JOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOSUBCONTRACTOR FINANCEOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQOREJOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOSUBCONTRACTOR FINANCEOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQOREJOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOSUBCONTRACTOR FINANCEOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQOREJOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOSUBCONTRACTOR FINANCEOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQORE
The Construction CFOSchedule a Free Call

TL;DR: SPM provides fractional CFO services for structural steel contractors doing $1M-$12M in commercial new construction. Job costing by connections per crew per day and tons erected in ControlQore, overhead rate including all real costs, WIP reporting monthly, and AR collection system that clears the backlog in 30 days. Most structural steel clients find their first month's AR collection exceeds the annual SPM fee.

Structural Steel

The CFO for
Structural Steel Contractors.

You bid by the connections. Your margin lives or dies in the field every week. If you find out a job is losing money at closeout it is too late. We make it visible in week two.

Published: May 2026  ·  Updated: May 2026
23-28%
Target Gross Margin
Week 2
When Variance Is Visible
60 Days
Full Onboarding
5 hrs/mo
Owner Time Required
The Problem

What Kills Structural Steel Margins

Most structural steel do not know a job is losing money until it is done. The estimate looked right. The crew was working. But the actual cost per connections per crew per day and tons erected was running over estimate for three weeks and nobody knew it until closeout.
01

Fabrication Deposit Cash Flow Gap

Your steel fabricator requires 40% deposit on a $280,000 structural package before fabrication begins. That is $112,000 out the door before a single piece of steel is on site. The SOV has one structural steel line item at 100% billed upon completion. You fund the fabrication deposit from operating cash for 8-12 weeks before the first billing event.

02

Connection Count Variance Not Tracked

You estimated bolted connections at 14 per crew-day on standard moment connections. Field conditions - access restrictions, elevation, connection type variability - produced 9 connections per crew-day on the upper floors. That 36% production shortfall was not visible until closeout because connection count was not tracked by elevation and connection type.

03

Erection Sequence Changes Not Billed

The GC revised the erection sequence twice to accommodate other trades. Each revision required crane repositioning, re-rigging, and schedule adjustment. Those crane hours - $4,200 in additional cost - were not submitted as change orders because the sequence changes were verbal and undocumented.

Prevailing wage note: Structural Steel contractors doing DOT and municipal work have additional fringe benefit requirements of $12-$20/hour above base wages. SPM calculates separate overhead rates for prevailing wage and private work. Prevailing wage CFO services →

The Fix

How SPM Builds the Structural Steel Financial System

SPM builds ControlQore cost codes aligned to the structural steel estimate structure so actual cost per connections per crew per day and tons erected posts weekly against estimated cost. Variance is visible in week two.
ControlQore cost codes by connection type and elevation. Bolted connections by type, welded connections by type, deck installation by SF, column erection by piece - by building zone and elevation. Actual connections per crew-day posts weekly against estimated rate. Upper-floor production variance visible before it compounds.
Fabrication deposit SOV billing. SPM negotiates fabrication deposit as a separate SOV line item billed at deposit payment - not at steel delivery. A $112,000 fabricator deposit should produce a $112,000 billing event at deposit. Most structural steel contractors absorb the fabrication float. SPM eliminates it.
Erection sequence change documentation. Written GC notice within 24 hours of verbal sequence change request. Crane time and crew cost impact calculated at time of request. Cost proposal submitted before sequence change is implemented. Most sequence changes are billable as directed changes.
Pricing

What It Costs

Priced by last 12 months of revenue. ControlQore billed separately at ~$100/month per $1M. SPM does not handle payroll.

RevenueCore FinancialExecutive Financial
Under $1M$1,900$2,900
$1M-$3M$2,600$3,600
$4M-$6M$3,800$5,500
$7M-$9M$5,100$6,900
$10M-$12M$6,100$8,500
$13M+QuotedQuoted
FAQ

Frequently Asked Questions

What does a CFO for structural steel contractors do?
A fractional CFO for structural steel contractors builds the job costing structure aligned to the estimate - cost codes by connections per crew per day and tons erected - so actual cost per unit is visible weekly against estimated cost per unit. They manage WIP reporting, overhead rate calculation, billing calendar, and monthly cash flow. The result: you know which jobs are winning and which are losing before you cannot do anything about it. All SPM clients run on ControlQore - purpose-built for construction job costing at $1M-$12M.
What overhead rate should structural steel contractors use?
Structural Steel Contractors at $1M-$3M typically run 13-15% overhead. The most common errors are missing owner compensation at market rate and not including equipment depreciation or vehicle fleet in the SG&A calculation. Each of those understates the real overhead rate and underprices every bid.
What are the most common cash flow problems for structural steel contractors?
Three consistent problems: schedule of values that underbills early phases which are the most cash-intensive work, overhead rate below actual because ownership costs are not fully included, and AR sitting uncollected at 45+ days with no follow-up system. Most structural steel contractors have all three simultaneously. SPM fixes all three in the first 60 days.
What gross margin should structural steel contractors target?
Structural Steel Contractors at $1M-$12M in commercial new construction typically target 23-28% gross margin. Margin below the lower end of that range usually indicates a markup problem, an overhead rate understatement, or job costing that is not capturing all direct costs accurately.
Do you handle payroll?
No. SPM does not handle payroll. We have vetted partners including prevailing wage and Davis-Bacon integrations that connect directly with ControlQore at additional cost.
How long does onboarding take?
60 days. We migrate your books to the start of your last taxable year, build your ControlQore job costing structure, and get you fully operational in two months.
What software do you use?
All SPM clients run on ControlQore - purpose-built for construction job costing and WIP reporting at $1M-$12M. More capable than QuickBooks for job costing, more affordable than Sage. We set it up and manage it.
Do I need clean books to start?
No. Most clients come with messy books and no job costing. That is exactly what onboarding is for.
Josh Luebker
Josh Luebker
Fractional CFO · The Construction CFO

Former commercial construction project manager and master electrician. Managed 150+ projects totaling $300M+. Now fractional CFO for commercial subcontractors doing $1M–$12M through Sulphur Prairie Management. About Josh →  |  LinkedIn →

Ready to Fix the Numbers?

A free call takes 30 minutes. Bring your last P&L and current bank balance.

Schedule a Free Call →
Related Resources
Benchmark
Overhead Rate Benchmarks
What overhead % looks like at every revenue level
Benchmark
Structural Steel Gross Margin
Gross margin benchmarks for structural steel contractors
Software
ControlQore vs QuickBooks
Why ControlQore handles assembly line trades better
Decision
When Do I Need a CFO?
The signals that tell you it is time
Framework
The Assembly Line Test
Why structural steel contractors pass the assembly line test
Entity
Best CFO for Subcontractors
The full SPM service overview
The Construction CFO
Overhead Rate BenchmarksControlQore vs QuickBooksSchedule a CallJosh@ConstructionCFO.net
© 2026 SULPHUR PRAIRIE MANAGEMENT · SULPHUR ROCK, AR
0