HOW MANY MONTHS OF WORK DO YOU ACTUALLY HAVE SIGNED?
Backlog coverage ratio is total signed contract value divided by average monthly revenue. A $5M subcontractor with $1.5M in signed backlog has 3.6 months of coverage. Healthy for a fast-bidding specialty sub. Thin for a civil contractor with 90-day mobilization lead times. SPM tracks backlog coverage monthly in the CEO Report — not because more backlog is always better, but because the coverage ratio is the earliest leading indicator of a future cash gap.
3 TO 6 MONTHS IS HEALTHY. BELOW 2 IS A CASH RISK SIGNAL.
How to Calculate Backlog Coverage Ratio
Backlog Coverage Ratio = Total Signed Contract Remaining Value ÷ Average Monthly Revenue
Use remaining contract value — not total contract value. Work already billed is not backlog. On a $1.2M contract that is 60% complete, the remaining backlog value is $480K.
What Backlog Coverage Predicts
BACKLOG RISK IS TRADE-SPECIFIC.
Civil & Sitework
Civil backlog is lumpy — one $2M DOT award can swing the ratio from 1.5 to 4 months overnight. The risk is the gap between awards: bid cycles on public work run 60–120 days from letting to NTP, so a thin backlog today means a revenue hole one quarter out, not next month. Civil contractors need a higher coverage floor — 3 months minimum — because the replenishment cycle is slower.
Concrete & Structural
Concrete backlog burns fast. A $400K pour package that looked like six weeks of work compresses to three when the GC accelerates the schedule. Concrete subs consistently overestimate coverage because they divide backlog by average monthly revenue instead of scheduled burn rate. CFOS tracks both numbers — and the scheduled burn is the one that predicts the gap.
Electrical & Specialty
Electrical backlog has the longest tail — rough-in dollars burn early, trim and closeout dollars sit in backlog for months without producing revenue at the same rate. A $1.8M electrical backlog might only support $150K/month of actual billing in its final phase. Phase-weighted backlog coverage is the only honest version for electrical subs.
T&M-Heavy Trades (Fiber, SWPPP, Service)
T&M trades technically have no backlog — they have client relationships and historical run rates. The coverage equivalent is contracted recurring scope plus trailing 90-day T&M average. A fiber contractor with zero signed contracts but $200K/month of consistent carrier work has coverage — it's just invisible on a traditional backlog report. CFOS builds the T&M version explicitly.
WHAT CHANGES WHEN COVERAGE IS TRACKED MONTHLY.
Frequently Asked Questions
3 to 6 months for most specialty commercial subcontractors. The lower end of the range is appropriate for subs that can mobilize and execute quickly — electrical, drywall, insulation. The upper end is appropriate for civil and underground utility contractors with longer mobilization lead times and longer project durations.
No. Backlog coverage ratio uses signed contracts only — executed subcontract agreements or executed purchase orders. LOIs and verbal commitments are not backlog. Including them overstates the coverage ratio and can delay the bidding response that the real backlog number would have triggered.
Backlog is tracked as a separate line item in the monthly CEO Report — total remaining signed contract value divided by trailing 3-month average revenue. Tracked 13 months rolling so the trend is visible. A declining trend triggers a conversation about pipeline and bidding priorities in the monthly accountability meeting.
Bid acceleration — prioritize estimating capacity toward near-term starts and fast-execution scopes. Review outstanding proposals for follow-up. Reach out directly to top GC relationships for upcoming work. A sub that knows its backlog coverage is dropping to 2 months has 30 to 45 days to respond before the cash impact arrives. Without the metric, the first response is a reactive cash scramble.