GRADING JOBS LOOK PROFITABLE. THE CASH IS STILL IN TRANSIT.
Grading subcontractors have no cash left for reasons specific to how the work is built and billed, on jobs that are making money. The three that cost the most in this trade are below, taken from grading contractor research. Most are at 75 to 90 days from finishing work to holding the money, and 45 days is achievable.
Cash and profit are measured on different clocks. Your profit and loss records revenue when you invoice and costs when you incur them, while the bank account only knows what cleared. Labour goes out weekly and collects 45 to 90 days later, minus retention. That distance is what a growing, profitable grading company funds out of pocket, and it widens as you grow. The specific things that widen it in this trade are what the rest of this page is about.
WHERE IT LEAKS OUT.
DOT work pays on measured quantities, agency estimates and public-agency cycles. Retainage and final acceptance take longer than private norms.
WHAT MOVES MARGIN IN THIS TRADE.
The Two Economies
Mass grading sells yards. Fine grading sells tolerance. One blended cost history misprices both, and at 18 percent gross margin you have no room for bids that are wrong every time in either direction.
The Acceptance Gate
Density tests and subgrade acceptance are payment gates. A failed proctor means unpaid production, retest fees and lost schedule. Your moisture and soils documentation decides whether you have a claim or pay for it yourself.
The Idle Spread
Overhead is sixteen percent at the small end, the heaviest in the dirt family. You pay it twelve months a year, and production is seasonal. Winter reserves and utilization tracking decide whether spring means a restart or a refinance.
DAYS SALES OUTSTANDING.
Ninety days is weak, 45 is the target, 30 is strong. Nothing else moves cash faster.
| Position | Days | What it means |
|---|---|---|
| Weak | 90 days | Roughly three months of work funded out of your own pocket. |
| Target | 45 days | You can get here on the days you control. Bill on time, send complete paperwork, and follow up in week two. |
| Strong | 30 days | Takes work every month. It's the cheapest money you can get. |
Moving from 90 days to 45 frees roughly annual revenue divided by 365, times 45 days. At $4M that's about $493,000. At $8M it's about $986,000. That money costs no interest and needs no bank. So we fix billing and collections before we talk about financing.
GRADING BENCHMARKS.
Grading subcontractors at $1M to $5M net 2 percent, against the CFOS net profit target, set at your trade's net profit average at your revenue plus 3.5 points, never below 10 percent, before taxes. The working capital target is 13 percent of annual revenue, and the monthly close should finish by day 10 so the numbers can still change a decision.
