Underground rough-in and above-slab rough-in are the most labor and material intensive phases of a plumbing subcontract. A GC-drafted SOV assigns them 15–20% of contract value. They represent 35–50% of actual cost.
Underground plumbing — trenching, underground drain lines, cleanouts, building main — is the most labor-intensive and material-intensive phase of a commercial plumbing subcontract. It requires the most equipment, the most labor, and occurs before any vertical work begins. A GC-drafted SOV typically assigns 8–12% of contract value to underground rough-in. Actual cost is often 20–28% of total contract cost. Every month of underground work is funded from operating cash at a 2:1 cost-to-billing ratio.
Above-slab rough-in — drain lines, vent stacks, supply rough-in — represents another 15–20% of total plumbing cost but is often consolidated with trim-out in the SOV into a single 'Rough-In and Trim' milestone. This blending allows the GC to defer approval of rough-in billing until trim-out is complete — months after the rough-in labor and material were incurred.
Trim-out and final inspection — fixture setting, trim, testing — are the least labor-intensive phases of a plumbing subcontract but often carry 40–50% of contract value in a GC-drafted SOV. The labor is minimal. The billing is maximum. The contractor has funded the entire project from operating cash and finally gets paid well in the last 20% of the timeline.
Submit your own SOV with four distinct phases weighted at actual cost distribution: underground rough-in (20–28% of contract value), above-slab rough-in (15–20%), trim-out (20–25%), and final including testing and inspection (10–15%). Mobilization as a separate first line at 5–8%. This structure recovers costs as they are incurred rather than at completion.
Pipe, fittings, and specialty material ordered before installation begins need a procurement line in the SOV — billable at delivery. On a $400,000 plumbing subcontract with $80,000 in pre-ordered material, a delivery line recovers that cash 4–8 weeks earlier than waiting for installation milestones.
Rather than waiting for the GC's rough-in approval, negotiate language that ties billing to AHJ rough-in inspection approval — not GC approval. AHJ inspections are on a defined schedule and produce a documented pass/fail. Once the rough-in inspection passes, the billing milestone is met regardless of the GC's internal approval process.
ControlQore cost codes by plumbing phase track actual cost incurred against the SOV milestone value. When rough-in is 60% complete by cost but only 20% billed (because the SOV milestone requires 100% completion), the underbilled position is flagged on the WIP schedule. SPM uses this flag to accelerate billing on completed portions and document phase completion for early billing.
The plumbing rough-in dynamic is identical to electrical rough-in. SPM's SOV restructuring approach produces the same result across all MEP trades.
Including underbillings from rough-in phases completed but not yet billed under GC-drafted SOV milestones.
On all new MEP subcontracts — rough-in phases weighted at actual cost distribution.
A free call with Josh takes 30 minutes. Bring your last P&L and current bank balance.
Schedule a Free Call →