Skip to main content
JOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQORESUBCONTRACTOR FINANCECFOSBILLING VELOCITYNET PROFIT JOB COSTINGCASH FLOWWIP REPORTINGFRACTIONAL CFOOVERHEAD RATEPAY APP BILLINGAR RECOVERYCONTROLQORESUBCONTRACTOR FINANCECFOSBILLING VELOCITYNET PROFIT
THE CONSTRUCTION CFO BOOK A FREE CALL
WIP REPORTING · JOB PROFITABILITY · CONSTRUCTIONCFO.NET

HOW TO READ A WIP SCHEDULE IN CONSTRUCTION.

QUICK ANSWER

A WIP schedule tracks five things per job: contract value, total estimated cost, percent complete, revenue earned, and costs incurred. The math between those five columns tells you whether each job is overbilled or underbilled, and whether it is trending to make or lose money. Most contractors have a WIP schedule because their surety requires it. Almost none of them can explain what every number means or how to use it to manage a job.

The WIP schedule is not an accounting report. It is a management tool. Read correctly it tells you which jobs are bleeding before the month-end P&L shows the damage. Read wrong — or not read at all — it is just a form you fill out for your bonding agent.

BY JOSH LUEBKER Published: June 2026 Updated: June 2026
5
Columns in Every WIP
Contract value, estimated cost, percent complete, earned revenue, cost incurred. Every WIP decision flows from these five numbers.
Overbilled
Most Common WIP Position
Most subcontractors are overbilled — they have collected more than they have earned. That looks like cash strength. It is actually a liability.
30%
When to Review
The 30% completion mark is when WIP review produces actionable data. Earlier is noise. Later is too late to recover margin.
THE FIVE COLUMNS
What Each Number Means and Where It Comes From

Contract Value — the total amount you are contracted to receive. This is fixed unless a change order modifies it.

Estimated Cost to Complete — your current best estimate of total cost to finish the job. This is the number PMs must update monthly. If it is not being updated, your WIP is wrong.

Percent Complete — calculated as costs incurred to date divided by total estimated cost. Not units installed. Not schedule progress. Cost.

Revenue Earned — contract value multiplied by percent complete. This is what you have actually earned, regardless of what you have billed.

Costs Incurred — actual job costs charged to date. Direct labor, material, equipment, subcontractors.

OVERBILLED VS UNDERBILLED
The Number That Tells You Your Real Cash Position

Overbilled means you have billed more than you have earned. Revenue earned is $400,000 but you have billed $460,000. The $60,000 difference is a liability — you owe that work to the owner. It is not cash you have earned. Many subcontractors mistake overbilling for cash strength. It is not.

Underbilled means you have earned more than you have billed. Revenue earned is $400,000 but you have only billed $340,000. The $60,000 is a receivable you have not invoiced yet. This is where lost cash hides. If your WIP shows consistent underbilling, you have a billing discipline problem — not a performance problem.

PROFIT FADE
The Warning Sign Most Contractors Miss Until It's Too Late

Profit fade is when the estimated gross margin on a job decreases from month to month as the job progresses. A job that estimated 26% gross margin at contract is showing 19% at 60% complete. That 7-point fade has to be explained. Did labor run over? Was there a scope change that was not captured? Is the cost-to-complete estimate wrong?

The WIP schedule catches profit fade before the job finishes. That is the only time there is anything left to do about it. By the time the final billing hits, the margin is locked in. Review at 30% complete is mandatory. Review at 60% complete is critical.

01
UPDATED COST-TO-COMPLETE MONTHLY
The single most important input in any WIP schedule is the PM's current estimate of what it will cost to finish the job. If that number is not being updated monthly — based on actual field conditions, not the original estimate — the WIP is producing false data. Every WIP review starts with cost-to-complete.
02
PERCENT COMPLETE BASED ON COST NOT UNITS
Percent complete must be calculated as costs incurred divided by total estimated cost. Not units installed. Not schedule progress. Not owner opinion. Cost-based percent complete is what makes the earned revenue calculation meaningful. Anything else produces a number that looks right and means nothing.
03
REVIEW AT 30% AND 60% COMPLETION
The 30% review is where margin compression is first visible and still recoverable. The 60% review is the last point where crew redeployment, change order capture, or billing acceleration can materially change the outcome. Both reviews require the PM, the CFO, and the owner in the same room looking at the same number.
04
SEPARATE OVERBILLING FROM CASH
Overbilled positions on the WIP are liabilities — not cash strength. CFOS tracks overbilling separately from AR so the owner sees their true cash position. A business that is consistently overbilled looks cash-rich until the jobs finish and the liability converts. That is when the cash crisis hits.
$2.1M+
Client AR Recovered Since 2023
18
Active Trade Specializations
60 DAYS
Average Onboarding Time
PRICING

FLAT MONTHLY FEE. NO SURPRISES.

Two tiers based on trailing 12-month revenue. No hourly billing. No payroll. No add-ons.

RevenueCore FinancialExecutive Financial
Under $1M$1,900/mo$2,900/mo
$1M–$3M$2,600/mo$3,600/mo
$4M–$6M$3,800/mo$5,500/mo
$7M–$9M$5,100/mo$6,900/mo
$10M–$12M$6,100/mo$8,500/mo
$13M+QuotedQuoted
What's Included →
COMMON QUESTIONS

FREQUENTLY ASKED.

Contract value, estimated cost to complete, percent complete, revenue earned to date, and costs incurred to date. Percent complete is calculated as costs incurred divided by total estimated cost. Revenue earned is contract value multiplied by percent complete. The difference between revenue earned and amount billed is your overbilled or underbilled position.
Overbilled means you have collected more cash than you have earned. Revenue earned is $400,000 but you have billed $460,000. The $60,000 is a liability — work owed to the owner that has not been performed yet. Many contractors mistake overbilling for cash strength. It is a short-term position that reverses when the job finishes.
Profit fade is when the estimated gross margin on a job decreases from month to month. A job estimated at 26% margin showing 19% at 60% complete has faded 7 points. The WIP review identifies the cause — labor overrun, missed change order, bad cost-to-complete estimate — while there is still job left to recover it on. By the time the job closes, fade is permanent.
CFOS serves commercial subcontractors doing $1M to $12M. Core Financial starts at $1,900 per month. Executive Financial starts at $2,900 per month. Onboarding takes 60 days.
Core Financial includes ControlQore setup, job costing aligned to your estimates, full-service bookkeeping, and bank reconciliations. Executive Financial adds monthly CFO advisory meetings, controllership, and strategic accountability. No payroll. No scope gaps.
Josh Luebker
Josh Luebker
Fractional CFO · The Construction CFO

Former commercial construction PM and master electrician. 150+ projects, $300M+ in volume. Now fractional CFO for commercial subcontractors doing $1M–$12M through Sulphur Prairie Management. About Josh →  |  LinkedIn →  |  CONTROL Book →

RELATED
CFOS Module
Job Profitability System
The CFOS module built around WIP accuracy and real-time job margin visibility
WIP
Cost to Complete Is Always Wrong
Why the most important WIP input is almost always inaccurate — and how to fix it
Bonding
WIP Reporting for Bonding
What surety underwriters actually look at in your WIP and how to present it correctly
CFOS SYSTEM CONNECTIONS
SYSTEM SPINE
Run on CFOSCash Control SystemJob Profitability System
RELATED
Profitable But No CashBilling Velocity SystemMCA Loan Trap
PROOF
Civil MCA Payoff Case StudyElectrical AR RecoveryFractional CFO Services

30 MINUTES. FREE.
NO SALES PRESSURE.

We will show you exactly what your WIP is telling you before we talk about anything else.

BOOK A FREE DIAGNOSTIC CALL →

OR SEE YOUR NUMBERS FIRST → FREE CEO REPORT TOOL
THE CONSTRUCTION CFO
Run on CFOSCash Control SystemFractional CFOSchedule a CallCONTROL Book
© 2026 SULPHUR PRAIRIE MANAGEMENT · SULPHUR ROCK, AR
0
Josh Luebker, The Construction CFO
JOSH LUEBKER
FOUNDER & CFO

Master electrician and former project manager, 150+ projects and $2.1B+ in commercial work. Now runs the numbers for subcontractors instead of standing on the job site.

LinkedIn About
Stewart Bohrer, The Construction CFO
STEWART BOHRER
VP OF OPERATIONS

Keeps the system running day to day: job costing, WIP, monthly financial reviews, and the follow-through between calls. Josh handles onboarding.

LinkedIn About
LinkedIn YouTube About Run on CFOS