JOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOSUBCONTRACTOR FINANCEOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQOREJOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOSUBCONTRACTOR FINANCEOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQOREJOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOSUBCONTRACTOR FINANCEOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQOREJOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOSUBCONTRACTOR FINANCEOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQORE
The Construction CFOSchedule a Free Call

TL;DR: Concrete subcontractor cash flow problems have three consistent root causes: schedule of values that underbills early phases (formwork, rebar, mobilization), overhead rate in bids set below actual SG&A, and AR sitting uncollected at 45+ days with no follow-up system. SPM fixes all three in the first 60 days — SOV review on new contracts, overhead rate recalculation, and AR audit at engagement start. Most concrete clients see measurable cash improvement within 30 days.

Concrete Contractor — Cash Flow

Cash Flow Problems
for Concrete Subcontractors.

Concrete subcontractors fund the most expensive work first and bill the least for it. Formwork, rebar, pump setup — all cash out before the first pay app. Here is how to fix the timing.

Published: May 2026Updated: May 2026
$120K
Typical Early-Phase Cash Hole on $600K SOV
30 Days
When AR Audit Cash Appears
5–8%
Target Mobilization Line in Every SOV
12–16%
Healthy Overhead Range for Concrete Contractors at $3M–$6M
The Problem

What You Are Dealing With

01

SOV Underbills Formwork and Rebar

Concrete subcontractors accepting GC-drafted SOVs are accepting billing structures that underbill the first 30–40% of project work. Formwork, rebar, pump mobilization — all cash-intensive — carry less SOV value than they represent as a percentage of actual cost. The cash hole is funded from operating cash or the line of credit for the first half of every project.

02

Overhead Rate Below Actual SG&A

Most concrete subs set an overhead rate from the estimating software default or from a calculation done years ago. Since then: a PM was hired, equipment was purchased, insurance went up. The overhead rate in bids did not update. Every job won since the last hire is underpriced by the difference between the old rate and the current one.

03

AR Sitting Uncollected

At $4M in annual billings, a concrete sub generates $330,000+ per month in invoices. A 10% collection lag is $33,000 per month sitting at 45+ days with no follow-up. Over a year, that lag accumulates into $100,000–$200,000 in an AR backlog that feels like a receivable but functions as an interest-free loan to every GC who is slow-paying.

The Fix

How to Fix It

SOV Review Before Every New Contract

SPM reviews every new concrete subcontract SOV before signing and recommends front-loading adjustments: mobilization line at 5–8% of contract value, formwork and rebar billable at installation, pump mobilization as a separate line, and concrete placement priced by pour phase rather than as a single lump milestone.

Overhead Rate Recalculation at Engagement Start

Pull SG&A from the last 12 months of P&L. Divide by revenue. That is the real overhead rate. Compare to what is in bids. The gap — almost always 4–8 points — goes into the bid model immediately and applies to every future job. On $4M in annual billings, a 6-point correction is $240,000 per year in recovered margin.

AR Audit in the First 30 Days

Every invoice over 30 days, every uncollected balance — pulled and called on in the first week. Most concrete contractors collect $80,000–$200,000 in the first 30 days of active collections. That cash funds operating needs while the structural fixes are being implemented.

Weekly AR Collections Going Forward

After the audit, weekly collections calls on every invoice over 30 days every Monday. On $4M in billings this takes 2–3 hours per week. It prevents the backlog from ever rebuilding to crisis level again.

Client Outcome

Real Results — Real Numbers

Concrete Contractor · $4.9M Revenue

This contractor had all three problems simultaneously: GC-drafted SOVs on every active job, overhead rate at 5% (actual was 12%), and $203,000 in AR sitting uncollected.

$203,000 in AR

Collected in the first 7 days of engagement.

Overhead: 5% → 12%

Corrected in the first 60 days. $130,000 in profit sharing paid within 12 months.

FAQ

Frequently Asked Questions

What causes cash flow problems for concrete subcontractors?
Three causes: schedule of values that underbills early phases (formwork, rebar, pump mobilization), overhead rate in bids below actual SG&A, and AR not being actively collected. Most concrete contractors have all three simultaneously. SPM fixes all three in the first 60 days.
How do I fix the SOV to improve concrete cash flow?
Submit your own SOV draft before the GC's version. Include mobilization at 5–8% of contract value, formwork and rebar as separate line items billable at installation, pump mobilization as its own line, and concrete placement priced by pour. After signing, the SOV structure is fixed for the life of the project.
What overhead rate should a concrete contractor use?
Concrete contractors at $1M–$3M typically run 12–16% overhead. At $3M–$6M, 10–14%. At $6M–$12M, 10–13%. Calculate yours: pull SG&A from last 12 months, divide by revenue. If the result is more than 3 points above what is in your bids, update the bid model immediately.
How much uncollected AR does a typical concrete sub have?
Most concrete contractors who have never run an active AR audit have 60–90 days of billings sitting at 45+ days uncollected. At $4M in annual revenue that is $65,000–$100,000 in a receivable backlog. SPM collects it in the first 30 days of engagement — money already earned, never followed up on.
Josh Luebker
Josh Luebker
Fractional CFO · The Construction CFO

Former commercial construction PM and master electrician. Managed 150+ projects totaling $300M+. Now fractional CFO for subcontractors doing $1M–$12M through Sulphur Prairie Management. About Josh →  |  LinkedIn →

Ready to Fix the Cash Problem?

A free call with Josh takes 30 minutes. Bring your last P&L and current bank balance.

Schedule a Free Call →
Related Resources
Billing
Concrete SOV Front-Loading
How to structure the SOV before signing
CFO Services
Best CFO for Concrete Contractors
Concrete-specific financial systems
Job Costing
Labor Cost Per Yard Tracking
The other concrete margin variable
Cash Flow Crisis
Profitable But No Cash
Why the P&L and bank account disagree
Tools
Overhead Rate Calculator
Find your real overhead rate
Cash Flow Crisis
MCA Loan Trap
When concrete cash flow problems escalate to MCA debt
The Construction CFO
Cash Flow ConcreteSOV Front-LoadingBest CFO ConcreteSchedule a CallJosh@ConstructionCFO.net
© 2026 SULPHUR PRAIRIE MANAGEMENT · SULPHUR ROCK, AR
0