WHEN YOU BUY IS A CASH DECISION.
Most subcontractors treat material buying as a logistics problem: order it so it shows up before the crew needs it. The cash side never gets planned — so a $180K package lands net-30 while the pay app that bills it collects in 60, and the line of credit eats the spread. Procurement forecasting maps every major buy against the billing calendar before the PO goes out: when it's needed, when it can be billed, what deposit terms move the float, and whether stored-material billing can close the gap. Same material. Same jobs. Months less float.
THE PO DATE IS A FINANCING DECISION. MOST SUBS LET THE SUPPLIER MAKE IT.
FOUR LEVERS INSIDE EVERY MAJOR BUY.
Buy Against the Billing Calendar, Not Just the Schedule
The field needs gear on site March 15. Logistics says order January 20. The cash question nobody asks: when does the pay app that carries this material go out, and when does it collect? If the answer is May, that PO just created a four-month float. Sometimes the float is unavoidable. It should never be unplanned — every buy over $25K gets mapped to its billing event before the PO is cut, and the 13-week cash forecast carries the spread.
Negotiate the Payment Curve, Not Just the Price
Suppliers negotiate price because everyone asks about price. Almost nobody negotiates the payment curve — deposit percentage, progress payments on fabricated items, net terms tied to delivery versus order date. Moving a gear package from 50% deposit at order to 20% at order and the balance at delivery can shift $50K of cash need by eight weeks at zero cost. The supplier's finance team says yes more often than their sales sheet suggests, especially for subs who pay like clockwork.
Bill It the Month You Buy It
Most subcontracts allow billing for properly stored materials — on site or in a bonded yard, insured, documented. Most subs never use the clause because nobody told the PM it exists. A $120K material buy billed as stored material in the same cycle it lands converts the float from months to weeks. The documentation cost is photographs, an insurance certificate, and a line on the SOV. The return is your money back before the work is even in place.
Lock Volatile Commodities When the Bid Wins, Not When the Crew Mobilizes
Copper, steel, PVC, lumber — bidding off today's price and buying at mobilization six months later is an unhedged commodity position wearing a hard hat. Early buyout with locked pricing trades a small carrying decision for protection against the move that erases a job's margin. The forecast tells you whether the cash position can carry the early buy; the alternative is hoping the market stays put. Hope is not a procurement strategy.
PROCUREMENT FLOAT, BY TRADE.
Electrical: The Gear Package
Switchgear and panel packages are the classic float: ordered months early for lead time, paid before installation, billed after. A $180K package bought in March, installed in May, billed in June, collected in July is a four-month float the bid never priced. Deposits negotiated down plus stored-material billing recover most of it.
Concrete: Volume Concentration
Ready-mix doesn't have long lead times — it has volume spikes. Three stacked pours put $200K of supplier invoices on net-30 against pay apps collecting in 60. Mapping pour schedules against the billing calendar tells you which months need the line and which months the line is funding bad planning.
Civil: Pipe, Aggregate, and Early Buyout
Underground utility and civil subs carry pipe and structure packages that reward early buyout on price but punish it on cash. The forecast makes it a real decision: the 4% price protection against the 60-day carrying cost, decided with numbers instead of nerve.
Structural Steel & Specialty: Fabrication Deposits
Fabricated packages front-load cash hard — deposits at order, progress payments through fab, delivery before billing. Progress-payment schedules tied to fabrication milestones, mirrored by stored-material and fabricated-item billing to the GC, keep the sub from banking the fabricator's float.