WHY YOU'RE SHORT

INTERIOR JOBS LOOK PROFITABLE. THE CASH IS STILL IN TRANSIT.

QUICK ANSWER

Interior subcontractors run out of cash for reasons specific to how the work is built and billed, on jobs that are making money. The three that cost the most in this trade are below, taken from interior contractor research. Most sit at 75 to 90 days from finishing work to holding the money, and 45 days is achievable.

Cash and profit are measured on different clocks. Your profit and loss records revenue when you invoice and costs when you incur them, while the bank account only knows what cleared. Labour goes out weekly and collects 45 to 90 days later, minus retention. That distance is what a growing, profitable interior company funds out of pocket, and it widens as you grow. The specific things that widen it in this trade are what the rest of this page is about.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-08-06
WHERE THE CASH GOES IN INTERIOR

WHERE IT LEAKS OUT.

01 · The TI float (financing the landlord's building)

Tenant-improvement work runs on allowances ($15 to $80 per square foot by market and asset class) that reimburse AFTER the work: the contractor gets paid by a tenant who gets paid by a landlord only on a clean draw package (paid invoices, lien waivers, proof of completion), typically 30 to 60 days after submission, and some deals hold the entire allowance until certificate of occupancy. The published tenant-side advice says it plainly: "you need working capital to float construction, which catches a lot of first-time tenants by surprise." It catches their contractors harder.

The module that controls this

02 · Compressed schedules against lease dates

The tenant's rent commencement and move-in date are contractual; the fit-out schedule inherits them backward. Retail TI runs 8 to 16 weeks permit-to-CO and restaurant 12 to 22, with permitting adding 4 to 12 weeks by jurisdiction, and long-lead equipment (switchgear at 18 to 30 weeks) can exceed the entire construction window. Hidden conditions in existing buildings justify the published 10-to-15 percent contingency norm.

The module that controls this

THE THREE THAT DECIDE THE YEAR

WHAT MOVES MARGIN IN THIS TRADE.

LEAK 01

The Reimbursement Float

TI money flows landlord-to-tenant-to-contractor, released 30 to 60 days after a clean draw package, sometimes only at certificate of occupancy. The contractor who builds lien waivers and invoice packages as the work happens gets the draw; the one who assembles them at month end finances the landlord's building.

LEAK 02

The Work-Letter Seam

Base-building versus tenant scope lives in the work letter, not the drawings, and every unread seam (demising walls, panel upgrades, code-triggered base work) surfaces as unpaid scope. Price the letter, then the plans.

LEAK 03

The Lease-Date Vise

Rent commencement is contractual, permits take 4 to 12 weeks, switchgear takes 18 to 30, and the schedule runs backward from a date the contractor never chose. Long-lead procurement and contingency discipline are the only slack in the system. (cfos-cash-flow-cycle-system) ---

THE NUMBER TO MANAGE

DAYS SALES OUTSTANDING.

Ninety days is weak, 45 is the target, 30 is strong. Nothing else moves cash faster.

PositionDaysWhat it means
Weak90 daysRoughly three months of work funded out of your own pocket.
Target45 daysAchievable on the days you control: submission timing, complete documentation, follow up in week two.
Strong30 daysRequires discipline every month, and it's the cheapest capital available to you.

Moving from 90 days to 45 frees roughly annual revenue divided by 365, times 45 days. At $4M that's about $493,000. At $8M it's about $986,000. That money doesn't come from a bank and it costs no interest, which is why we work the cycle before discussing financing anything.

WHERE YOU SHOULD BE

INTERIOR BENCHMARKS.

Interior subcontractors at $1M to $5M net 6 percent, against a CFOS target of 10 percent, set at 10 percent before taxes or 3.5 points better than your trade's average at your revenue, whichever is higher. Working capital should sit at 13 percent of annual revenue, and the monthly close should finish by day 10 so the numbers can still change a decision.

Full interior benchmarks
COMMON QUESTIONS

FREQUENTLY ASKED.

Because the jobs earn before the money comes in. Labour and material go out on a weekly cycle and collect 45 to 90 days later, with 5 to 10 percent held as retention behind that. In interior specifically that distance is widened by the ti float (financing the landlord's building) and compressed schedules against lease dates. None of that reads as a loss on any single job, which is why it goes unaddressed.
Landlord to tenant to contractor, backward from the work: the contractor bills the tenant, the tenant submits a draw package (paid invoices, lien waivers, completion proof) to the landlord, and reimbursement lands 30 to 60 days later, or at certificate of occupancy on tighter deals. Build the draw package as the work happens, and negotiate staged releases before signing; the float is real and someone is funding it.
Three tiers, and which one you are in depends on how much of the work you want off your desk. Core is where you stop guessing: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. Executive is where you stop touching the books, because we run the bookkeeping and the controllership as well. Strategic is where every job shows its margin while it is still running, because the job costing and WIP platform is set up and managed for you. No payroll. No scope gaps.
$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time
WHAT THIS TIES INTO
Josh Luebker, The Construction CFO
Josh Luebker
FRACTIONAL CFO · THE CONSTRUCTION CFO

Former commercial construction project manager and master electrician. Managed 150+ projects worth more than $2.1B combined, with individual jobs from $50,000 to $300M, including data centers, military bases, hospitals, and high-rises. Now fractional CFO for commercial subcontractors doing $1M to $12M through Sulphur Prairie Management.About Josh  | LinkedIn

WHICH WEEK DO YOU RUN SHORT?

Bring your open invoices and your payroll calendar. We will build enough of a forecast on the call to tell you which week is tight and why.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute diagnostic

20 minutes. No sales pressure. We will tell you exactly what's broken before we talk about anything else.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.