WHY YOU'RE SHORT

MECHANICAL JOBS LOOK PROFITABLE. THE BALANCE SHEET IS STILL THIN.

QUICK ANSWER

Mechanical subcontractors run out of cash for reasons specific to how the work is built and billed, on jobs that are making money. The three that cost the most in this trade are below, taken from mechanical contractor research. Most sit at 75 to 90 days from finishing work to holding the money, and 45 days is achievable.

Cash and profit are measured on different clocks. Your profit and loss records revenue when you invoice and costs when you incur them, while the bank account only knows what cleared. Labour goes out weekly and collects 45 to 90 days later, minus retention. That distance is what a growing, profitable mechanical company funds out of pocket, and it widens as you grow. The specific things that widen it in this trade are what the rest of this page is about.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-08-06
WHERE THE CASH GOES IN MECHANICAL

WHERE IT LEAKS OUT.

01 · Equipment is the job (deposits, leads, and the escalator that broke)

Mechanical scope is equipment-dominated, and 2026 lead times are historic: chillers quote 20 to 85 weeks depending on configuration, with commercial chilled-water systems benchmarked at 48 to 60 weeks on customization and material bottlenecks. Deposits go out at release, storage and insurance carry the middle, and the pay application catches up at delivery, if the SOV was written to allow it. The existing equipment-deposit; 2026 gives it teeth.

The module that controls this

THE THREE THAT DECIDE THE YEAR

WHAT MOVES MARGIN IN THIS TRADE.

LEAK 01

The Equipment Float

Chillers at 20 to 85 weeks, deposits at release, payment at delivery: the mechanical contractor is a procurement bank unless the SOV bills deposits and stored equipment explicitly. In 2026's lead-time market, the float is the job.

LEAK 02

The Three-Shop Contract

Sheet metal, piping, and controls are separate businesses inside one price. Divisional cost codes by discipline are the only way to know which shop earns and which one rides.

LEAK 03

The Subsidy Nobody Ordered

Service and construction run opposite cash and margin profiles, and blended books let one silently fund the other for years. The trade's best-in-dataset net ceiling belongs to operators who split the book and manage both on purpose. (cfos-job-profitability-system) ---

THE NUMBER TO MANAGE

DAYS SALES OUTSTANDING.

Ninety days is weak, 45 is the target, 30 is strong. Nothing else moves cash faster.

PositionDaysWhat it means
Weak90 daysRoughly three months of work funded out of your own pocket.
Target45 daysAchievable on the days you control: submission timing, complete documentation, follow up in week two.
Strong30 daysRequires discipline every month, and it's the cheapest capital available to you.

Moving from 90 days to 45 frees roughly annual revenue divided by 365, times 45 days. At $4M that's about $493,000. At $8M it's about $986,000. That money doesn't come from a bank and it costs no interest, which is why we work the cycle before discussing financing anything.

WHERE YOU SHOULD BE

MECHANICAL BENCHMARKS.

Mechanical subcontractors at $1M to $5M net 9 percent, against a CFOS target of 11 percent, set at 10 percent before taxes or 3.5 points better than your trade's average at your revenue, whichever is higher. Working capital should sit at 13 percent of annual revenue, and the monthly close should finish by day 10 so the numbers can still change a decision.

Full mechanical benchmarks
COMMON QUESTIONS

FREQUENTLY ASKED.

Because the jobs earn before the money comes in. Labour and material go out on a weekly cycle and collect 45 to 90 days later, with 5 to 10 percent held as retention behind that. In mechanical specifically that distance is widened by equipment is the job (deposits, leads, and the escalator that broke). None of that reads as a loss on any single job, which is why it goes unaddressed.
Three tiers, and which one you are in depends on how much of the work you want off your desk. Core is where you stop guessing: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. Executive is where you stop touching the books, because we run the bookkeeping and the controllership as well. Strategic is where every job shows its margin while it is still running, because the job costing and WIP platform is set up and managed for you. No payroll. No scope gaps.
$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time
WHAT THIS TIES INTO
Josh Luebker, The Construction CFO
Josh Luebker
FRACTIONAL CFO · THE CONSTRUCTION CFO

Former commercial construction project manager and master electrician. Managed 150+ projects worth more than $2.1B combined, with individual jobs from $50,000 to $300M, including data centers, military bases, hospitals, and high-rises. Now fractional CFO for commercial subcontractors doing $1M to $12M through Sulphur Prairie Management.About Josh  | LinkedIn

WHICH WEEK DO YOU RUN SHORT?

Bring your open invoices and your payroll calendar. We will build enough of a forecast on the call to tell you which week is tight and why.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute diagnostic

20 minutes. No sales pressure. We will tell you exactly what's broken before we talk about anything else.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.