WHY SITEWORK CONTRACTORS WORK FOR FREE ON CHANGED CONDITIONS.
Sitework scope creep happens when conditions in the field diverge from the plans and the contractor absorbs the cost without a change order. Soil conditions harder than anticipated, rock encountered at unexpected depth, drainage re-routing, grade revisions, utility conflicts — each one adds cost that was not in the original estimate. When those costs are absorbed into job costs without a corresponding change order, the margin is gone and no one sees it coming until closeout.
CFOS runs a weekly open change order review on every active sitework job. Every variance that cannot be explained by estimate error gets evaluated for change order eligibility the week it occurs — not 60 days later when the GC has already closed the cost period.
A sitework PM gets a call from the GC's superintendent: the grade needs to come down another 18 inches on the northwest corner because the drainage plan changed. The PM says yes, directs the crew, and the grading is done. The GC never sends a written directive. The PM never submits a change order. The cost hits job costs as normal earthwork.
Six weeks later at billing, the PM mentions the grade change to the project exec, who says the GC already closed that billing period and the change is too small to pursue. The cost is absorbed. The margin is gone. This happens on every sitework job that lacks a documented changed conditions process.
Most commercial sitework contracts include a differing site conditions clause. If subsurface conditions materially differ from what was represented in the bid documents — harder soil, unexpected rock, higher groundwater, buried obstructions — the contractor has a contractual right to additional compensation. That right expires if it is not asserted in writing within the contract's notice window, which is typically 7 to 14 days from discovery.
CFOS tracks daily production rates against the estimate. When a production rate drops below 70% of estimated for two consecutive days, the trigger fires: document the condition, notify the GC in writing, and open a change order. The contractual clock starts running on the discovery date, not the final cost date.
GC pay applications close on a schedule — typically the 25th of the month. Any costs incurred but not billed by that date carry to the next period. Any change orders not submitted before cut-off are pushed to the following month's negotiation, when the GC's PM has mentally moved on and the context for the change has faded.
CFOS aligns change order submission with the GC's billing cut-off. Every open change order is reviewed by the 20th of the month, submitted by the 23rd, and tracked for approval or dispute response. Change orders that slip to the following month recover at a significantly lower rate than those submitted in the period the work occurred.
FLAT MONTHLY FEE. NO SURPRISES.
Two tiers based on trailing 12-month revenue. No hourly billing. No payroll. No add-ons.
| Revenue | Core Financial | Executive Financial |
|---|---|---|
| Under $1M | $1,900/mo | $2,900/mo |
| $1M–$3M | $2,600/mo | $3,600/mo |
| $4M–$6M | $3,800/mo | $5,500/mo |
| $7M–$9M | $5,100/mo | $6,900/mo |
| $10M–$12M | $6,100/mo | $8,500/mo |
| $13M+ | Quoted | Quoted |
WHERE SITEWORK SCOPE CREEP COMES FROM.
Differing Site Conditions
The geotech said sandy clay; the excavator found rock at four feet. Differing site conditions are the largest legitimate CO source in sitework — and the most time-sensitive. The clause typically requires notice before disturbing the condition. Dig through it undocumented and the claim is buried with it.
Quantity Overruns on Unit-Price Work
Plan quantities said 12,000 yards of cut; the survey says 14,300. On unit-price contracts the overrun is payable — if it's measured, documented, and noticed inside the contract window. Load counts, survey shots, and daily quantity logs are the difference between 2,300 paid yards and 2,300 donated ones.
Plan Revisions and Re-Grades
The civil sheets revised, the pad elevations moved, the pond got bigger. Every revision date needs a scope-delta review against what's already built and priced. Sitework subs that don't log drawing revisions against work-in-place absorb the re-work as if the first version never existed.
GC-Directed Extras
The superintendent asks for a temporary road, extra silt fence, a re-handle of stockpiled material — small, verbal, constant. Individually under $2K, collectively $50K–$100K a year on an active sitework book. The 48-hour written confirmation habit converts hallway requests into paid scope.