WHY YOU'RE SHORT

DEMOLITION JOBS LOOK PROFITABLE. THE CASH IS STILL IN TRANSIT.

QUICK ANSWER

Demolition subcontractors run out of cash for reasons specific to how the work is built and billed, on jobs that are making money. The three that cost the most in this trade are below, taken from demolition contractor research. Most sit at 75 to 90 days from finishing work to holding the money, and 45 days is achievable.

Cash and profit are measured on different clocks. Your profit and loss records revenue when you invoice and costs when you incur them, while the bank account only knows what cleared. Labour goes out weekly and collects 45 to 90 days later, minus retention. That distance is what a growing, profitable demolition company funds out of pocket, and it widens as you grow. The specific things that widen it in this trade are what the rest of this page is about.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-08-06
WHERE THE CASH GOES IN DEMOLITION

WHERE IT LEAKS OUT.

01 · Mobilization-heavy, milestone-poor

Big iron moves in before dollar one bills, and shoring or stabilization of adjacent structures adds engineered cost at the front. Demolition's spend curve is the steepest front-load in the dirt trades.

The module that controls this

THE THREE THAT DECIDE THE YEAR

WHAT MOVES MARGIN IN THIS TRADE.

LEAK 01

The Survey Skipped

Hazmat discovered mid-swing stops the machine and adds $2 to $7 per square foot under abatement protocol. The pre-demolition survey is a billed line and a change-order trigger, or it's the most expensive thing the contractor never charged for.

LEAK 02

The Gate Rate

Disposal runs 20 to 30 percent of project cost, and tipping fees moved about 10 percent in a year to roughly $62 per ton. Per-ton actuals tracked against the bid rate is the trade's simplest, highest-value variance report.

LEAK 03

The Untracked Paycheck in the Pile

Salvage is contract consideration: ferrous drives the tonnage, non-ferrous drives the margin, and disputes go to court. A per-job scrap ledger with grading, weights, and settlement documentation turns a guess into revenue. (cfos-job-profitability-system) ---

THE NUMBER TO MANAGE

DAYS SALES OUTSTANDING.

Ninety days is weak, 45 is the target, 30 is strong. Nothing else moves cash faster.

PositionDaysWhat it means
Weak90 daysRoughly three months of work funded out of your own pocket.
Target45 daysAchievable on the days you control: submission timing, complete documentation, follow up in week two.
Strong30 daysRequires discipline every month, and it's the cheapest capital available to you.

Moving from 90 days to 45 frees roughly annual revenue divided by 365, times 45 days. At $4M that's about $493,000. At $8M it's about $986,000. That money doesn't come from a bank and it costs no interest, which is why we work the cycle before discussing financing anything.

WHERE YOU SHOULD BE

DEMOLITION BENCHMARKS.

Demolition subcontractors at $1M to $5M net 4 percent, against a CFOS target of 10 percent, set at 10 percent before taxes or 3.5 points better than your trade's average at your revenue, whichever is higher. Working capital should sit at 13 percent of annual revenue, and the monthly close should finish by day 10 so the numbers can still change a decision.

Full demolition benchmarks
COMMON QUESTIONS

FREQUENTLY ASKED.

Because the jobs earn before the money comes in. Labour and material go out on a weekly cycle and collect 45 to 90 days later, with 5 to 10 percent held as retention behind that. In demolition specifically that distance is widened by mobilization-heavy, milestone-poor. None of that reads as a loss on any single job, which is why it goes unaddressed.
Three tiers, and which one you are in depends on how much of the work you want off your desk. Core is where you stop guessing: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. Executive is where you stop touching the books, because we run the bookkeeping and the controllership as well. Strategic is where every job shows its margin while it is still running, because the job costing and WIP platform is set up and managed for you. No payroll. No scope gaps.
$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time
WHAT THIS TIES INTO
Josh Luebker, The Construction CFO
Josh Luebker
FRACTIONAL CFO · THE CONSTRUCTION CFO

Former commercial construction project manager and master electrician. Managed 150+ projects worth more than $2.1B combined, with individual jobs from $50,000 to $300M, including data centers, military bases, hospitals, and high-rises. Now fractional CFO for commercial subcontractors doing $1M to $12M through Sulphur Prairie Management.About Josh  | LinkedIn

WHICH WEEK DO YOU RUN SHORT?

Bring your open invoices and your payroll calendar. We will build enough of a forecast on the call to tell you which week is tight and why.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute diagnostic

20 minutes. No sales pressure. We will tell you exactly what's broken before we talk about anything else.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.