THE INVOICE WAS RIGHT. IT CAME BACK ANYWAY.
Four things cause most rejected pay applications, and you can tell them apart in about an hour. One, the percentages don't agree with what the general contractor's own field staff saw. Two, the billing period fell outside the cut-off in the subcontract. Three, the work was done on a verbal and there's no priced change order behind the line. Four, the lien waiver, certified payroll or insurance certificate that had to go with the application didn't. Only the first is an argument about the work. The other three are paperwork, and you can fix each one before the next application goes out. Find out which one you have before you escalate. If you take a paperwork problem to a project executive, you lose credibility you'll want later for a real dispute.
A disputed application is worse than a late one because it stops the clock. A late one only extends it. A late invoice is still an invoice, and it's still aging toward a day you can call about it. A disputed one is worth nothing until somebody agrees on the amount. Every day you disagree, your own cash pays for somebody else's project. And your AR aging still lists money that may never come in at that figure.
Rather talk it through first? Book a 20 minute call. Nothing gets sold on this call.
Want Josh to build it with you? Cash Flow Intervention, $497 one time. A 90 minute session that fills in the 13 week forecast with your real numbers and makes the billing changes on the call.
WHAT IT MEANS.
A disputed invoice in construction is a pay application the general contractor has refused or reduced while agreeing that some work was performed. It's a different problem from a late payment. A late payment is an argument about the date. A disputed invoice is an argument about the amount, and the clock on collection doesn't start until the amount is settled.
Almost everything that decides a dispute months later was created or missed the week the work happened. That's a daily report with a photograph, a written direction with a number on it, and an email confirming a verbal instruction. None of it feels urgent that week. It's what a reasonable reader looks at when two accounts of the same events disagree. The contractors who win these arguments kept better records while nobody was arguing.
FOUR CAUSES, AND ONLY ONE IS A REAL ARGUMENT.
The percentages don't agree with what the field observed
You billed a phase at seventy percent. The general contractor's superintendent walked it and called it fifty. This is the only one of the four that's a dispute about the work, and evidence decides it. Daily reports, dated photographs and quantities installed against the schedule of values settle it. Your own foreman's second opinion doesn't. If the schedule of values was front-loaded at the start of the job, expect this argument when the billing gets ahead of the work anybody can see. Expect to lose it if real early cost never justified the loading.
The application missed the general contractor's cut-off
Most subcontracts state a day of the month the application has to be in by. That day is tied to the general contractor's own billing to the owner. Miss it by a day and the whole application waits a full cycle. Your office reads that as a rejection, and it's a calendar problem. It's the most common cause on this list and the cheapest to get rid of. Take the cut-off from the subcontract at setup and put it in the billing calendar. Then nobody has to remember it at month end.
There's no priced change order behind the line
Your crew did extra work on a verbal instruction, and the application includes the cost with no executed change order behind it. The general contractor has nothing to certify, so the line comes off. Now your job reports a loss on a phase, and the real cause was a billing failure. Your subcontract almost always entitles you to a written direction before you proceed. If the work is already done, write a change order letter. State the instruction, who gave it, when, and what it cost. That letter is the document that recovers the money.
The compliance documents didn't travel with it
The application needs conditional lien waivers for you and your lower tiers, certified payroll on public work, and an insurance certificate that hasn't lapsed. On a lot of projects a system refuses the application before a person reads it, because one of these is missing or out of date. Nobody at the general contractor thinks of this as a dispute. To them the application was never complete, so it can go unresolved for weeks. Track vendor compliance beside the billing and it stops happening.
WHAT IT LOOKS LIKE IN DOLLARS.
Get the reason in writing before you respond to it. A reduced line with no comment is usually a percentage disagreement. A whole application returned is usually a cut-off or a compliance failure. If nobody will put a reason in writing, take the conversation a level up.
Pull the daily reports, photographs, quantities, the change order log and every email around the instruction. Do it before you make an argument. The argument you can support is often smaller than the one you want to make, and it costs you to find that out in the meeting.
Split the application. Bill everything nobody is arguing about now, and keep the contested line separate. Contractors routinely hold a whole application back over one disputed line and finance the difference themselves for a month. You could always collect the undisputed part, so don't make it wait on the rest.
Check the notice periods for claims, and the preliminary notice and lien deadlines where you work. Both depend on your jurisdiction and both are shorter than people assume. Do this step while the dispute is young. The deadline doesn't pause while you negotiate, and a right you've let expire gives you no leverage.
THREE CONTROLS, ALL OF THEM CHEAP.
Read it off the subcontract the week the job is awarded and give it to whoever produces the applications. Set one recurring reminder for each active job. That takes ten minutes a job and removes the most common cause on the list. Your billing calendar also stops depending on one person's memory during the busiest week of the month.
Get a number, a date and a signature before anybody builds extra work. The person who enforces it is whoever assigns the crew, so this is a dispatch rule. It removes cause three entirely. It also removes the argument where your own superintendent's memory is the only evidence you have.
Track waivers, certified payroll and insurance certificates for you and your lower tiers, and check the expiry dates before an application goes out. Cause four produces the longest silences, because the general contractor has nothing to respond to. Closing the books and reconciling by the tenth helps here too. An application built from a closed month has figures nobody has to defend twice.
FLAT MONTHLY FEE. NO SURPRISES.
Three tiers, priced by your trailing twelve month revenue. Which one you're in depends on how much of the work you want off your desk. We don't bill by the hour, and we don't do payroll. The one-time onboarding fee is in the table.
Built for subs doing $1M to $12M. Above $12.5M we quote.
| Last 12 months revenue | Core | Strategic | Platinum | One-time onboarding |
|---|---|---|---|---|
| Under $1M | $1,900 | $3,100 | $3,300 | $2,500 |
| $1M to $3.5M | $2,600 | $4,100 | $5,300 | $4,500 |
| $3.5M to $6.5M | $3,800 | $5,900 | $8,300 | $6,000 |
| $6.5M to $9.5M | $5,100 | $7,600 | $11,800 | $7,500 |
| $9.5M to $12.5M | $6,100 | $8,900 | $14,900 | $9,000 |
| Above $12.5M | Quoted | Quoted | Quoted | Quoted |
The onboarding fee covers migrating your books back to the start of your last taxable year and getting you fully operational in 60 days. It's billed once, with your first invoice. It's the same for all three tiers, and it moves with your revenue band. Your first month is prorated, and your monthly engagement starts on the first of the first full month.
Just want the setup? Onboarding only is the same onboarding work with no monthly service after it, one time, at the onboarding fee plus $2,000. Start a monthly engagement later and $2,000 counts toward it. It starts at $4,500, and the price for every band is on the pricing page.
The three tier columns are the whole price. Which one fits depends on how much of the work you want off your desk. No payroll. No hidden line items. The onboarding fee is right here in the table.
- Online software only: QuickBooks, Sage, Viewpoint and similar. No VPN or hosted desktop.
- Not in any tier: payroll, pay applications, collections on receivables.
- Pricing valid through 2027.
CFO work. Your own bookkeeper keeps doing the books.
We build your plan every month. Your team does the work.
You get the CFO work: job costing built to match the way you estimate, a 13 week cash forecast, WIP every month, and a monthly meeting that ends with decisions.
Your bookkeeper still does the books.
Core, plus bookkeeping and bank reconciliations, plus job costing and WIP software set up and managed for you. Use your own online accounting software or we supply it, one price.
We build the plan, track it and adjust it every month.
We only work with trade subcontractors. We know what to look for, and we fix problems while they're still small. Everything in Core, plus the bookkeeping and bank reconciliations done for you, and the job costing and WIP software set up, loaded with your cost codes, and managed every month. Use your own online software, or move to ours and we pay for it.
Our team does the bookkeeping and the reconciliations. We don't do payroll.
Strategic, plus a controller who handles payables and receivables the way an in-house controller would. You approve every payment.
We manage the money side for you, every week.
Everything in Strategic, plus our team does the controller work. We handle your bills and receivables the way an in-house controller would: we call vendors, pay the bills and keep the accounting current. We plan the cash flow first, and you approve every payment because it is your money.
Our team does the payables and receivables. We don't do payroll, pay applications or collections.
