UNDERGROUND UTILITIES

PIPE PROCUREMENT IS A UTILITY CASH PROBLEM.

QUICK ANSWER

Underground utility contractors order pipe 8 to 12 weeks before the trench opens. The pipe reaches the yard before the site is ready, installation happens weeks later, billing triggers after installation, and collection comes 45 to 60 days after that. From deposit to cash can run 120 to 150 days. On a $300K pipe package that's $300K out the door for five months before it comes back, and on two jobs at once you're carrying $600K of permanent float.

The procurement to payment timeline on a utility job is longer than almost any other trade. That's a structural feature of underground work rather than anybody's fault: the material has to be on site before the trench opens and it gets paid for long after it's buried. That also means the float requirement is predictable, and a predictable requirement is a fundable one. A utility contractor who has calculated the figure can size a line of credit against it and stop treating every large pipe order as an emergency.

BY JOSH LUEBKERPublished 2026-08-06Updated 2026-08-07
THE DEFINITION

WHAT IT MEANS.

Pipe procurement float is the money an underground utility contractor has tied up between paying for pipe and fittings and collecting the billing for them, and it routinely runs 120 to 150 days.

WHAT WE SEE IN THIS BUSINESS

WHERE THE CASH GETS BURIED.

01

Long lead pipe orders

Large diameter pipe, ductile iron, and specialty fittings can run 8 to 16 week lead times. The order goes in before site prep is complete and sometimes before the contract is fully executed, and the deposit goes out immediately. By the time the trench opens, that cash has been out for two to three months with no billing event in sight.

02

Delivery before the installation window

Pipe gets delivered when the supplier can deliver, not when the crew is ready to install it. Lining delivery up with the trench schedule is hard, so material often sits in the yard or on the laydown area for 2 to 4 weeks before installation starts. That's 2 to 4 more weeks of carrying the full material cost with no billing event triggered.

03

Installation based billing structure

Most utility SOVs are built around installation milestones: pipe placed, tie ins complete, and testing complete. The billing event triggers after installation, which leaves the whole procurement and staging period uncompensated from a billing standpoint. Without stored materials billing, the only way to recover procurement cost is to get the work installed first.

04

Fittings and appurtenances add up

Main pipe is visible and easy to track. Fittings, couplings, valves, service saddles, and appurtenances usually disappear into a miscellaneous material line. On a $1M utility job, fittings and appurtenances can run $80K to $120K, ordered early, delivered piecemeal, and billed at installation completion, so tracking them separately is the difference between billing $400K and billing $520K in month two.

THE ARITHMETIC

WHAT IT LOOKS LIKE IN DOLLARS.

The float math

On a $300K pipe package, the 120 to 150 day distance between deposit and collection means $300K is out for roughly five months. Run two jobs like that at once and $600K is permanently tied up in float. That is a capital requirement, and it has to be funded before the job starts.

What the line of credit has to cover

Model the full procurement float: deposits to pipe suppliers plus fittings and delivery costs, less any upfront mobilization billing recovery. On a $4M utility contractor running two simultaneous jobs with $300K in pipe orders each, the minimum line of credit capacity for procurement alone is $600K. Most utility contractors are badly underbanked against their real float requirement.

HOW SPM FIXES IT

THREE THINGS WE CHANGE.

A stored materials line in every utility SOV

Every utility contract with real pipe value should carry a stored materials line item negotiated before contract execution. The line covers pipe, fittings, and appurtenances at delivery rather than at installation. That one SOV negotiation compresses the wait from delivery to billing from 60 to 90 days down to 5 to 10 days on major deliveries.

Track fittings and appurtenances on their own stored materials schedule

Don't let fittings disappear into a miscellaneous line. Build a stored materials schedule that itemizes pipe by size and quantity, fittings by type, and appurtenances by item. Photograph everything at delivery, then tag and stage it in a designated laydown area, so each delivery becomes a billable event instead of a miscellaneous charge absorbed into an installation milestone 6 weeks later.

Map procurement payments into the 13 week cash forecast

Every pipe order has a deposit date and a delivery date, and every delivery triggers a possible billing event. Map those dates against the billing collection schedule in the 13 week forecast. Anywhere procurement payment beats billing collection by more than 30 days is a line of credit draw candidate, and the draw gets made ahead of the shortfall rather than after the bank account runs low.

$10.7M+
Client AR Recovered Since 2023
48
Active Trade Specializations
60 DAYS
Average Onboarding Time
PRICING

FLAT MONTHLY FEE. NO SURPRISES.

Three tiers, priced by your trailing twelve month revenue. Which one you're in depends on how much of the work you want off your desk. No hourly billing, no payroll, and no add-ons.

Last 12 months revenueMonthly fee
Up to $1M$1,900 to $2,900
$1M to $3.5M$2,600 to $3,900
$3.5M to $6.5M$3,800 to $5,700
$6.5M to $9.5M$5,100 to $7,100
$9.5M to $12.5M$6,100 to $8,500
$12.5M to $15.5M$7,400 to $11,000
$15.5M to $18.5M$9,400 to $13,500
$18.5M+Quoted individually

Range reflects the three tiers below. Which one you're in depends on how much of the work you want off your desk. No payroll. No hidden line items.

Core

You stop guessing.

You get the CFO work. Job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a meeting every month that ends in decisions rather than a report.

Your bookkeeper keeps doing the books.

Executive

You stop touching the books.

Everything in Core, and we run the bookkeeping and the controllership as well. Nobody in your office is answering coding questions or chasing a reconciliation at month end.

We do the books. No payroll.

Strategic

Every job shows its margin while it's still running.

Everything in Executive, plus the job costing and WIP platform set up, loaded with your cost codes, and managed for you every month. You never have to learn it.

We do the job costing.

COMMON QUESTIONS

FREQUENTLY ASKED.

Utility contractors order pipe and fittings 8 to 12 weeks before installation, pay deposits or the full invoice on delivery, and then wait through the installation phase and a 45 to 60 day GC payment cycle before collecting. The total distance from deposit to collection routinely runs 120 to 150 days on large pipe packages. That's a pure capital requirement, and it has to be funded rather than absorbed.
Three moves. Negotiate stored materials billing into the SOV so pipe can be billed at delivery and not at installation. Structure the SOV with a mobilization and material recovery line billable at contract start. Then build a 13 week cash forecast that maps procurement payments against expected billing collection dates so the line of credit gets drawn before the shortfall hits.
A stored materials schedule listing pipe sizes, quantities, linear footage, unit values, and storage location. Photos showing the pipe tagged and staged. A certificate of insurance covering the stored value. For off site storage, a bonded warehouse agreement listing the GC as an additional insured, and GC approval secured before the first billing event.
Model the full procurement float: deposit payments to pipe suppliers plus fittings and material delivery costs, less any upfront contract mobilization billing recovery. On a $4M utility contractor running two simultaneous jobs with $300K in pipe orders each, the minimum line of credit capacity for procurement alone is $600K. Most utility contractors are significantly underbanked against their real float requirement.
Three tiers, and which one you are in depends on how much of the work you want off your desk. Core is where you stop guessing: job costing built against the way you estimate, a 13 week cash forecast, monthly WIP, and a monthly meeting that ends in decisions, while your bookkeeper keeps doing the books. Executive is where you stop touching the books, because we run the bookkeeping and the controllership as well. Strategic is where every job shows its margin while it is still running, because the job costing and WIP platform is set up and managed for you. No payroll. No scope gaps.
WHAT THIS TIES INTO
Josh Luebker, The Construction CFO
Josh Luebker
FRACTIONAL CFO · THE CONSTRUCTION CFO

Former commercial project manager and master electrician: 150+ projects worth $2.1B combined, from $50,000 to $300M. Now fractional CFO to commercial subcontractors.

HOW MUCH OF YOUR CASH IS SITTING IN PIPE?

Bring your open pipe orders and your current line of credit balance. We will calculate your real procurement float and tell you what the line needs to be.

You don't hire a CFO because it's safe, you do it because the real risk isn't having one.
Book a 20 minute diagnostic

20 minutes. No sales pressure. We will tell you exactly what's broken before we talk about anything else.

OR START WITH THE WORKBOOKS. NO CALL NEEDED.