CIVIL AND EXCAVATING JOBS LOOK PROFITABLE. THE ACCOUNT IS STILL EMPTY.
Civil and Excavating subcontractors have no cash left for reasons specific to how the work is built and billed, on jobs that are making money. The three that cost the most in this trade are below, taken from civil and excavating contractor research. Most are at 75 to 90 days from finishing work to holding the money, and 45 days is achievable.
Cash and profit are measured on different clocks. Your profit and loss records revenue when you invoice and costs when you incur them, while the bank account only knows what cleared. Labour goes out weekly and collects 45 to 90 days later, minus retention. That distance is what a growing, profitable civil and excavating company funds out of pocket, and it widens as you grow. The specific things that widen it in this trade are what the rest of this page is about.
IN THEIR OWN WORDS.
You don't get paid if he doesn't get paid. You just know he's going to tell you he didn't get paid.
Mike Holt forums, contract issues thread
These GC's are trying to hire you but want you to chase the money.
Mike Holt forums, billing thread
WHERE IT LEAKS OUT.
Bills from people who don't call to collect get paid last. Payroll taxes are trust funds. Paying them late brings penalties, personal liability exposure and bonding damage. When they fall behind, the cause is a cash problem further up the line.
WHAT MOVES MARGIN IN THIS TRADE.
The Mobilization Gap
Civil work spends cash up front. You pay fuel, bond premiums, moves and payroll 60 to 90 days before pay app 1 clears. On a $2M job that's $150K to $200K spent before the first dollar comes back. Fix: put mobilization on its own schedule-of-values line and bill it on pay app 1.
The Retainage Stack
Every job holds 5 to 10 percent. At a 7 percent net margin before taxes, a 10 percent hold ties up the whole job profit until release. Three jobs at once tie up six figures, and payroll is due every week. Fix: track retainage as its own receivable class, put releases on the calendar, and size your working capital to fund it.
Iron That Bills Nothing
Ownership cost keeps going whether the machine is parked or working. A CAT 330 that isn't moving costs roughly $200 per day, and industry idle rates are near 30 percent. A bid without an ownership rate gives that money away. A $7.1M civil contractor recovered $779K in total to date once it tracked equipment cost.
DAYS SALES OUTSTANDING.
Ninety days is weak, 45 is the target, 30 is strong. Nothing else moves cash faster.
| Position | Days | What it means |
|---|---|---|
| Weak | 90 days | Roughly three months of work funded out of your own pocket. |
| Target | 45 days | You can get here on the days you control. Bill on time, send complete paperwork, and follow up in week two. |
| Strong | 30 days | Takes work every month. It's the cheapest money you can get. |
Moving from 90 days to 45 frees roughly annual revenue divided by 365, times 45 days. At $4M that's about $493,000. At $8M it's about $986,000. That money costs no interest and needs no bank. So we fix billing and collections before we talk about financing.
CIVIL AND EXCAVATING BENCHMARKS.
Civil and Excavating subcontractors at $1M to $5M net 7 percent, against the CFOS net profit target, set at your trade's net profit average at your revenue plus 3.5 points, never below 10 percent, before taxes. The working capital target is 13 percent of annual revenue, and the monthly close should finish by day 10 so the numbers can still change a decision.
