ELECTRICAL SUBCONTRACTOR CASH GAP BEFORE FIRST PAYMENT.
The average commercial electrical subcontractor deploys costs for 73 days before the first check clears. Switchgear deposit on day one. Mobilization week two. Rough-in labor and conduit material weeks two through six. First pay app submitted at end of month one. GC billing to owner. Owner payment. GC processing. Check in the bank at day 73. Every one of those days is funded by the LOC, cash reserves, or both.
Understanding the 73-day cash gap is not a problem-solving exercise — it is a business planning exercise. Every commercial electrical project has this gap. The question is whether the LOC is sized to cover it, whether the mobilization SOV line recovers some of it early, and whether stored materials billing is in the contract to recover the switchgear deposit before installation.
WHAT HAPPENS BETWEEN CONTRACT SIGNING AND FIRST PAYMENT.
Peak gap: By week 14, most electrical contractors have deployed $180,000+ on a $480K contract and collected $48,000. The $132,000 gap is funded by the LOC. On a contractor with a $250,000 LOC and two other active projects, this one project can max the line before switchgear is even installed.
THREE TOOLS THAT REDUCE THE 73-DAY GAP — IN ORDER OF IMPACT.
Stored Materials Billing for Switchgear
Negotiate a stored materials line in the SOV at contract signing. When the switchgear deposit is paid and the purchase order is submitted with documentation, bill the stored materials line at the deposit amount. GC approves with a materials submittal, proof of purchase, and lien waiver. The deposit is recovered before installation. This is the single highest-impact change to electrical cash flow — it converts a 6-month carrying cost into a 30-day billing event.
Mobilization SOV Line at 8–10% of Contract
A mobilization line weighted at 8–10% of contract value covers temporary power, site setup, and initial procurement deposits. On a $480K contract, 9% mobilization is $43,200. Bill it when equipment is on site and temporary power is established. This covers the initial mobilization costs and reduces the LOC requirement in the first 30 days before any production billing advances.
LOC Sized to Peak Electrical Draw Before Contract Signing
Calculate the peak LOC requirement before signing: switchgear deposit + conduit order deposit + weeks of overhead and labor until first payment. That is your minimum available LOC requirement. If current LOC availability is below that number, either get an increase before mobilization or negotiate stored materials billing before signing. Discovering the shortfall at week six means borrowing at the worst possible time.