Skip to main content
ELECTRICAL CASH GAPFIRST PAYMENTSWITCHGEAR DEPOSITWORKING CAPITALCFOS $1M–$12MELECTRICAL CASH GAPFIRST PAYMENTSWITCHGEAR DEPOSITWORKING CAPITALCFOS $1M–$12M
THE CONSTRUCTION CFOBOOK A FREE CALL
ELECTRICAL CLUSTER · PAIN POINT

ELECTRICAL SUBCONTRACTOR CASH GAP BEFORE FIRST PAYMENT.

QUICK ANSWER

The average commercial electrical subcontractor deploys costs for 73 days before the first check clears. Switchgear deposit on day one. Mobilization week two. Rough-in labor and conduit material weeks two through six. First pay app submitted at end of month one. GC billing to owner. Owner payment. GC processing. Check in the bank at day 73. Every one of those days is funded by the LOC, cash reserves, or both.

Understanding the 73-day cash gap is not a problem-solving exercise — it is a business planning exercise. Every commercial electrical project has this gap. The question is whether the LOC is sized to cover it, whether the mobilization SOV line recovers some of it early, and whether stored materials billing is in the contract to recover the switchgear deposit before installation.

BY JOSH LUEBKERPublished: May 2026Updated: May 2026
THE 73-DAY TIMELINE

WHAT HAPPENS BETWEEN CONTRACT SIGNING AND FIRST PAYMENT.

DAY 1
Contract signed. Switchgear ordered. Deposit paid: −$42,000 out of cash immediately.
WEEK 2
Mobilize. Temporary power, site setup, first conduit runs. Overhead begins: −$8,000/week.
WEEK 3
Underground conduit order: conduit, fittings, pull boxes. −$18,000 material deposit.
WEEK 4
First pay app submitted. GC billing cut-off was week 3. Next cut-off is week 7. Waiting.
WEEK 8
Second pay app submitted. Cash deployed so far: −$124,000+. Still no checks received.
WEEK 10
First check arrives — pay app #1 collected. +$48,000. LOC still drawn for the balance.
WEEK 14
Switchgear arrives. Balance due on delivery: −$58,000. Cannot bill until installed in week 18.

Peak gap: By week 14, most electrical contractors have deployed $180,000+ on a $480K contract and collected $48,000. The $132,000 gap is funded by the LOC. On a contractor with a $250,000 LOC and two other active projects, this one project can max the line before switchgear is even installed.

HOW TO FUND IT

THREE TOOLS THAT REDUCE THE 73-DAY GAP — IN ORDER OF IMPACT.

TOOL 01 — HIGHEST IMPACT

Stored Materials Billing for Switchgear

Negotiate a stored materials line in the SOV at contract signing. When the switchgear deposit is paid and the purchase order is submitted with documentation, bill the stored materials line at the deposit amount. GC approves with a materials submittal, proof of purchase, and lien waiver. The deposit is recovered before installation. This is the single highest-impact change to electrical cash flow — it converts a 6-month carrying cost into a 30-day billing event.

TOOL 02

Mobilization SOV Line at 8–10% of Contract

A mobilization line weighted at 8–10% of contract value covers temporary power, site setup, and initial procurement deposits. On a $480K contract, 9% mobilization is $43,200. Bill it when equipment is on site and temporary power is established. This covers the initial mobilization costs and reduces the LOC requirement in the first 30 days before any production billing advances.

TOOL 03

LOC Sized to Peak Electrical Draw Before Contract Signing

Calculate the peak LOC requirement before signing: switchgear deposit + conduit order deposit + weeks of overhead and labor until first payment. That is your minimum available LOC requirement. If current LOC availability is below that number, either get an increase before mobilization or negotiate stored materials billing before signing. Discovering the shortfall at week six means borrowing at the worst possible time.

COMMON QUESTIONS

FREQUENTLY ASKED.

On a $500K commercial electrical contract with a 60-day payment cycle: switchgear deposit $40,000–60,000, conduit and wire deposits $15,000–25,000, 10 weeks of labor and overhead at $18,000/week = $180,000. Total peak LOC requirement: $235,000–$265,000 before any revenue is received. If stored materials billing covers the switchgear, the LOC requirement drops to $155,000–$195,000. Size the LOC to the higher number and use stored materials billing to reduce actual draws.
Standard package: materials submittal identifying the equipment with manufacturer and model, purchase order or supplier invoice showing the deposit amount, warehouse receipt or on-site storage confirmation, conditional lien waiver for the stored material value, and certificate of insurance naming the GC and owner as additional insureds. Some GCs require a joint check agreement. Prepare this documentation at contract signing, not when the gear is ordered.
Yes. The 13-week cash flow forecast for electrical contractors maps switchgear deposit dates, conduit order dates, pay app submission dates, and expected collection dates explicitly — not as a single material cost line. Each major cash outflow and inflow event is a separate line on the weekly forecast. The peak LOC draw week is visible before mobilization. Stored materials billing recovery is mapped to its expected approval date. The gap is managed in advance, not discovered at week eight.
Josh Luebker
Josh Luebker
Fractional CFO · The Construction CFO

Former commercial construction project manager and master electrician. Managed 150+ projects totaling $300M+. Now fractional CFO for commercial subcontractors doing $1M–$12M. About Josh →  |  LinkedIn →

RELATED RESOURCES
RELATED
Electrical Material Buyout Cash Flow
The full buyout timeline and how to fund it without maxing the LOC
RELATED
Cash Flow for Electrical Subcontractors
The three structural cash flow problems specific to electrical work
TOOLS
Cash Flow Tools
The 13-week forecast that maps the 73-day gap before mobilization
SYSTEM CONNECTIONS
CFOS SPINE
Run on CFOSElectrical OSCash Control
RELATED
Material BuyoutElectrical Cash FlowProfitable But No Cash
SERVICE
Fractional CFOCash Flow ToolsBook a Call

HAVE YOU MODELED THE PEAK LOC REQUIREMENT ON YOUR NEXT ELECTRICAL CONTRACT?

A 30-minute diagnostic will calculate it from your project scope and show you whether stored materials billing or a LOC increase is the faster fix.

BOOK A FREE 30-MIN DIAGNOSTIC →

30 minutes. Free. No sales pressure.

OR SEE YOUR NUMBERS FIRST → FREE CEO REPORT TOOL
THE CONSTRUCTION CFO
Run on CFOSFractional CFOSchedule a CallJosh@ConstructionCFO.net
© 2026 SULPHUR PRAIRIE MANAGEMENT · SULPHUR ROCK, AR
0
Josh Luebker, The Construction CFO
JOSH LUEBKER
FOUNDER & CFO

Master electrician and former project manager, 150+ projects and $2.1B+ in commercial work. Now runs the numbers for subcontractors instead of standing on the job site.

LinkedIn About
Stewart Bohrer, The Construction CFO
STEWART BOHRER
VP OF OPERATIONS

Keeps the system running day to day: job costing, WIP, monthly financial reviews, and the follow-through between calls. Josh handles onboarding.

LinkedIn About
LinkedIn YouTube About Run on CFOS