ELECTRICAL CONTRACTOR MATERIAL BUYOUT CASH FLOW.
Switchgear lead times run 14–26 weeks on commercial projects. You order it the day the contract is signed. The deposit — typically 30–50% of the gear cost — comes out of your cash or LOC immediately. The gear arrives on site in week 14. You install it in week 18. You bill it in week 18. You collect it in week 24. From deposit payment to cash collection: 24 weeks of carrying the cost of a $60,000–$150,000 gear package before a dollar comes back.
This is the single largest cash flow timing problem in commercial electrical subcontracting and it is entirely structural — built into how electrical work is sequenced and how GC billing cycles work. Understanding it, building it into every cash forecast, and structuring the SOV to recover material cost as early as possible are the three tools that keep electrical contractors from maxing their LOC on profitable projects.
HOW A $480K ELECTRICAL CONTRACT PRODUCES A CASH CRISIS IN WEEK 10.
The gap: By week 14, you have spent $166,000+ on a contract where you have collected $48,000. The $118,000 gap is funded by the LOC. On a contractor with a $250,000 LOC and two other active projects, this one project can max the line before installation even begins.
HOW TO FUND THE BUYOUT WITHOUT MAXING YOUR LINE OF CREDIT.
Stored Materials Billing in the SOV
Negotiate a stored materials line item in the SOV at contract signing. A switchgear stored materials line at the full gear value — billed when the deposit is paid and documentation is submitted — recovers the deposit cost before installation. Requirements: materials submittal, proof of purchase, lien waiver, certificate of insurance. Most GCs approve stored materials billing with proper documentation. This eliminates the LOC requirement for the gear entirely.
Negotiate a Mobilization Line That Covers Procurement Deposits
If stored materials billing is not available, negotiate a mobilization line weighted at 8–10% of contract value — explicitly covering equipment mobilization, site setup, and initial procurement deposits. On a $480K contract, 9% mobilization is $43,200. That covers the switchgear deposit. Bill it at contract mobilization date. It will not cover the balance due on delivery but it reduces the LOC requirement for the largest single outflow.
Size the LOC to the Electrical Buyout Before Signing
Before signing any electrical subcontract with major gear procurement, calculate the peak LOC draw: switchgear deposit + conduit and wire order deposits + weeks of overhead until first payment. That number is the minimum available LOC required to fund the project without a cash crisis. If your current LOC availability is below that number, either increase the LOC before mobilization or negotiate stored materials billing before signing. Do not discover the shortfall in week 8.