The percentage of completion method recognizes construction revenue and gross profit in proportion to how much of a contract is complete -- calculated using the cost-to-cost formula: costs incurred to date divided by total estimated costs. The result drives WIP reporting, over/underbilling calculations, and balance sheet presentation. Getting the percentage wrong -- usually because total estimated cost is stale -- produces misleading financials that lenders, bonding companies, and buyers will catch.

THE CONSTRUCTION CFO SCHEDULE A FREE CALL
Financial Literacy — Construction Accounting

Percentage of Completion Method Explained.

The percentage of completion method recognizes revenue and gross profit as work progresses on a contract -- not when cash is collected and not when the job closes. Most commercial subcontractors use it because it matches revenue to the period the work was performed. The critical variable is percent complete, calculated by dividing costs incurred to date by total estimated cost. If that estimate is stale, everything downstream is wrong.
Schedule a Free Call →
Published: May 2026Updated: May 2026
The Core Concept

How Percentage of Completion Actually Works.

Revenue recognition under percentage of completion follows the work, not the billing. If a $1.2M job is 35% complete at month end, you recognize $420K in revenue for that period -- regardless of what you've billed or collected. The WIP schedule reconciles that recognized revenue against actual billings to produce the over/underbilling position for the balance sheet.

The Formula: % Complete = Costs Incurred to Date ÷ Total Estimated Costs × 100
Recognized Revenue = Contract Value × % Complete
Recognized GP = (Contract Value − Total Estimated Costs) × % Complete

A Concrete Example.

A $900K electrical contract with total estimated cost of $720K (20% gross margin). At month end, $288K in costs have been incurred.

% Complete: $288K ÷ $720K = 40%

Recognized Revenue: $900K × 40% = $360K

Recognized GP: ($900K − $720K) × 40% = $72K

If billed $320K: Underbilled by $40K (contract asset on balance sheet)

That $40K underbilling isn't a cash problem yet -- it's a future billing right. But it means the P&L is showing $360K in revenue while only $320K has been invoiced. The WIP schedule is what reconciles those two numbers and keeps the balance sheet honest.

Where It Goes Wrong

Three Ways Percentage of Completion Gets Distorted.

Most percentage of completion errors don't come from bad math. They come from a stale estimate in the denominator -- total estimated cost that hasn't been updated to reflect current conditions on the job.

01

Stale Total Estimated Cost

The job started at $720K estimated cost. Labor has been running hot. The current cost-to-complete is actually $800K -- but nobody updated the estimate. The denominator is wrong, so the percentage is wrong, so the recognized revenue is wrong. The job looks 40% complete when it's really 36%.

02

Costs Not Posted to the Job Timely

AP invoices sitting in the inbox for two weeks before they're posted. Timesheets entered monthly instead of weekly. If costs aren't in the system, the numerator is understated -- which overstates the percentage complete and overstates recognized revenue. Overbilling that isn't real.

03

Percent Complete Estimated From Billing, Not Cost

Using billing percentage as a proxy for completion percentage is backwards. You billed 40% because that's what the schedule of values allowed -- not because you're 40% done. Overbilled jobs look further along than they are. Underbilled jobs look behind. The WIP is wrong in both directions.

WIP Reporting

How Percentage of Completion Drives the WIP Schedule.

The WIP (Work In Progress) schedule is the monthly reconciliation of every active job's percentage complete against its billed amount. It's the document that turns percentage of completion accounting into something a banker, bonding agent, or buyer can evaluate.

JobContract ValueEst. Total CostCosts to Date% CompleteRev. RecognizedBilled to DateOver/(Under)
Job A$900K$720K$288K40%$360K$320K($40K)
Job B$1.4M$1.1M$770K70%$980K$1.05M$70K
Job C$600K$480K$96K20%$120K$118K($2K)

Job B is overbilled by $70K -- a liability on the balance sheet. This isn't necessarily a problem if the overbilling is intentional front-loading, but if it's because percent complete was overstated, the remaining job will show a loss at completion. Bonding companies see this immediately on a WIP review.

What Lenders and Bonding Companies Look For.

Every bank, surety, and serious buyer of a construction company will request a WIP schedule. They're looking for three things: whether your percentage complete estimates are supportable, whether your overbilling position is within acceptable range, and whether your total estimated costs are updated monthly or frozen from job start.

What a Bondable WIP Schedule Requires

Percent complete estimated by field supervision monthly -- not assumed from billing
Total estimated cost updated whenever scope, labor productivity, or material cost changes
All costs posted to the job within the period they were incurred -- no lagging AP
Over/underbilling reconciled to the balance sheet -- not just tracked in a spreadsheet
WIP schedule reviewed and signed off monthly by the owner or CFO

SPM produces a bondable WIP schedule monthly for all clients through ControlQore. The schedule updates automatically as costs post and billing is entered -- no manual assembly required.

Common Questions

FAQs -- Percentage of Completion.

The percentage of completion method is an accounting method where revenue and gross profit are recognized in proportion to how much of a contract is complete. If a $1M job is 40% complete, you recognize $400K in revenue and the associated gross profit in that period -- even if you haven't billed or collected $400K yet. It's the standard method for long-term construction contracts under GAAP and ASC 606.

The most common method is cost-to-cost: divide costs incurred to date by total estimated costs. If you've spent $300K on a job estimated to cost $800K total, you're 37.5% complete. Multiply that by the contract value to get recognized revenue. The key variable is total estimated cost -- if that number is wrong, your revenue recognition is wrong.

Under percentage of completion, revenue is recognized as work progresses throughout the project. Under the completed contract method, all revenue and profit are deferred until the job is substantially complete. Most commercial subcontractors use percentage of completion because it better matches revenue to the period the work was performed -- and it's required under GAAP for companies with annual revenue over $25M.

Overbilling (billings in excess of costs) occurs when you've billed more than the percentage of completion warrants. Underbilling (costs in excess of billings) occurs when you've billed less. Both appear on the balance sheet via the WIP schedule and affect how lenders, bonding companies, and buyers evaluate financial health.

The WIP schedule reconciles every active job's percentage complete against its billed amount. Jobs that are overbilled show as a liability. Jobs that are underbilled show as an asset. The net position tells you whether your company's reported revenue is backed by actual work performed. Bonding companies, banks, and buyers all require a WIP schedule.

Josh Luebker — Fractional CFO, The Construction CFO
Josh Luebker
FRACTIONAL CFO · THE CONSTRUCTION CFO

Former commercial construction project manager and master electrician. Managed 150+ projects totaling $300M+ including Google data centers, military bases, hospitals, and high-rises. Now fractional CFO for commercial subcontractors doing $1M–$12M through Sulphur Prairie Management. About Josh →  |  LinkedIn →

Related Resources
Education
Job Costing Explained
The foundation that makes percentage of completion work
Problem Diagnosis
Profit Fade Warning Signs
How a stale cost estimate causes fade you can't see coming
Software
ControlQore vs QuickBooks
Why QuickBooks can't produce a bondable WIP schedule natively
CFO Services
Fractional CFO for Subcontractors
Monthly WIP production and percentage of completion management
Company Value
What Your Company Is Worth
Why buyers require WIP history before they'll make an offer

GET A BONDABLE WIP SCHEDULE EVERY MONTH.

One call. We'll show you what percentage of completion reporting looks like through ControlQore and what it takes to get there in 60 days.

Schedule a Free Call →
THE CONSTRUCTION CFO
Job Costing Explained Profit Fade Warning Signs ControlQore vs QuickBooks CFO Services Schedule a Call Josh@ConstructionCFO.net
© 2026 SULPHUR PRAIRIE MANAGEMENT · SULPHUR ROCK, AR
0
Josh Luebker, The Construction CFO
JOSH LUEBKER
FOUNDER & CFO

Master electrician and former project manager, 150+ projects and $2.1B+ in commercial work. Now runs the numbers for subcontractors instead of standing on the job site.

LinkedIn About
Stewart Bohrer, The Construction CFO
STEWART BOHRER
VP OF OPERATIONS

Keeps the system running day to day: job costing, WIP, monthly financial reviews, and the follow-through between calls. Josh handles onboarding.

LinkedIn About
LinkedIn YouTube About Run on CFOS