JOB LOOKED FINE. NOW IT'S NOT. WHAT HAPPENED.
Early in a job you can't see much of the cost. The phases that have started look fine. The phases that haven't started show zero actual cost, so every job looks better than it will at 60% complete. Something happened between this looks good and we're underwater. Every job that turns has a cause, and the cause decides the fix.
There are four causes, and one of them is yours. Labor went over estimate on a phase. Material cost moved after the bid. Change order work got built and never billed. Or early overbilling is correcting now that production has caught up to it. Two of those are cost problems and two are timing problems, and they need opposite responses. A job total tells you nothing about which one you have. A phase-level cost report and a WIP schedule together tell you inside 20 minutes.
Rather talk it through first? Book a 20 minute call. Nothing gets sold on this call.
Want Josh to check your own numbers? Financial Health Snapshot, $1,500 one time. Your last 12 months read against your trade's benchmarks, with a 60 minute readout.
WHAT IT MEANS.
An apparent mid-job loss is either a true cost overrun on one phase or a billing timing problem. A phase-level job cost report read against the WIP schedule tells you which one you have.
You can only fix it while the job is still in progress. Find the cause at closeout and you've paid full price for a lesson. Find the same cause at 40% complete and you can still change crew size, a purchase order, or an invoice that goes out this week.
FIND THE SOURCE BEFORE CLOSEOUT.
Labor hours exceeded the estimate
This is the most common cause. The crew is 15% to 25% over estimated hours on one phase. Early in the job the extra hours are few and the total variance looks manageable. By 50% to 60% complete the overrun has grown until it's using up margin that was bid on other phases. A phase-level labor report shows it while you still have time to adjust crew size or production approach.
Material cost escalation
You bid the job when material costs were lower. By the time the purchase orders went out, prices had moved. Delivery had fuel surcharges. Steel or copper went up. Supply chain delays forced you to buy from secondary vendors at higher prices. Every dollar of material cost above bid comes out of gross margin, and nothing offsets it.
Change order work completed and not billed
This one looks like a loss when there's no loss. T&M and change order work gets completed in the field and verbally approved. The cost posts to the job, and the formal billing waits. The job cost report then shows a large apparent overrun. It's really $40K to $80K of unbilled change order work recorded as cost with no revenue against it. Pull the change order log and compare it to what has been formally invoiced.
Early overbilling correcting
Early in the job, billing was ahead of percent complete. That's standard practice to front-load cash flow. Now the work is catching up to that billing, and the apparent margin is correcting downward. The cost never changed. The overbilling is reversing as earned revenue catches up, and the job may still be on margin. The WIP schedule tells you which it is.
WHAT IT LOOKS LIKE IN DOLLARS.
A job that looks unprofitable often has $30,000 to $80,000 of change order work completed and verbally approved but never formally billed. The cost is real, and nobody has asked for the revenue yet. Compare the change order log with formal billing and you almost always find it.
A labor phase that is 25% over at 40% complete is a decision you can still make this week. A job total that is 8% over is a number you can only worry about. That's why you code cost by phase.
THE TABLE IS AT RUN ON CFOS.
With 45 day payment terms, an overbilling of 6, 8 or 10 percent of contract value leaves any job shorter than 15 months behind the work done in cash.
Source: Run On CFOS, Overbilling against payment terms, updated October 17, 2026. The full table and the data are published there. Cite as: Run On CFOS. Overbilling against payment terms. 2026. Sulphur Prairie Operations, LLC. https://runoncfos.com/overbilling-and-45-day-terms. CC BY 4.0.
TWO REPORTS. BOTH NEEDED.
Pull actual against estimated cost for every phase or cost code on the job. Sort by variance percentage, with the largest negative variance at the top. The phase with the biggest overrun against its own estimate is where the margin went. A labor phase that is 25% over at 40% complete tells you what to fix. A job total that is 8% over tells you nothing you can act on.
Calculate percent complete as cost to date divided by estimated total cost. Earned revenue is contract value times percent complete. Then compare it with billed to date. If billed to date is well above earned revenue, the job is overbilled and the early billing is correcting itself. If billed to date is well below earned revenue, you're underbilled and that invoice needs to go out immediately. The WIP tells you whether the apparent loss is a cost problem or a billing problem, and each one takes a different fix.
Finding the cause takes two reports. Most contractors in the $1M to $12M range either don't have them or don't produce them monthly. Once you have both, the cause is almost always obvious inside 20 minutes of review. SPM does the job cost and WIP review every month for every client, so the answer comes before closeout.
FLAT MONTHLY FEE. NO SURPRISES.
Three tiers, priced by your trailing twelve month revenue. Which one you're in depends on how much of the work you want off your desk. We don't bill by the hour, and we don't do payroll. The one-time onboarding fee is in the table.
Built for subs doing $1M to $12M. Above $12.5M we quote.
| Last 12 months revenue | Core | Strategic | Platinum | One-time onboarding |
|---|---|---|---|---|
| Under $1M | $1,900 | $3,100 | $3,300 | $2,500 |
| $1M to $3.5M | $2,600 | $4,100 | $5,300 | $4,500 |
| $3.5M to $6.5M | $3,800 | $5,900 | $8,300 | $6,000 |
| $6.5M to $9.5M | $5,100 | $7,600 | $11,800 | $7,500 |
| $9.5M to $12.5M | $6,100 | $8,900 | $14,900 | $9,000 |
| Above $12.5M | Quoted | Quoted | Quoted | Quoted |
The onboarding fee covers migrating your books back to the start of your last taxable year and getting you fully operational in 60 days. It's billed once, with your first invoice. It's the same for all three tiers, and it moves with your revenue band. Your first month is prorated, and your monthly engagement starts on the first of the first full month.
Just want the setup? Onboarding only is the same onboarding work with no monthly service after it, one time, at the onboarding fee plus $2,000. Start a monthly engagement later and $2,000 counts toward it. It starts at $4,500, and the price for every band is on the pricing page.
The three tier columns are the whole price. Which one fits depends on how much of the work you want off your desk. No payroll. No hidden line items. The onboarding fee is right here in the table.
- Online software only: QuickBooks, Sage, Viewpoint and similar. No VPN or hosted desktop.
- Not in any tier: payroll, pay applications, collections on receivables.
- Pricing valid through 2027.
CFO work. Your own bookkeeper keeps doing the books.
We build your plan every month. Your team does the work.
You get the CFO work: job costing built to match the way you estimate, a 13 week cash forecast, WIP every month, and a monthly meeting that ends with decisions.
Your bookkeeper still does the books.
Core, plus bookkeeping and bank reconciliations, plus job costing and WIP software set up and managed for you. Use your own online accounting software or we supply it, one price.
We build the plan, track it and adjust it every month.
We only work with trade subcontractors. We know what to look for, and we fix problems while they're still small. Everything in Core, plus the bookkeeping and bank reconciliations done for you, and the job costing and WIP software set up, loaded with your cost codes, and managed every month. Use your own online software, or move to ours and we pay for it.
Our team does the bookkeeping and the reconciliations. We don't do payroll.
Strategic, plus a controller who handles payables and receivables the way an in-house controller would. You approve every payment.
We manage the money side for you, every week.
Everything in Strategic, plus our team does the controller work. We handle your bills and receivables the way an in-house controller would: we call vendors, pay the bills and keep the accounting current. We plan the cash flow first, and you approve every payment because it is your money.
Our team does the payables and receivables. We don't do payroll, pay applications or collections.
