while the building closes up, and trim-out returns months later to collect final payment behind punch and retainage. Phase-weighted schedules of values, with rough-in billed at rough-in weight and trim-out as a separate remobilization, are the fix.
Three tiers, and which one you are in depends on how much of the work you want off your desk. Core is where you stop guessing: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. Executive is where you stop touching the books, because we run the bookkeeping and the controllership as well. Strategic is where every job shows its margin while it is still running, because the job costing and WIP platform is set up and managed for you. No payroll. No scope gaps.
$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time
WHAT THIS TIES INTO
Josh Luebker, The Construction CFO
Josh Luebker
FRACTIONAL CFO · THE CONSTRUCTION CFO

Former commercial construction project manager and master electrician. Managed 150+ projects worth more than $2.1B combined, with individual jobs from $50,000 to $300M, including data centers, military bases, hospitals, and high-rises. Now fractional CFO for commercial subcontractors doing $1M to $12M through Sulphur Prairie Management.About Josh  | LinkedIn

WHICH WEEK DO YOU RUN SHORT?

Bring your open invoices and your payroll calendar. We will build enough of a forecast on the call to tell you which week is tight and why.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute diagnostic

20 minutes. No sales pressure. We will tell you exactly what's broken before we talk about anything else.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.