CFOS for QuickBooks, coming January 2027Join the waitlist: 12 months with no subscription fee
WHY YOU'RE SHORT

INTERIORS JOBS LOOK PROFITABLE. THE CASH IS STILL IN TRANSIT.

QUICK ANSWER

Interiors subcontractors have no cash left for reasons specific to how the work is built and billed, on jobs that are making money. The three that cost the most in this trade are below, taken from interiors contractor research. Most are at 75 to 90 days from finishing work to holding the money, and 45 days is achievable.

Cash and profit are measured on different clocks. Your profit and loss records revenue when you invoice and costs when you incur them, while the bank account only knows what cleared. Labour goes out weekly and collects 45 to 90 days later, minus retention. That distance is what a growing, profitable interiors company funds out of pocket, and it widens as you grow. The specific things that widen it in this trade are what the rest of this page is about.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-11-02
WHERE THE CASH GOES IN INTERIORS

WHERE IT LEAKS OUT.

01 · The TI float (financing the landlord's building)

Tenant-improvement work depends on allowances ($15 to $80 per square foot by market and asset class) that reimburse AFTER the work. The contractor gets paid by a tenant. The tenant gets paid by a landlord only on a clean draw package (paid invoices, lien waivers, proof of completion), typically 30 to 60 days after submission. Some deals hold the entire allowance until certificate of occupancy. The published tenant-side advice says it plainly: "you need working capital to float construction, which catches a lot of first-time tenants by surprise." It's harder on their contractors.

The system that controls this

02 · Compressed schedules against lease dates

The tenant's rent commencement and move-in date are in the contract, and the fit-out schedule works backward from them. Retail TI takes 8 to 16 weeks permit-to-CO and restaurant 12 to 22. Permitting adds 4 to 12 weeks by jurisdiction. Long-lead equipment (switchgear at 18 to 30 weeks) can take longer than the entire construction window. Unseen conditions in existing buildings are why the published contingency norm is 10-to-15 percent.

The system that controls this

THE THREE THAT DECIDE THE YEAR

WHAT MOVES MARGIN IN THIS TRADE.

LEAK 01

The Reimbursement Float

TI money goes from landlord to tenant to contractor. It's released 30 to 60 days after a clean draw package, and sometimes only at certificate of occupancy. Build lien waivers and invoice packages as the work happens and you get the draw. Put them together at month end and you pay for the landlord's building.

LEAK 02

The Work-Letter Seam

The work letter decides base-building versus tenant scope. The drawings don't. Every seam you don't read (demising walls, panel upgrades, code-triggered base work) turns into unpaid scope. Price the letter, then the plans.

LEAK 03

The Lease-Date Vise

Rent commencement is in the contract. Permits take 4 to 12 weeks and switchgear takes 18 to 30. The schedule works backward from a date you never chose. Long-lead procurement and a contingency you hold to are the only slack you have.

THE NUMBER TO MANAGE

DAYS SALES OUTSTANDING.

Ninety days is weak, 45 is the target, 30 is strong. Nothing else moves cash faster.

PositionDaysWhat it means
Weak90 daysRoughly three months of work funded out of your own pocket.
Target45 daysYou can get here on the days you control. Bill on time, send complete paperwork, and follow up in week two.
Strong30 daysTakes work every month. It's the cheapest money you can get.

Moving from 90 days to 45 frees roughly annual revenue divided by 365, times 45 days. At $4M that's about $493,000. At $8M it's about $986,000. That money costs no interest and needs no bank. So we fix billing and collections before we talk about financing.

WHERE YOU SHOULD BE

INTERIORS BENCHMARKS.

Interiors subcontractors at $1M to $5M net 6 percent, against the CFOS net profit target, set at your trade's net profit average at your revenue plus 3.5 points, never below 10 percent, before taxes. The working capital target is 13 percent of annual revenue, and the monthly close should finish by day 10 so the numbers can still change a decision.

Full interiors benchmarks
COMMON QUESTIONS

FREQUENTLY ASKED.

Because the jobs earn before the money comes in. Labour and material go out on a weekly cycle and collect 45 to 90 days later, with 5 to 10 percent held as retention behind that. In interiors specifically that distance is widened by the ti float (financing the landlord's building) and compressed schedules against lease dates. None of that reads as a loss on any single job, which is why it goes unaddressed.

Landlord to tenant to contractor, after the work is done. You bill the tenant. The tenant submits a draw package (paid invoices, lien waivers, completion proof) to the landlord. Reimbursement comes 30 to 60 days later, or at certificate of occupancy on tighter deals. Build the draw package as the work happens, and negotiate staged releases before you sign. The float is real and someone is paying for it.

Three tiers, and which one you are in depends on how much of the work you want off your desk. On Core we build your plan every month and your team does the work: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. On Strategic we build the plan, track it and adjust it every month: our team does the bookkeeping and the bank reconciliations, and the job costing and WIP software is set up and managed for you, on your own online software or ours. On Platinum we manage the money side for you every week: our team handles your bills and receivables the way an in-house controller would, and you approve every payment. We don't do payroll.
$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time
WHAT THIS TIES INTO
Josh Luebker, SPM The Construction CFO
Josh Luebker
FRACTIONAL CFO · SPM THE CONSTRUCTION CFO

Josh Luebker is a master electrician turned construction CFO, president of SPM The Construction CFO and author of CONTROL: C.F.O.S. Construction Financial Operating System.

WHICH WEEK DO YOU COME UP SHORT?

Twenty minutes of questions about your open invoices, your payroll calendar, and how your general contractors really pay. Josh won't pitch you or send a proposal. If Josh can help, you'll set a longer second call.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute call

20 minutes. No pitch or proposal. Josh asks questions to find out if he can help.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.